Anderson v. Todd

77 N.W. 599, 8 N.D. 158, 1898 N.D. LEXIS 34
CourtNorth Dakota Supreme Court
DecidedNovember 22, 1898
StatusPublished
Cited by19 cases

This text of 77 N.W. 599 (Anderson v. Todd) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson v. Todd, 77 N.W. 599, 8 N.D. 158, 1898 N.D. LEXIS 34 (N.D. 1898).

Opinion

Young, J.

Action to recover a balance claimed to be due upon a building contract and for extras, and to enforce a mechanic’s lien therefor. The defense is noncompliance with, and nonperformance of, the contract. The trial court determined that the contract had been substantially complied with, and after making certain deductions, to which allusion will be subsequently made, found for the plaintiffs. Defendant appeals, and specifies some 47 errors. These it will not be necessary or useful to consider in detail, for reasons which will appear as we proceed. The defendant, being desirous of erecting a two-story brick building upon a certain corner lot owned by him in the City of Grafton,' — the first story to be used for a store, and the second for offices, — caused plans and specifications therefor to be prepared by Orff & Joralemon, architects in Minneapolis. On *159 July 17, 1894, the plaintiffs, who are contractors and builders, entered into a written contract with defendant to erect such building in accordance with the plans and specifications so prepared, except as to the foundation, which was modified by the following language inserted in the contract: “Instead of foundation being built by piers as shown by plans, said foundation is to be solid foundation under all the exterior walls of said building, to go down six (6) feet below the surface, and to be built at the bottom three (3) feet wide and one (1) foot thick, of concrete, the same as set forth in the plans; and the balance of the wall to be of brick, three (3) feet wide at the bottom, and gradually tapering to the top of said foundation wall, which is to be sixteen (16) inches wide.” Plaintiffs also stipulated in said contract “to lay all foundation brick in cement, and foundation wall to be plastered inside and outside with cement, of the same kind set out in plans and specifications;” that is, Yankton cement. Defendant, on his part, bound himself therein to pay the sum of $6,000, as follows: 75 per cent, of the cost of all the material upon the ground, to be-estimated every 14 days; the balance “to be paid when the building is completed and turned over, and accepted by the said first party, and when the said second party turns over to the first party receipts in full showing payment of all material used in- said building, and payment to all subcontractors in full of the amount due them for material furnished or labor done.” The findings of the trial court enumerate certain specific particulars in which the plaintiffs deviated from the'ir written contract, and to which we now call attention: First, Milwaukee or Louisville, and not Yankton, cement was used; the evidence showing that from 180 to 210 barrels were necessary, and that the relative cost thereof per barrel at Grafton was as follows: Milwaukee, $1.44; Louisville, $1.79; Yankton, $3.40. Second. The foundation wall did not taper up 6 feet from a 3-feet width at the bottom to 16 inches at the top, but was blocked into a 16-inch wall 2 feet from the bottom, at a saving of 6,000 brick to the contractors. Third. The plate glass was not free from sand holes. Fourth. The front of the building was not properly constructed. Fifth. The plaintiffs did not turn over receipts showing payments to subcontractors, and for material, as required by the contract. Sixth. The rear and party walls were not built of selected brick, as to color. The trial court held, however, that the plaintiffs had not willfully deviated from the contract, but had acted in good faith, and, upon the basis that there had been a substantial performance on their part, allowed the plaintiff’s to recover the contract price, also $188.49 for extras furnished, less payments made, but reduced the balance so found to be due by an allowance for defects and damages as set out in the following finding: “That the total deduction to be made from the contract price of said building by reason of noncompliance with the contract is the sum of $416.46, as follows: Defects in plate glass, $25; defective construction of front, $50; foundation not built as to contract, as per finding No. 13, $275; painting of front $25; *160 removing rubbish, insurance plate glass in side door, $16.46; pointing up holes in wall $25.”

