Simmons v. Ocean Causeway

21 A.D. 30, 47 N.Y.S. 360
CourtAppellate Division of the Supreme Court of the State of New York
DecidedOctober 15, 1897
StatusPublished
Cited by16 cases

This text of 21 A.D. 30 (Simmons v. Ocean Causeway) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Simmons v. Ocean Causeway, 21 A.D. 30, 47 N.Y.S. 360 (N.Y. Ct. App. 1897).

Opinion

Bradley, J.:

The action is founded on an alleged breach of the contract by the defendant. •

The plaintiffs by their complaint charge:

• 1. That they, having nearly completed the work under the first or-causeway contract, were, on or about June 29, .1895, prevented by the defendant from' proceeding further in the fulfillment of it, and that the defendant had failed to make payments to which the plaintiffs were entitled.

. 2. That the plaintiffs had also nearly completed the work under the other or bridge contract when they, at the same time) were wrongfully prevented from proceeding further with it, and that the defendant refused to pay them.

3. That the plaintiffs performed extra work upon the causeway, for which they are entitled to recover.

• 4. That they also performed extra work upon the drawbridge^ .

The alleged breach of the contracts on the part of the defendant mainly arises out of the fact that, during the progress of the work, and on June 29, 1895, the defendant, by its president, addressed and sent to the plaintiffs a telegram, of which the following is a copy: “Your men quit work Thursday; have instructed Smith to finish road under your contract.” The name subscribed to the telegram was Geo. 0. Band, who was such officer. Thomas D. Smith was the engineer who had been selected by the defendant. This was Saturday, and thereafter the plaintiffs did no more work upon the causeway job) but the defendant, on the second day of July, took charge of it and proceeded with its completion. For that purpose the men and tools theretofore in the service of the plaintiffs were employed by the defendant. This taking possession of the work to finish it, the defendant alleges, was pursuant to the provision of the contract, to the effect that in case the plaintiffs failed to supply a sufficiency of materials or workmen the defendant should have the power, on three days’ notice, to provide them, complete the work and deduct the expense from the amount of the contract. The defendant also alleges that the expense of its accomplishment exceeded the amount of the contract price remaining unpaid to the plaintiffs. ■

Whether or not the defendant was, by any fault of .the plaintiffs, [33]*33justified in taking the work from them under that provision of the contract, was a controverted question of fact upon which it must be assumed that the jury found against the defendant, and although they would have been fairly warranted in finding otherwise, we think the conclusion of the jury in that respect was permitted by the evidence. It is true that the time specified in the contract for the completion of the work had expired before the defendant took the control of it, and if nothing chargeable to the defendant had intervened to permit the extension of the time of its performance by the plaintiffs, a different question would have been presented for consideration, since, in view of the purpose and contemplated use of the causeway, time may be deemed as of the essence of the contract. But after the making of the causeway contract, and early in August, 1894, the plaintiffs, in the expectation of proceeding at once with the work, were prepared with shanties, men and implements on the ground to do so, but were- denied the right to commence by notice from the defendant that legal obstacles then prevented the beginning of the work, which, it seems, were occasioned by a failure of the defendant to obtain the right of way through the meadow in the town of Hempstead.. This was not accomplished so as to enable the plaintiffs to commence the work before September third, when they entered upon its performance. The consequences of this interruption and delay were the expenses of the transportation of the unemployed workmen and their wages, and the loss of a portion of the better season for the work, which it was more difficult to perform in the late autumn and winter in that place. It seems that in time of high tide the plaintiffs were unable to work on the meadow lands there. The evidence of one of the plaintiffs tends to prove that at an interview with Mr. Rand, the president of the defendant, on the subject of the delay in the commencement of the work, the latter said that it was unavoidable, and that the plaintiffs should have an allowance of time to enable them to get the work done as soon as they could. There is also evidence on the part of the plaintiffs to the effect that a further obstructive delay in the work was occasioned by some of the directors of the defendant during its progress. The jury were permitted by evidence to conclude- that the defendant was not justified by lapse of time in taking the work from the [34]*34plaintiffs. Following the conclusion of the jury, that this was done by the defendant in violation of the contract, there arose upon the evidence questions of fact relating to the extent of the work which the plaintiffs had performed under the contract, including such as was denominated extra work. ' The trial proceeded, and the case wag submitted to the jury upon the theory that the plaintiffs were entitled to recover the amount of money expended by them upon the work, less the amount paid to them by the defendant thereon..

