Smith v. Gugerty

4 Barb. 614
CourtNew York Supreme Court
DecidedNovember 8, 1848
StatusPublished
Cited by42 cases

This text of 4 Barb. 614 (Smith v. Gugerty) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Gugerty, 4 Barb. 614 (N.Y. Super. Ct. 1848).

Opinion

By the Court, Strong, P. J.

The counsel for the defendant in error said truly on the argument, that it is the province of the court, on a writ of error, to decide questions of law, and not questions of fact upon which there has been a conflict of evidence. Hence it is the usual, and where it is possible, the more correct course, when it is intended to review cases tried before referees, to embody in the record a statement of the facts proved before, and found by them, as a substitute for a special verdict. But it often happens that the questions of law raised on the trial do not relate so much to the facts themselves, as to the admission, rejection, or import of the testimony adduced or offered to prove them. In such cases it is proper and indeed necessary, to set forth in the record so much of the evidence as may be requisite to point and elucidate the questions of law. It is probably for that reason, and possibly for the additional reason that it is difficult to separate the evidence which may, from that which does not have a bearing upon the points of law raised for our determination, that the parties in this cause have spread upon the record a détailed statement of all the testimony adduced by them on a protracted trial before the referees. It has subjected us to the necessity of giving to the whole an elaborate, and to those not practically acquainted with the trade of a mason necessarily a difficult, examination. We ought not, however, to regret the labor, if it was requisite to do justice to the parties.

This is one of the eases which are so frequently before our courts on building contracts. The parties to such contracts apparently differ most widely in reference to their obligations. The builder seems to suppose that while he adheres generally to the plan which is prescribed for him, he is at liberty to disregard minute and unimportant particulars, while the owner imagines that a departure from such plan in any respect, although it may be the effect of accident, and of no possible injury to him, exon[620]*620erates him from the obligation to make any payment which is in terms made dependant upon the full performance of the contract. Both are wrong. Parties should undoubtedly be exact in the fulfilment of their agreements, even to the smallest particulars, and if they wilfully or carelessly depart from any one of them they should incur the penalty, however severe it may be.. But if a party while acting in good faith, and with a determination to do what he has contracted to do, should unintentionally, and without any negligence, happen in some trifling and unimportant matter to vary or depart from the terms of his agreement, the law is not so severe and exacting as to deprive him of all compensation. It ever regards the substantial rights of parties, but overlooks trivial and unimportant matters. De minimis non curat lex. Were it otherwise no builder, who, as in the case under consideration, makes his compensation dependant upon the full completion of his work, according to a specification containing avast number of minute directions, could obtain payment for his labor. No builder ever does or can comply with every minute requisition. A brick, a stone, a nail, a shingle or a board may have some slight defect which might have been almost, and perhaps entirely imperceptible, until it had been fixed in its place, and it had become impossible to remove it; or as I said' on the argument, it may happen that a minute portion of mortar among a large mass, may not have been mixed precisely in the required proportions, and the difficulty may not be discovered until it is too late to change it. Such things will constantly occur unless men should become more perfect in their powers of perception and discrimination than they are at present. If there is an honest effort to perform the contract according to the letter, and it is substantially fulfilled, the builder should be entitled to receive the reward of his labor, although he may not (as the architect employed in this case has certified) have in every instance complied with its terms “literally in every punctilio.” A substantial compliance, without any intentional variation, should in all cases be considered as a full performance of a condition, whether precedent or subsequent.

