Kennedy v. McKone

10 A.D. 88, 41 N.Y.S. 782, 75 N.Y. St. Rep. 1179
Appellate Division of the Supreme Court of the State of New York·Decided November 15, 1896·Published·Cited by 14 cases

Opinion

Barrett, J.:

1. While quite agreeing with the learned referee that a contract existed between McKone and Robinson, and that that contract included the tiling, plastering and papier mache work, we cannot concur in the view that the contract price was $1,200. The undisputed evidence seems to establish the contrary. According to the defendant McKone’s own testimony, the only limit put upon the cost was that it should not exceed $1,500. The same thing is shown by the defendant’s Exhibit E. This was a card on which Robinson first wrote the details of the work which he was to do: At the foot of it, in McKone’s handwriting,are the words, “Will not run over $1,500; ” and the latter admits that he placed these words there as a memorandum of what occurred at the interview with Robinson. This evidence is absolutely undisputed except by Robinson, who claimed terms more favorable to himself, a claim which the referee rightly disregarded. It is thus proved that Robinson agreed to do the work for a sum not to exceed $1,500. The legal effect of such an agreement was that Robinson became entitled to recover the reasonable value of the work done, with the limitation that such recovery could not exceed $1,500. The case is not, as the plaintiffs claim, analogous to Carll v. Spofford (45 N. Y. 61). There the plaintiff refused to put a limit on the cost of his work, but merely made a “ rough guess ” that it would not exceed a figure named. Here Robinson definitely fixed a sum which the cost should not exceed, and he cannot recover more than the sum so named.

The contract price was not affected by the recital in the order of August 30, 1894, that it was but $1,200. The price was not fixed at the interview which occurred on that day, but at the previous interview between McKone and Robinson. The contract price was, as we have seen, to be about $1,200, but not to run over $1,500. The words “ my contract price of $1,200,” were merely words of description. And they misdescribed the contract, of rather failed to describe it fully and accurately. That is all. The only purpose of the order was to define the amount which McKone should pay the plaintiffs, and the legal effect of it so far as these plaintiffs are concerned is precisely the same, in all respects, as if the words “ my contract price,” had been omitted.

2. We are also unable to agree with the learned referee that the [93]*93plaintiffs became substituted as contractors in the place of Robinson. The order of August 30,1894, does not effect any such substitution. There is only one possible construction to be put upon it, and that is that it gives the plaintiffs, as sub-contractors under Robinson, the security of McKone’s responsibility up to the amount of $1,200. If the plaintiffs became chief contractors in Robinson’s stead, they would be entitled to receive-Robinson’s compensation. But even if we should assume, contrary to the fact, that Robinson’s compensation on August 30, 1894, was fixed at $1,200, it would still remain true that the plaintiffs were not absolutely entitled to this sum. They were to receive the “ amount of their bill,” which was not to exceed ” the sum of $1,200. The learned referee admits that, on its face, this is what the order means, but says that, nevertheless, the evidence as a whole shows that such a substitution was effected. After a careful perusal of his opinion, and examination of the evidence, we are unable to see that he refers to, or that the record discloses, any fact or circumstance permitting such an inference. In fact, the testimony of McKone and his attorney, Enstis, shows that the question of the retention of Robinson or the substitution of the plaintiffs was directly discussed, and the former course deliberately chosen. This was done, as they testify, both because McKone knew Robinson and wanted him to superintend the work, and because the latter believed that there was still a profit in the contract for him after paying the plaintiffs. McKone, from friendly motives, was desirous that Robinson should make any such possible profit.