Of course the amount chargeable and expended under the contracts could not exceed the compensatory sums provided for by them, nor is it claimed that the expense incurred in the performance of the work specified in the'contracts exceeded such sums; but including the expenditures for extra work on the causeway, the evidence on the part, of the plaintiffs tended to prove that they amounted to $15,519.16, of Which the sum of $4,660 was- expended for what the plaintiffs’ evidence tended to prove was extra- work.. The. plaintiffs received from the defendant on account of their work on the causeway $8,241.16... They also claim, and evidence on their-part was given tending to prove, that the drawbridge- was substantially completed by them prior to July 2, .1895, and that, they had expended $1,300 in its construction, and having received on account of that work $700, they claimed the right to the allowance - of the further sum of $500, the residue of the contract,price for the construction of the bridge, and the further sum of $72.40 for extra work. In addition to this, the plaintiffs claim by their evidence that the expenses incurred by them, in consequence of the delay to which they were subjected as before mentioned in the outset, were $650, of which amount they were paid $340 by the defendant on that account,

The matter of extra work which the ¡ffaintiffs claimed to have performed, was the subject of controversy at the trial. And the evidence on the part of the defendant was to the effect that the value of the work done and materials furnished by the plaintiffs upon the causeway was only $9,448, and on the drawbridge $860, and that the defendant expended in completion of the causeway upwards of $5,000 after taking possession of the work, and that the work to be done to. complete the bridge and remedy the. defects would' cost $1,020. Of the sum so expended by the defendant upon the causeway, $3¡,600 were paid to Murray and De Mott, who in May, [35]*351895, by contract made with the plaintiffs, agreed to put three inches of loam and three inches of gravel upon the roadway for the sum. of $3,600. This contract was made with the assent of the president, Eand, and with the understanding that Murray and De Mott were to receive their pay directly from the defendant. They commenced the performance of this contract before, and completed it after the defendant took the control of the work from the plaintiffs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paul Hardeman, Inc. v. Arkansas Power & Light Company
380 F. Supp. 298 (E.D. Arkansas, 1974)
Henderson v. Cochran
100 S.E.2d 910 (Supreme Court of Georgia, 1957)
General Supply & Construction Co. v. Goelet
149 A.D. 80 (Appellate Division of the Supreme Court of New York, 1912)
Taylor v. Goelet
142 A.D. 467 (Appellate Division of the Supreme Court of New York, 1911)
Davenport v. Prentice
126 A.D. 451 (Appellate Division of the Supreme Court of New York, 1908)
Barnum v. Williams
115 A.D. 694 (Appellate Division of the Supreme Court of New York, 1906)
Niles v. Sire
46 Misc. 321 (New York Supreme Court, 1905)
Pitts v. Davey
40 Misc. 96 (New York Supreme Court, 1903)
Day v. Eisele
76 A.D. 304 (Appellate Division of the Supreme Court of New York, 1902)
O'Dwyer v. Smith
38 Misc. 136 (Appellate Terms of the Supreme Court of New York, 1902)
McAveney v. Pasquini
23 A.D. 120 (Appellate Division of the Supreme Court of New York, 1897)
Gilroy v. Loftus
22 Misc. 105 (Appellate Terms of the Supreme Court of New York, 1897)
Simmons v. Ocean Causeway of Lawrence
47 N.Y.S. 1148 (Appellate Division of the Supreme Court of New York, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
21 A.D. 30, 47 N.Y.S. 360, Counsel Stack Legal Research, https://law.counselstack.com/opinion/simmons-v-ocean-causeway-nyappdiv-1897.