[621]*621The work in this case was not completed until long after the time specified for that purpose in the contract. That would be fatal to Gugerty’s recovery, unless the extension of time was caused 'by Smith’s acts, or was assented to by him. Undoubtedly a party cannot take advantage of the nonperformance óf a condition, if such non-performance has been caused by himself. (The Mayor, &c. of New- York v. Butler, 1 Barb. S. C. R. 325.) . It seems from the evidence that soon after the commencement of work Smith requested Gugerty to dig and wall a cellar in an old house adjoining the proposed new house. The architect says that “ this was not thought of at the time of making the specification. It was a secondary consideration. That Smith, after the specification was done, made a counter cellar under the bid building, and that he did not remember hearing any thing about such cellar until after Gugerty commenced his work on the building.” He also says that they “ increased the thickness of the wall between the old building and the yard of the new.” There were also various other additions to the work mentioned in the specifications; all these required additional time. Taking the old and the new work together, Gugerty never agreed to perform the whole within the time specified in the contract. An extension of the work called for and justified an extension of the time. But if there had been no additional labor, the protraction of the time would not, if assented to by Smith, have impaired Gugerty’s claim. It is not necessary that the assent should be in writing, or that it should be established by positive testimony. It may be inferred from the circumstances, (Jewell v. Schroeppel, 4 Cowen’s Rep. 564, and cases there cited. Ladue v. Seymour and Wood, 24 Wend. 60.) Now in this case there are many circumstances from which such assent may be inferred. The work proceeded after the expiration of the prescribed time (October 20th, 1839) under Smith’s own eyes, and superintendence, and often by his express direction. The third and fourth instalments whicli became due, the third to some extent, and the fourth principally, for work done after that date, were subsequently paid by Mr. Smith. And although the architect was [622]*622under examination several times, it nowhere appears that Smith expressed any dissatisfaction at, or was in any way opposed to the delay. If he intended to take advantage of such delay, he should on every account have signified his intention to do so, promptly at the time. It is too late to raise the objection now.

There were unquesliotiably many variations in the work from the specification which was signed at the same time with the contract. Some portions of the work were omitted. Some were altered : and there were considerable additions. A right was reserved to Smith, in the specification, to require such omissions, alterations and additions, as he might think proper. It appears clearly, from the evidence, that the plans originally drawn were subsequently changed. There is no written evidence as to the extent, or particulars. The architect testified that he drew new plans when they had alterations to make after the buildings were commenced; that in any case where he required an alteration, it was by the direction of Mr. Smith, without which he did nothing. Some of the changes were absolutely necessary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stewart v. Spalding
23 Haw. 502 (Hawaii Supreme Court, 1916)
Standard Dry-Kiln Co. v. Ellington
90 S.E. 564 (Supreme Court of North Carolina, 1916)
Torrey v. . Cannon
88 S.E. 768 (Supreme Court of North Carolina, 1916)
Healer v. Inkman
146 P. 1172 (Supreme Court of Kansas, 1915)
Headley v. Cavileer
82 A. 908 (Supreme Court of New Jersey, 1912)
Mortimer v. Dirks
107 P. 184 (Washington Supreme Court, 1910)
Holland Torpedo Boat Co. v. Nixon
61 Misc. 469 (New York Supreme Court, 1908)
Cook v. Stimson Mill Co.
83 P. 419 (Washington Supreme Court, 1906)
Parker v. Brown House Co.
44 S.E. 807 (Supreme Court of Georgia, 1903)
Chicago & Alton Railroad v. Lewandowski
190 Ill. 301 (Illinois Supreme Court, 1901)
Hellyer v. People
58 N.E. 245 (Illinois Supreme Court, 1900)
McFadden v. Block
29 Misc. 398 (New York Supreme Court, 1899)
Laycock v. Parker
79 N.W. 327 (Wisconsin Supreme Court, 1899)
Weisbrod v. Dembosky
25 Misc. 485 (Appellate Terms of the Supreme Court of New York, 1898)
Anderson v. Todd
77 N.W. 599 (North Dakota Supreme Court, 1898)
Stillman v. Wickham
76 N.W. 1008 (Supreme Court of Iowa, 1898)
D'Andre v. Zimmermann
17 Misc. 357 (Appellate Terms of the Supreme Court of New York, 1896)
Grannis & Hurd Lumber Co. v. Deeves
25 N.Y.S. 375 (New York Supreme Court, 1893)
People v. Wilson
16 N.Y.S. 583 (New York Supreme Court, 1891)

Cite This Page — Counsel Stack

Bluebook (online)
4 Barb. 614, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-gugerty-nysupct-1848.