The effect of this, however, is not what the referee and counsel for the plaintiffs have assumed, viz., that the plaintiffs were entitled to recover their full $1,200 from McKone in any event, leaving the latter to look to Robinson if the work was not completed. McKone has completely protected himself from such a result by the condition in the order that the plaintiffs’ right to receive the amount of their bill from him (within the limit of $1,200) shall be dependent upon the completion of the work. McKone was not in the first place liable to the plaintiffs at all. Robinson hired them, and they would have had to look to him throughout but for the order. There is no promise on McKone’s part, express or implied, to pay them anything except as specified in the order. They must recover in accordance with its terms, or not at all. The condition made in this paper puts [94]*94the plaintiffs, for the purposes of this action, in much the same position as if they had been chief contractors. They could not, like a chief contractor, be held by McKone to liability for breach of contract ; but when they took the initiative and sought to recover their bill, it became incumbent upon them to show fulfillment of the contract, either by themselves or by Eobinson. If McKone had not elected (as his answer shows he did) to finish the work as agent for the contractor, the plaintiffs would have lost all right to compensation. As McKone, however, elected to finish the work and charge up the cost, we think the referee did right in deducting the value of this uncompleted work and awarding plaintiffs the balance. When a contractor fails to complete and the owner does so for him, the former is debited with the amount of the latter’s necessary expense, on the theory that the owner is acting as the agent of the contractor; that such expense is incurred in order to entitle the contractor to the contract price, and that the contractor would have had to incur the same expense if he had done his duty. The plaintiffs stand in no better position here. They can recover under their order only what Eobinson could have recovered if he had proceeded with the work — always, however, within the $1,200 limit. If McKone was justified, as he clearly was, in doing the work which Eobinson’s contract called for, but which was not done, either by Eobinson or the plaintiffs, he can properly deduct the value of that work from the value . of the work which was actually done, and the balance is the just meed of the plaintiffs’ recovery.

3. From the foregoing, it results that the plaintiffs should not have been nonsuited on their second cause of action. McKone was liable to Eobinson in the sum of $1,500 if the work done was of that value. Eobinson assigned away his right to recover $1,200 of this amount, but remained entitled to the other $300 if sufficient work was done. The plaintiffs’ assignment covers certain services rendered by Eobinson and materials furnished by him. For each day of labor and pound of material Eobinson was entitled to recover from McKone, with the limitation, originally, that the whole sum should not exceed $1,500 •— with the limitation, after the execution of the order, that such recovery should not exceed $300, if the plaintiffs earned their full $1,200. This difference, between the amount of money earned by the plaintiffs and the full amount earned under [95]*95the contract, Robinson remained entitled to recover after the order, and the plaintiffs, in so far as they have succeeded to Robinson’s rights, must have judgment for the amount so due.

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Kennedy v. McKone, 10 A.D. 88, 41 N.Y.S. 782, 75 N.Y. St. Rep. 1179 (N.Y. Ct. App. 1896).

10 A.D. 88 (Kennedy v. McKone) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Seybolt v. Baber
97 A.2d 907 (Court of Appeals of Maryland, 1953)
Hershey Farms, Inc. v. State
202 Misc. 105 (New York State Court of Claims, 1952)
Higby v. Hooper
221 P.2d 1043 (Montana Supreme Court, 1950)
Bates v. St. Anthony's Church
196 N.W. 638 (Nebraska Supreme Court, 1923)
Salerno v. Vogt
78 Misc. 64 (New York County Courts, 1912)
McNally v. Rowan
101 A.D. 342 (Appellate Division of the Supreme Court of New York, 1905)
Armstrong v. Chisolm
91 N.Y.S. 299 (Appellate Division of the Supreme Court of New York, 1904)
United Press v. . New York Press Co.
58 N.E. 527 (New York Court of Appeals, 1900)
Volkmar v. Third Avenue Railroad
28 Misc. 141 (Appellate Terms of the Supreme Court of New York, 1899)
United Press v. New York Press Co.
35 A.D. 444 (Appellate Division of the Supreme Court of New York, 1898)
Simmons v. Ocean Causeway
21 A.D. 30 (Appellate Division of the Supreme Court of New York, 1897)
Wyckoff v. Taylor
13 A.D. 240 (Appellate Division of the Supreme Court of New York, 1897)