Pullman v. Corning

14 Barb. 174, 1851 N.Y. App. Div. LEXIS 138
New York Supreme Court·Decided June 3, 1851·Published·Cited by 6 cases

Opinion

By the Court, Welles, J.

The action was brought by Pullman, the appellant, to recover pay for doing the mason work in putting up the walls of a cobble-stone house for the respondents, upon their land in the town of Webster, Monroe county, at the price of fifty cents a perch, the respondent furnishing the materials, and claiming that the walls, when completed, measured 540 perches; also for extra work on the same building ; and for damages in consequence of the respondents not being ready for the appellant to commence the work according to agreement. The answer denied any indebtedness of the respondents to the appellant ; and set out a special parol agreement between the parties respecting the building the walls of the house m question, alledging that the appellant commenced the work, and went on and pretended to have completed it; but alledged that it was not done according to contract, but that it was done in an unskillful, unworkmanlike manner, specifying the defects particularly, and claiming that the work was worthless, and that their damage in consequence thereof was $305. The replication fortified the complaint, and alledged that whatever defects existed were attri[175] butable to the directions and conduct of the respondents, and the badness of the materials furnished.

The action was tried before referees, who, after hearing a large amount of evidence, made a report, in July, 1849, by which they found that the plaintiff, (the appellant,) in the spring of the year 1848, contracted with the defendants (the respondents) to build them the cobble-stone building, with walls of the dimensions mentioned in the answer, in a good, skillful and workmanlike manner, at and for the sum of fifty cents a perch, of materials to be furnished by the defendants, which price the defendants agreed to pay when the work should be completed in manner aforesaid.

The referees further found by their report, that the plaintiff constructed the walls of such building, of materials furnished by the defendants, by the 12th day of August, 1848; but that he constructed the same in so unskillful, negligent and unworkmanlike manner, that by reason thereof they were cracked, warped and unsafe, and could not be made good and safe walls, without taking down and rebuilding two-fifths of the same.

They also found that the defendants had not accepted the work, nor waived a faithful, skillful and workmanlike performance thereof. That the other material allegations in the plead-, ings they did not find proved; and they therefore found that the defendants were not indebted to the plaintiff for the work.

By a supplemental report, made in pursuance of an order of tho court, the referees reported that the ground upon which they found that the plaintiff was not entitled to recover, was, that while they found that two-fifths of the wall built would require to be taken down and relaid, they did not regard the plaintiff’s .iob complete, and found that it was not so. Also that they found the value of the good wall, exclusive of materials, to be $161,60. and the expense of taking down the bad wall to be $57, and the value of the good wall after deducting the latter sum to be $104,60; to this they added $4,50 for extra work, making $109. That this last sum was the value of the plaintiff’s services to the defendants, unless they might have sustained damages by loss of the use of the building.

[176] Judgment was entered in favor of the defendants, at a special term, from which the plaintiff appealed.

It is admitted by the appellant’s counsel to be a general rule, that in actions for work, labor and services, where performance of the work to be done is the consideration of the promise to pay for it the stipulated price, a substantial performance is a condition precedent to the right to recover. But it is claimed that this rule has its exceptions, and that in cases of building contracts, especially on the land of the party for whom the building is constructed, where the work is fully done but not in the manner stipulated in the contract, yet if done in good faith and it is of any value to the party, he is answerable for the amount of such value, deducting what it would cost to make the work as good as the contract required. This is a question of a good deal of practical importance, and has been the subject of. much discussion and some conflict - of decision in the courts of England and this country. As remarked by Bronson, justice, in Mead v. Degolyer, (16 Wend. 632,) “ Some confusion has crept into the cases, for the want of proper care in distinguishing between the right and the remedy; or in other words, between the cause of action and the mode of enforcing it. These are distinct considerations, and yet the language of judges, in relation to one branch of the subject, has frequently been quoted as an authority in relation to the other. Where there is no dispute about the right of action, there may be still a question about the form of the remedy.” Many cases are reported where the plaintiff has not been allowed to recover when it appeared he had a good cause of action, on the ground that his declaration was not adapted to his case as disclosed by the evidence; as for instance, where he had declared upon a special agreement to perform a particular service, or do a particular job of work in a specified manner and within a certain time, for a compensation agreed upon, averring performance on his part, and the evidence showed only a part performance and a legal excuse for not performing the residue, or a full performance but not by the time or in the manner which the contract required, but there had been a waiver of strict performance or an acceptance by the other party, or an [177] express or an implied agreement extending the time or changing the manner of performance. In all of these cases the plaintiff would be entitled to recover for his services on the common counts for work and labor, but not under a special count upon the contract.

In this case, however, there is no question made in relation to the form of stating the cause of action in the complaint. It is simply a question of the appellant’s right to recover, upon the facts found by the referees.

Free access — add to your briefcase to read the full text and ask questions with AI

Pullman v. Corning, 14 Barb. 174, 1851 N.Y. App. Div. LEXIS 138 (N.Y. Super. Ct. 1851).

14 Barb. 174 (Pullman v. Corning) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Todd
77 N.W. 599 (North Dakota Supreme Court, 1898)
Hand v. Church
46 N.Y. Sup. Ct. 303 (New York Supreme Court, 1886)
Sinclair v. Tallmadge
35 Barb. 602 (New York Supreme Court, 1861)
Merkle v. State
37 Ala. 139 (Supreme Court of Alabama, 1861)
Wolcott v. Yeager
11 Ind. 84 (Indiana Supreme Court, 1858)
Pullman v. Corning
1 Seld. Notes 161 (New York Court of Appeals, 1853)