Mead v. Degolyer

16 Wend. 632
CourtNew York Supreme Court
DecidedMay 15, 1837
StatusPublished
Cited by36 cases

This text of 16 Wend. 632 (Mead v. Degolyer) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mead v. Degolyer, 16 Wend. 632 (N.Y. Super. Ct. 1837).

Opinions

By the Court, Bronson, J.

The offer made by the defendant below for the purpose of effecting a settlement, was rejected by the plaintiff, and must therefore be laid out of the case.

The change which the defendant consented to make in the price to be paid for the timber, only modified the written contract in that particular. .In all other respects the agreement, and the rights of the parties under it, remained unaltered. The delivery of the whole quantity of timber, and by the specified time, continued, as they were before, to be conditions precedent to the plaintiff’s right to the price; except as to that portion which was payable on the delivery of each load, and that has been paid.

The contract afterwards underwent a further modification, by enlarging the time for the delivery of the timber. Although there was no express stipulation to that effect, [635]*635Such an agreement may be implied from what took place after the first day of July—the time when the contract should have been fully executed on the part of the plaintiff. He continued to deliver timber after the day had passed, which the defendant received without objection. Payments were made and received on the contract. Both parties, therefore, may be regarded as having tacitly assented to an extension of the time for performance on the part of the plaintiff. If when the day arrived the defendant intended to insist on the default, and not allow the plaintiff to proceed to a completion of the delivery, he should have spoken at that time. Jewell v. Schroeppel, 4 Cowen, 564. The plaintiff on his part had no choice but to go on with the contract, or forfeit what he had done under it. Neither party can now set up that the contract was wholly rescinded by what took place after the first of July. The quantity and description of timber to be delivered, and the price to be paid—subject to all just allowances to the defendant for the default—remained untouched. Whatever foundation there might be for the defendant to insist that the contract was at an end, there was surely no ground for any such argument on the part of the plaintiff. All the wrong had been on his part. He refused in the first place to proceed with the contract without a large advance in price; and then made default in point of time. The most that he can ask is, that the original contract shall be deemed to have been modified in these two particulars—not wholly abandoned. To go further would be the height of injustice. Indeed the court below did not put the case upon the ground that the contract had been rescinded, nor did the counsel for the plaintiff assume that position on the argument in this court.

What then is this case ? The plaintiff agreed to deliver a large quantity of timber ; for which he was to be paid— ■except the part which he has already received—when the whole quantity should be delivered. He furnished a part of the timber, and then, without any excuse or apology whatever, stopped short; and now claims to recover for the timber actually delivered. The mere statement of the [636]*636case furnishes a complete answer to the action. Courts have no dispensing power to absolve men from their legal engagements, nor can they make contracts for them. The delivery °f the timber was a condition precedent to the payment of the price ; and the plaintiff must first perform on his part before he has any ground of complaint against the defendant. This court has never held any other doctrine. I shall not go through with the cases—it will be enough to refer to a few of them. M'Millan v. Vanderlip, 12 Johns. Rep. 165. Jennings v. Camp, 13 id. 94. Ketcham v. Evertson, id. 359. Wood v. Edwards, 19 id. 205. Champlin v. Rowley, 13 Wendell, 258. Sickles v. Pattison, 14 id. 257.

