United States ex rel. Hudson River Stone Supply Co. v. Molloy

144 F. 321, 11 L.R.A.N.S. 487, 11 L.R.A (N.S.) 487, 1906 U.S. App. LEXIS 3837
CourtCourt of Appeals for the Second Circuit
DecidedFebruary 1, 1906
DocketNo. 35
StatusPublished
Cited by5 cases

This text of 144 F. 321 (United States ex rel. Hudson River Stone Supply Co. v. Molloy) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Hudson River Stone Supply Co. v. Molloy, 144 F. 321, 11 L.R.A.N.S. 487, 11 L.R.A (N.S.) 487, 1906 U.S. App. LEXIS 3837 (2d Cir. 1906).

Opinion

TOWNSEND, Circuit judge.

This case has already been before this court on a writ of error from a direction of a verdict for defendants (127 Fed. 953, 62 C. C. A. 585), and the opinion therein sufficiently states the facts bearing on this controversy and the relations of the parties, so far as they were shown on the former trial. Upon this trial it appeared that plaintiff had failed to keep the defendants supplied with stone “as required,” in accordance with the terms of the express contract. The court held that the contract had not been fulfilled, and directed a verdict for defendants.

The exceptions challenge the correctness of the action of the trial judge in directing said verdict, and also in excluding certain papers offered by the plaintiff, claimed as tending to show that the defendant was not delayed in the work by the plaintiff’s breaches of the contract. It is a sufficient answer to this second exception that the [322]*322papers offered were incompetent to prove any such claim. They consisted merely of statements furnished to the government, by the de-' fendant Molloy, of plant, labor, and material employed in the work actually done by him for the government, for which he had asked payment. There is nothing to -show that he was not delayed in his work by reason of plaintiff’s defaults, or that he did not actually need the stone which was required by him, and which plaintiff failed to furnish. This exception, therefore, is without merit.

The exception to the direction of a verdict is supported by the contentions (1) that the agreement “to keep the party o'f the second, part supplied with stone as required” means as he actually and reasonably required in the conduct of his business; (2) that the plaintiff was entitled to show that the alleged breaches were' not substantial or material; and (3) that inasmuch as the defendant Molloy accepted and used some of the installments of stone, although not delivered or received in accordance with the terms of the contract as to time of delivery, defendants are liable for the value of said installments.

As to the first contention it is sufficient to say that no competent evidence was offered to show that the stone as required by Molloy was not actually and reasonably required. He testified as follows:

“We never got any stone on time, always delayed. Q. Always late. On the 25th you sent a letter or telegram: ‘No -stone here yet. What is the matter?’ Do you recall that? A. Xes. The stone had not been furnished. We were out of stone at that time. The statements in the letters and telegrams in regard to the delays or failure to get stone there were absolutely true and correct. I did have a talk with Mr. Alsdorf with reference to this delay. He was the gentleman mentioned by Mr. Shaw as the vice president of the company. He was the man with whom this contract was made, or the negotiations for it. The conversation with him about this delay was that I complained all the while to him, and he said there was something the matter with the crusher, and they had' oversold • the quantity the crusher would produce, and the crusher had broke down or something. And they were promising and promising. Meanwhile the Government was pressing me on the other side. I had to' db something or get out of there. When X had no stone there the men could not work. There was nothing but concreting at that time — nothing for the men to do.”

This evidence disposes also of the second contention because it tends to show that plaintiff’s breaches were substantial or material.

The third contention raises the question as to the liability of defendants for the acceptance and use by the defendant Molloy of certain installments of stone not delivered as required under the contract.

This action is not brought upon the written contract between the parties, but upon a quantum valebat for the value of stone delivered to, and accepted and used by, defendant Molloy in the work covered by his contract with the government. He asserts that none of this stone was received on time or “when required” in accordance with the terms of his contract with plaintiff, and that, therefore, he (Mol-loy) elected, after the receipt of certain installments, to treat plaintiff’s •defaults as an absolute breach of the contract, and refused to accept installments subsequently tendered. It appears, therefore, that the stone received by the defendant Molloy was accepted and used by him with knowledge of the fact that it had not been delivered in accordance with the terms of the contract, but in violation thereof. [323]*323The precise question here raised is whether in these circumstances, the defendant can retain the stone and yet refuse to pay for it. In our former opinion in this case we referred to some cases bearing on this question, but expressly declined to pass upon the point because it was not involved therein.

Mr. Parsons, in his work on Contracts, stated the general rule as follows:

“We have seen that where parties make a contract which is not apportion-able, no part of the consideration can be recovered in an action on a contract, until the whole of that for which the consideration was to be paid is performed. ' But it must not he inferred from this that a party who has performed a part of his side of a contract, and has failed to perform the residue, is in all cases without a remedy. For although he can have no remedy on the contract as originally made, the circumstances may be such that tiie law will raise a new contract, and give him a remedy on a quantum meruit. * * *
“So, too, if one party, without the fault of the other, fail§ to perform his side of the contract in such a manner as to enable him to sue upon it, still, if the other party have derived a benefit from the part performed, it would be unjust to allow him to retain that without paying anything. The law, therefore, generally implies a promise on his part to pay such a remuneration as the benefit conferred upon him is reasonably worth; and to recover that quantum of remuneration, an action of indebitatus assumpsit is maintainable.’ 2 Parsons, Cont. 523.

This statement of the law is referred to with approval by the Supreme Court of the United States in Dermott v. Jones, 23 How. 220-232, 16 L. Ed. 442. The cases bearing upon this subject may be divided into three classes — contracts of sale, contracts for some specific work, such as the erection of a building upon the land of another, and contracts for personal services. There was formerly such a conflict of authority as to the right of recovery in any of these cases that the foregoing statement rather expressed what the rule should be than what it was in fact. Such right of recovery in personal services cases has been generally denied, except in New Hampshire (Britton v. Turner, 6 N. H. 481, 26 Am. Dec. 713) and Iowa (Byerlee v. Mendel, 39 Iowa, 382). In cases of work done and materials furnished for another on his land, but not according to contract, such right of recovery on quantum meruit or valebat has been sustained in Massachusetts (Hayward v. Leonard, 7 Pick. 181, 19 Am. Dec. 268; Smith v. First Cong. Meetinghouse, 8 Pick. 178; Lord v. Wheeler, 1 Gray, 282; Hedden v. Roberts, 134 Mass. 38, 45 Am. Rep. 276), and in Maine, Minnesota, Pennsylvania, Illinois, Vermont, and many other states. In some of the cases there was evidence of an actual assent or acceptance, in others such assent was implied from the retention of the materials or other benefit received by defendant. The whole question is fully discussed in Gillis v. Cobe, 177 Mass. 584, 59 N. E. 455.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
144 F. 321, 11 L.R.A.N.S. 487, 11 L.R.A (N.S.) 487, 1906 U.S. App. LEXIS 3837, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-hudson-river-stone-supply-co-v-molloy-ca2-1906.