An examination of the evidence satisfies us that the findings of the trial court relating to the deviations from the contract as above indicated are not only sufficiently supported, but are favorable to the plaintiffs; for they rest, not upon disputed and conflicting evidence, but upon the testimony of plaintiffs’ own witnesses. Although the findings are silent upon that point, the undisputed evidence also shows that no foundation wall at all was built under the front portion of the building. The defendant’s answer placed in issue the performance of the contract, not only generally, but by particularizing various oiiiissions and defects in addition to those already alluded to; including unskillful and careless workmanship, and the use of defective and improper materials. Evidence was introduced which we must say tended to some extent, at least, to establish these further grievances. But in our view it is not necessary to deliberate over conflicting testimony in order .to properly determine this case; for, under the controlling facts in the findings themselves, we are convinced that the plaintiffs have not substantially complied with the contract, and they cannot, therefore, recover upon it. It is true that the early rule, requiring a technical and literal compliance with the contract as a condition precedent to a recovery upon it, has been so modified, in the interest of, and for the protection of, the honest, skillful, and prudent contractor, that he may now recover upon his contract when it appears that he has endeavored to perform it in good faith, and according to its terms, and has done so, except as to unimportant omissions or deviations, which are the result of mistake or inadvertence, and were not intentional, and which are susceptible of remedy, so that the other party will get substantially the building he has contracted for. In such event the doctrine of substantial performance prevails, and the contractor may recover the contract price, less the expense of repairing the defects and omissions. See Leeds v. Little (Minn.) 44 N. W. Rep. 309; Elliott v. Caldwell (Minn.) 45 N. W. Rep. 845; Smith v. Brady, 17 N. Y. 173; Aldrich v. Wilmarth (S. D.) 54 N. W. Rep. 811; Crouch v. Gutmann, 134 N. Y. 45, 31 N. E. Rep. 271; Pullman v. Corning, 14 Barb. 174; 2 Beach, Mod. Cont. § 1729; Glacius v. Black, 50 N. Y. 145; Phillip v. Gallant, 62 N. Y. 256; Woodward v. Fuller, 80 N. Y. 312; Heckmann v. Pinkey, 81 N. Y. 211; Glacius v. Black, 67 N. Y. 563; Nolan v. Whitney, 88 N. Y. 649. Blit the doctrine does not go to the extent of compelling a person to pay the contract price for a building differing in important particulars from that for which he has contracted. The defendant had a right to use his own judgment as to the kind-of material to be used in this structure, and his own taste to fix the style of its architecture. All the details were set our fully in the written specifications and contract. This contract governs their rights.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Curtis Construction Co. v. American Steel Span, Inc.
2005 ND 218 (North Dakota Supreme Court, 2005)
All Seasons Water Users Ass'n v. Northern Improvement Co.
399 N.W.2d 278 (North Dakota Supreme Court, 1987)
Storebo v. Foss
325 N.W.2d 223 (North Dakota Supreme Court, 1982)
Dittmer v. Nokleberg
219 N.W.2d 201 (North Dakota Supreme Court, 1974)
Odegaard v. Investors Oil, Inc.
118 N.W.2d 362 (North Dakota Supreme Court, 1962)
City of Granville v. Kovash, Incorporated
118 N.W.2d 354 (North Dakota Supreme Court, 1962)
Karlinski v. P. R. & H. Lumber & Construction Co.
281 N.W. 898 (North Dakota Supreme Court, 1938)
Fargo Glass & Paint Co. v. Smith
266 N.W. 100 (North Dakota Supreme Court, 1936)
Cotherman v. Oriental Oil Co.
272 S.W. 616 (Court of Appeals of Texas, 1925)
Dinnie v. Lakota Hotel Co.
186 N.W. 248 (North Dakota Supreme Court, 1921)
Horton v. Emerson
152 N.W. 529 (North Dakota Supreme Court, 1915)
Wiebener v. Peoples
1914 OK 397 (Supreme Court of Oklahoma, 1914)
Mortimer v. Dirks
107 P. 184 (Washington Supreme Court, 1910)
Marchand v. Perrin
124 N.W. 1112 (North Dakota Supreme Court, 1910)
Connor v. Trapp
104 N.W. 333 (Supreme Court of Iowa, 1905)
Braseth v. State Bank
98 N.W. 19 (North Dakota Supreme Court, 1904)
Franklin v. Schultz
57 P. 1037 (Montana Supreme Court, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
77 N.W. 599, 8 N.D. 158, 1898 N.D. LEXIS 34, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-v-todd-nd-1898.