The cases cited by the plaintiff’s counsel will not aid him. In Linningdale v. Livingston, 10 Johns. R. 36, the contract had been partially performed by the plaintiff in proper time, and after the day he offered to complete the work, but was prevented by the defendant. The court said that this put an end to the special contract, and the plaintiff might recover for the logs which had been delivered, under the general counts. In the case under consideration, the plaintiff has never offered to complete the performance of his contract, nor has he been prevented from doing so by any act of the defendant. Raymond v. Bearnard, 12 Johns. Rep. 274, turned on the same distinction. The plaintiff offered to. go on with the contract, but the defendant refused, on the ground that the plaintiff was in default. The court held that there was no longer any subsisting special agreement between the parties, and the plaintiff might recover back the money paid, under the common counts. In Dubois v. The D. & H. Canal Co., 4 Wendell, 285, the plaintiff had been prevented from performing the work in time by the act of the defendants, and it had, in fact, been performed, though after the day. It was also said that the special contract had been rescinded by the acts of the de-, fendants. But in this case, the plaintiff has neither performed on his part, nor is there any pretence that the defendant has done any act to put an end to the special agreement. The remarks of Sir James Mansfield, C. J., in [637]*637Cooke v. Munstone, 4 B. & P. 351, have been cited and misapplied a hundred times. The decision itself proves nothing in favor of this action. The plaintiff had paid £2, 5s., as earnest money on a contract by which the defendant was to deliver 35 chaldrons of soil, and the defendant had wrongfully refused to deliver it. The plaintiff declared on the special agreement, and added the money counts. Although he clearly had a right of action, the court held that he could not recover on the special count, because there was a variance between it and the special agreement; and that he could not recover back the money paid under the general counts, because the special agreement was still in force. With great respect, I think the last branch of the decision was not well founded. The defendant, by his own wrongful act, had put it in the power of the plaintiff to sue for a breach of the special agreement, or to waive that right, and recover back the money paid. It did not lie with the defendant to object that the special contract was still in force after he had refused to perform it. It is, however, unnecessary to decide any thing on that point. It is enough that the case cannot aid the plaintiff The only case which favors this action is Oxendale v. Wetherell, 9 B. & C. 401, and it has already been held that this decision is not in accordance with the rule as settled in this state. Champlin v. Rowley, 13 Wendell, 258.

Some confusion has crept into the cases for the want of proper care in distinguishing between the right and the remedy—or in other words, between the cause of action and the mode of enforcing it. These are distinct considerations, and yet the language of judges, in relation to one branch of the subject, has frequently been quoted as an authority concerning the other. Where there is no dispute about the right of action, there may still be a question about the form of the remedy. One general rule in relation to special agreements for the performance of labor, delivery of materials, or the like, is, that so long as the contract continues executory, the plaintiff must declare specially ; but when it has been executed,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlantic & Pacific Packing Co. v. Weinstein
272 A.D.2d 1073 (Appellate Division of the Supreme Court of New York, 1947)
Harris Lumber Co. v. Wheeler Lumber Co.
115 S.W. 168 (Supreme Court of Arkansas, 1908)
Doncourt v. Denton
55 Misc. 594 (New York Supreme Court, 1907)
Silberman v. Fretz
16 Misc. 449 (New York Supreme Court, 1896)
D. M. Osborne & Co. v. Martin
56 N.W. 905 (South Dakota Supreme Court, 1893)
Kokomo Strawboard Co. v. Inman
31 N.E. 248 (New York Court of Appeals, 1892)
Brown v. Griffin
40 Ill. App. 558 (Appellate Court of Illinois, 1891)
Travelers Insurance v. Sheppard
12 S.E. 18 (Supreme Court of Georgia, 1890)
E. P. Reed & Co. v. F. C. Pinney & Co.
35 Ill. App. 610 (Appellate Court of Illinois, 1890)
Brown v. Norton
2 N.Y.S. 869 (New York Supreme Court, 1888)
Drabek v. Grand Lodge of Bohemian Slavonian Benevolent Society
24 Ill. App. 82 (Appellate Court of Illinois, 1887)
Keith v. Goldston
22 Ill. App. 457 (Appellate Court of Illinois, 1887)
White v. Old Dominion Steamship Co.
1 Silv. Ct. App. 41 (New York Court of Appeals, 1886)
Dunbier v. Day
12 Neb. 596 (Nebraska Supreme Court, 1882)
Avery v. . Willson
81 N.Y. 341 (New York Court of Appeals, 1880)
McBean v. Fox
1 Ill. App. 177 (Appellate Court of Illinois, 1878)
Timmons v. Nelson
66 Barb. 594 (New York Supreme Court, 1873)
Siebert v. Leonard
17 Minn. 433 (Supreme Court of Minnesota, 1871)
Nightingale v. Meginnis
34 N.J.L. 461 (Supreme Court of New Jersey, 1871)

Cite This Page — Counsel Stack

Bluebook (online)
16 Wend. 632, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mead-v-degolyer-nysupct-1837.