Kilby Mfg. Co. v. Hinchman-Renton Fire Proofing Co.

132 F. 957, 1904 U.S. App. LEXIS 4359
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 31, 1904
DocketNo. 2,085
StatusPublished
Cited by18 cases

This text of 132 F. 957 (Kilby Mfg. Co. v. Hinchman-Renton Fire Proofing Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kilby Mfg. Co. v. Hinchman-Renton Fire Proofing Co., 132 F. 957, 1904 U.S. App. LEXIS 4359 (8th Cir. 1904).

Opinion

SANBORN, Circuit Judge.

The Hinchman-Renton Fire Proofing Company, a corporation, brought an action against another corporation, called the Kilby Manufacturing Company, for $5,819.-35, which the plaintiff alleged to be the reasonable value of materials furnished and labor performed for the defendant in the erection of a sugar factory. The defendant answered that this work and these materials were not furnished at its request, but that the materials were furnished and the labor was performed in-fulfillment of a contract between the plaintiff and James J. Cooke. There was a judgment for the plaintiff for $6,082 and costs, which the defendant has sued out this writ of error to reverse.

The trial of the action developed these facts: The Kilby Company had undertaken with another corporation to construct for it a sugar factory. Thereupon James J. Cooke made a contract with the Kilby Company to construct this factory for $130,855, in accordance with certain plans and specifications. Before this contract was let, the plaintiff had been requested by the Kilby Company to bid upon certain portions of the work and materials, and had agreed with it to furnish these materials and perform-this work for $62,500. The defendant then made the agreement with Cooke whereby the latter agreed to construct the factory, and Cooke made an agreement with the plaintiff whereby the latter agreed to perform the work and furnish the materials assigned to it for the amount of its bid to the Kilby Company. Each of these contracts provided that the contractors should perform the work according to the same plans and specifications. Cooke agreed in his contract with the defendant that the latter might make any alterations, additions, or deductions in the work, that the amount of expense of such alterations should be added to or deducted from-: the contract price, that it should be estimated at the same rates at which the contract was undertaken, and that he would make no charge for extra work unless the same was ordered in writing by the defendant or by its engineers. The plaintiff, in its contract with Cooke, recited that the defendant had reserved in its contract the right to make alterations, additions, and deductions, and that Cooke-should also have the right to make corresponding alterations, additions,, or deductions in the work as he thought best; that the amount of the expenses of such alterations should be added to or deducted from the-[959]*959contract price as the case might be; that it should be estimated at the same rates at which the contract was undertaken; and that no charge should be made by it for extra work unless the same had been ordered in writing by the defendant or by its engineers or by Cooke. Cooke and the plaintiff proceeded to perform their contracts, and the defendant settled with and paid Cooke for his work and materials. In the course of the performance of the plaintiff’s contract the defendant verbally requested it to perform labor and furnish materials which it claimed it was not required to perform and furnish under its contract with Cooke. After it had completed its work it presented to the defendant an itemized bill of this work and material, which contained 32 items. The defendant conceded that 26 of them were not covered by the contract, and that it ought to pay them, and paid to the plaintiff $761.03 on account of six of these items. This action was brought to recover for some of the remainder of the items, two of which present the real controversies in the case. A part of the work which the plaintiff agreed to perform consisted of the construction of the walls and approaches of the beet sheds. One of these items was for $1,974.40 for paving the approaches to the beet sheds. The other was for $2,243.15 for increasing the height of the walls of the sheds. The plaintiff was required by its contract to pave the approaches and roadways to the sheds. Before the plaintiff made its bid to the Kilby Company for the work which it subsequently agreed by its contract with Cooke to perform, its president said to the general manager of the Kilby Company: "Mr. Kilby, from these plans and specifications, the way they read, you would have me paving all the north end of that county. Give me some idea of where we stop, what the limit is;” and Mr. Kilby said: “Pave the roadways and 25 feet on each end of the sheds and the width of the roadways.” And the plaintiff made its bid and contracted upon that basis. The defendant subsequently requested the plaintiff to extend this paving beyond the 25 feet, and there was evidence in the case that the reasonable value of this extra paving was $1,974.40.

The plans and specifications required the walls of the beet sheds to be 9 feet high and 400 feet long; between the walls of each shed they disclosed a floor; that the bottom of the footings of the walls were to be 3 feet below this floor at its lower end; that the walls were to be constructed upon a horizontal plane, but that the floor was to be laid upon an inclined plane, so that the upper end would be about three feet higher than the lower end. Thus the walls would be nine feet high throughout, but at the lower end of them about six feet of the walls would be above the floor and three feet below the floor, while at the upper end there would be three feet of the walls above the floor and six feet below them. Before the plaintiff made its bid or contract, its president had a copy of these plans and specifications. He said to the general manager of the defendant: “Mr. Kilby, about how will we figure these beet shed walls? Mr. Kilby, how will we figure these; on the grade?” and Mr. Kilby said: “Yes, figure them on the grade. It would be foolishness putting concrete down into the ground to the depth of that, because where it gets to the upper end of the shed the grade raises about eight feet in a thousand, and the upper end of a shed [960]*960of 400 feet would raise something over 3 feet out of the hill.” Notwithstanding this conversation, the contracts with Cooke required the beet shed walls to be constructed in accordance with the original plans and specifications. When the walls of the sheds were laid out by the engineer of the Kilby Company he required the footings to be only 18 inches below the floor, and when the walls of the first shed were nearing completion it was found that the sheds would not have the capacity required by the contract between the Kilby Company and its employer. Thereupon the defendant required the plaintiff to place upon the top of the walls about the amount of materials which would have been placed in the ground below the actual footings of the walls if the original plans and specifications had been complied with. This change from the original plans and specifications did not require more labor or materials than were required by them. But it did require more than would have been required if the original plans and specifications had provided for the construction of the walls on the grade of the floors in accordance with the conversation between the president of the plaintiff and the general manager of the defendant.

The court charged the jury that the plaintiff might recover the reasonable value of any work done or materials furnished at the request of the defendant that were not included in the contract between the plaintiff and Cooke, and it tried the case upon this theory.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blake Construction Company v. United States
252 F.2d 658 (Fifth Circuit, 1958)
Blake Construction Co. v. United States
252 F.2d 658 (Fifth Circuit, 1958)
Arkansas Amusement Corporation v. Kempner
57 F.2d 466 (Eighth Circuit, 1932)
American Refining Co. v. Sims Oil Co.
282 S.W. 894 (Court of Appeals of Texas, 1926)
Oklahoma City v. Derr
1928 OK 159 (Supreme Court of Oklahoma, 1925)
Stewart v. Spalding
23 Haw. 502 (Hawaii Supreme Court, 1916)
Berg v. Erickson
234 F. 817 (Eighth Circuit, 1916)
Douglass & Varnum v. Village of Morrisville
95 A. 810 (Supreme Court of Vermont, 1915)
Riverside Tp. v. Stewart
211 F. 873 (Third Circuit, 1914)
Miller v. Spring Garden Ins.
202 F. 442 (Ninth Circuit, 1913)
Sisters of Charity v. Burke
22 Colo. App. 230 (Colorado Court of Appeals, 1912)
Connecticut Fire Ins. v. Buchanan
141 F. 877 (Eighth Circuit, 1905)
Rucker v. Bolles
133 F. 858 (Eighth Circuit, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
132 F. 957, 1904 U.S. App. LEXIS 4359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kilby-mfg-co-v-hinchman-renton-fire-proofing-co-ca8-1904.