Stewart v. Spalding

23 Haw. 502, 1916 Haw. LEXIS 50
CourtHawaii Supreme Court
DecidedNovember 17, 1916
DocketNo. 904
StatusPublished
Cited by14 cases

This text of 23 Haw. 502 (Stewart v. Spalding) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stewart v. Spalding, 23 Haw. 502, 1916 Haw. LEXIS 50 (haw 1916).

Opinion

OPINION OP THE COURT BY

ROBERTSON, C. J.

The plaintiff in error was the defendant in an action of assumpsit tried in the circuit court with a jury wherein judgment, was entered against him in the sum of $57,038.76. The plaintiffs’ complaint included four counts. The first count was upon a contract in writing bearing date the 29th day of July, 1909, and alleged to have been modified by certain letters dated August 3 and 10, 1909, for the construction of a building at Portland, Oregon, a balance of $54,506 being claimed to be due and unpaid under said contract. The second count was in quantum meruit for the reasonable value of the material furnished, and the work and labor performed in the erection and completion of the building. The third count was upon an account stated wherein it was alleged that in the month of February, 1911, the parties found to be due, and the defendant promised to pay, the sum of $54,506. The fourth count was in quantum meruit for the value of additional work, including the furnishing of material and labor, upon said building not covered by the contract. The defendant, in his answer, denied that there remained an unpaid balance due the plaintiffs under the contract or otherwise, and claimed that the sum of $26,500 had been improperly charged against him, and that he had been damaged by reason of delay in the completion of the building and by defective construction, in the sum of $25,811.25. The jury returned a verdict for the plaintiffs in the sum of $38,847.63, with interest from February 3, 1911.

[505]*505At the outset there is a dispute as to what the contract between the parties was. The evidence showed that the plaintiffs by a letter dated at New York on July 29, 1909, addressed to the defendant at that city, made alternative offers based upon plans and specifications prepared by one Cass Gilbert, an architect, the second of which was as follows:

“2. We will erect this building on a percentage basis, you paying only the exact cost of the building with the changes made in the plans and specifications, as estimated, Four Hundred Eighty-two Thousand, Three Hundred Fourteen Dollars ($482,314.00); you paying us for our services Eight Per Cent (8%) of the actual cost of the building, or, if you prefer, we will make a fixed commission of Thirty-eight Thousand Dollars ($38,000.00) on the building erected in accordance with the changes now outlined, subject to any increase for any additional work done not now determined upon; our employment under this proposition being arranged for practically in accordance with the contract which I showed you some months ago, made between us and the owners of the First National Bank Building, Denver, which we are now erecting, which contract provides:
“That we shall furnish at our expense such machinery, tools and equipment as are necessary for the prompt erection of the building;
“That we will make every effort to adopt every practical means to reduce the cost of the building as far as possible;
“That we will keep separate accounts, files of letters, etc., for this work;
“That we will furnish monthly statements of all materials entering into the building, payrolls, and amounts due to sub-contractors;
“That we will maintain an office in Portland;
“That we will attend to the question of insurance, employer’s liability, etc.”

The defendant accepted the offer on the fixed commission basis with the modification, mutually agreed upon, to the effect that should the contractors effect a saving on the [506]*506total cost without modifying the quality or extent of work or materials they should receive an additional 10% commission on the amount of such saving. The defendant left New York for Europe on August 1. On August 3 A. hi. Stewart addressed a letter to Cass Gilbert saying, among other things:

“In order that there may be no question with Col. Spalding as to what items enter into the cost of the building in ascertaining finally what is the actual cost, and there may not be charged against our commission certain payment which really enter into the cost of the work, we desire to have added to the specifications, or to the contract a clause clearly stating this understanding, and I would suggest the following, viz:
“ ‘In calculating the cost of the building under this contract there shall be included therein the amount of all subcontracts, of all material entering into this construction, and the wages of all persons employed upon the building, also the cost of all permits, surveys, temporary office with telephone and supplies, temporary heat, light, enclosures, floors, bridges to the sidewalks, etc., temporary water closets, and other plumbing, freights on all materials, equipment and tools, liability insurance, and repairs to streets or to the adjoining property/ ”

Replying thereto on August 10 Gilbert wrote:

“As to the second and third paragraphs of your letter, I think there can be no question ‘as to what items enter into the cost of the building in ascertaining finally what is the actual cost.’ The general conditions of the specifications are clear on this subject and I find your statement of the case to be correct on the subject as follows: ‘In calculating the cost of the building under this contract there shall be included therein the amount of all sub-contracts, of all material entering into its construction and the wages of all persons employed upon the building, also the cost of all permits, surveys, temporary offices with telephone and supplies, temporary heat, light, enclosures, floors, bridges to sidewalk, etc., temporary water closets, and other plumbing, freights on all materials, equipment and tools, also [507]*507liability insurance and repairs to streets or adjoining property.’ ”

A contract was drawn up by the architect and the plaintiffs signed the same on August 27, and the defendant signed it on his return from Europe on September 11. A clause in the specifications which were made part of the contract provided that “The contractor is to provide derricks, hoists, machinery, scaffolding, tools and appliances of every description required for the proper execution of this work.” It was also provided in the specifications that “The general permit for the erection of the building will be obtained by the architect at contractor’s expense. The contractor shall obtain and pay for all other permits which may be required by the city laws and regulations.” Thus appeared a flat contradiction between the terms of the offer made by the plaintiffs in their letter of July 29 and the contract executed by the parties, on one hand, and. the terms of the letters of August 3 and 10, on the other. The cost of tools and equipment, permits, liability insurance, and the maintenance of a temporary office in Portland constituted a part of the plaintiffs’ claim and was admitted in evidence over the objections of the defendant. The court instructed the jury that “The burden is also upon the plaintiffs of proving by a preponderance of the evidence that the letters of Augüst 3, 1909, and August 10, 1909, between the architect and the plaintiffs were ratified by the defendant. If you find that they were so ratified, then the written contract was to that extent modified.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Metzler Contracting Co. LLC v. Paul Stephens
479 F. App'x 783 (Ninth Circuit, 2012)
Metzler Contracting Co. LLC v. Stephens
774 F. Supp. 2d 1073 (D. Hawaii, 2011)
Tri-S Corp. v. Western World Insurance Co.
135 P.3d 82 (Hawaii Supreme Court, 2006)
Daiichi Hawai'i Real Estate Corp. v. Lichter
82 P.3d 411 (Hawaii Supreme Court, 2003)
Coon v. City and County of Honolulu
47 P.3d 348 (Hawaii Supreme Court, 2002)
Wilart Associates v. Kapiolani Plaza, Ltd.
766 P.2d 1207 (Hawaii Intermediate Court of Appeals, 1988)
Barwick Pacific Carpet Co. v. Kam Hawaii Construction, Inc.
630 P.2d 638 (Hawaii Intermediate Court of Appeals, 1981)
HEW v. Aruda
462 P.2d 476 (Hawaii Supreme Court, 1969)
Honolulu Roofing Co. v. Felix
426 P.2d 298 (Hawaii Supreme Court, 1967)
Saiki v. Lee Sing
27 Haw. 399 (Hawaii Supreme Court, 1923)
Yamashiro v. Costa
26 Haw. 54 (Hawaii Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
23 Haw. 502, 1916 Haw. LEXIS 50, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stewart-v-spalding-haw-1916.