Meehan v. Williams

2 Daly 367
New York Court of Common Pleas·Decided June 15, 1868·Published·Cited by 6 cases

Opinion

By the Court.—Daly, F. J.

The evidence fully justified the finding of the referee, that the conveyance of the premises to John A. Williams was not bond fide, but was made with intent to defraud the plaintiff and defeat his lien. The plaintiff had a right to impeach its validity in this action. He had an incipient lien when this transfer was made, which became absolute, under the Act of May 5, 1863, when the notice was filed with the county clerk. The Act of 1863 provides that incumbrancers may be made parties in the action or proceeding, to enforce the lien. John A. Williams, to whom this fraudulent conveyance was made, comes under the denomination of an incumbrancer, and as such was made a party; and the plaintiff, having established in the action that he was a creditor of the fraudulent grantor to the extent of $866, was entitled to have this conveyance declared void, so far as it interposed any obstacle to the enforcement of his lien (2 Rev. Stat. 137, § 1; Clute v. Fitch, 25 Barb. 432; Van Etten v. Hurst, 6 Hill, 311). The Act of 1863 declares that the court may determine the rights of all the parties, and that such judgment or decree shall be made as to the rights and equities of the several parties among themselves, and as against any owner, as may be just (§§ 2, 5, 7). This is ample to confer upon the court, in this action, the power to give relief against this conveyance, and to declare it, as against the rights of the plaintiff, to be fraudulent and void; and the conveyance, having been adjudged to be fraudulent and void, it becomes unnecessa[373] ry to consider whether there is any thing in the objection raised to the constitutionality of the provision in the Act of 1863, which declares that the lien shall become absolute, notwithstanding any sale, transfer, or incumbrance made after the commencement of the work or the furnishing of the materials.

The plaintiff testified that he could have completed the work by the 15th of February, but for a delay arising from the impossibility of plastering on account of the weather. Several of the defendants’ witnesses testified that the delay in the plastering could have been avoided by putting up stoves in the building and keeping up fires to dry the walls, and Williams and his wife swore that the plaintiff said to them that he would do so. This the plaintiff denied, and gave a very different version of what passed between him and Mr. and Mrs. Williams upon the subject, while one of his witnesses, a plasterer, testified that fires will not have much effect in drying walls. The evidence upon this head being conflicting, we must assume that the referee found that the testimony on the part of the plaintiff was the more reliable, and that testimony was to the effect that both Williams and Mrs. Williams assented to the delay. The plaintiff swore that he told Williams that it was impossible to do the plastering on account of the weather; that if he insisted upon having it done it would tumble when a thaw came, and that Williams answered that he did not want it to tumble on him—in which connection it may be remarked that the plaintiff swore that Williams told him when he ordered the extra work to be done, that he owned the premises, and that Williams never told him at any time that his wife was the owner of the property. The plaintiff testified, further, that he told Williams, that he, the plaintiff, would be obliged to wait until the weather would permit, and that Williams replied that the weather might change, and he must get at it as quick as he could, making no objections to the delay. When further interrogated upon this point, the plaintiff stated that there were two carpenters present, whom he named, when this conversation occurred, and that Williams said that he wanted the plaintiff to get on as soon as Tie oovM, and that Mrs. W. [374] said that she did not want to move into the house before it was. perfectly dry. We have here the fact that neither jie nor she-, made any objections to the delay, and in addition a much more important circumstance, in respect to which there was no conflict, that is, that Williams, in the presence of his wife, paid the plaintiff the fourth installment ten days after the tinqe limited in the contract for the completion of the building. Williams swore that he never agreed with the plaintiff to extend the time, that his wife never authorized him to do so or to modify the. contract, and her affidavit was read to the same effect. But this was rather swearing to a conclusion than controverting the specific testimony from which a different inference was. drawn. He did swear that he did not tell the plaintiff that if the work could not be done in cold weather he did not want him to do it; but this was contradicting what was sworn to by the plaintiff; and the referee believed the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Meehan v. Williams, 2 Daly 367 (N.Y. Super. Ct. 1868).

2 Daly 367 (Meehan v. Williams) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Murray v. Gerety
11 N.Y.S. 205 (City of New York Municipal Court, 1890)
Gilbert Car Manufacturing Co. v. Mann
3 N.Y. St. Rep. 301 (New York Supreme Court, 1886)
Gross v. Daly
5 Daly 540 (New York Court of Common Pleas, 1875)
Burt v. Saxton
4 Thomp. & Cook 109 (New York Supreme Court, 1874)
Shute v. Hamilton
3 Daly 462 (New York Court of Common Pleas, 1871)
Schneider v. Hobein
41 How. Pr. 232 (New York Court of Common Pleas, 1871)