Nickel v. Pollia

179 F.2d 160, 1950 U.S. App. LEXIS 3683
CourtCourt of Appeals for the Tenth Circuit
DecidedJanuary 3, 1950
Docket3895
StatusPublished
Cited by10 cases

This text of 179 F.2d 160 (Nickel v. Pollia) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nickel v. Pollia, 179 F.2d 160, 1950 U.S. App. LEXIS 3683 (10th Cir. 1950).

Opinion

HUXMAN, Circuit Judge.

Andrew A. Pollia and six use plaintiffs brought this action in the United States District Court for the District of Wyoming, against E. C. Nickel, the base contractor, herein referred to as the contractor, and the Federal Public Housing Authority, herein referred to as F.P.H.A., formerly the United States Housing Authority, to recover for work done and materials furnished under a subcontract with the contractor. The rights of the six use plaintiffs and an intervener are all dependent upon Pollia and further reference to them is not necessary. The amended complaint contains seven counts. In count one, Pollia sought recovery of an estimate dated October 17, 1946, for $17,848.80. In count two, he sought recovery of an estimate dated November 4, 1946, for a like sum. In count three, he sought recovery for additional work and materials furnished in the sum of $8,267.20, on 102 housing units, excluded from the contract. Count four sought the recovery of $2,311.50, for alleged extra work. Count five was for $24,342, alleged loss on 300 housing units on which the work had not been completed when the *162 contract was terminated. Count six was for $496.72, for materials furnished by Pol-lia to the contractor. Count seven sought recovery of $2,356.97, alleged to be due for loss resulting from unreasonable and unjustifiable delay on the part of the contractor in providing Pollia with materials at erection sites. Trial was had to the court.

The United States appeared specially and moved to dismiss the action as to the F.P. H.A. on the ground that it was an action against the United States and that it had not consented to be sued. The motion was overruled. The trial court entered judgment for Pollia on counts one and two in the amount of the two estimates, totaling $35,695.60. It gave judgment on count three for $8,226.28, on count four for $2,311.50, and on count six for $1,759.12. On counts five and seven, judgment was entered for the defendants. This appeal does not challenge the court’s judgment on count six.

The facts necessary to consider the questions presented by this appeal, briefly are as follows:

On June 14, 1946, the United States through the F.P.H.A. entered into a contract with the contractor for the removal of 900 housing units from the State of Washington and the resurrection thereof in the States of Montana and Wyoming. This was a cost plus fixed fee contract. The contract provided that with the approval . of the contracting officer of the F.P.H.A., the contractor could employ subcontractors to do part of the work. On September 2, 1946, with the approval of the United States, Nickel entered into a subcontract with Pollia for the removal and reinstallation of the plumbing and heating fixtures on 402 of the units for a total consideration of $89,244. The subcontract provided for partial payments as the work progressed at the end of each calendar month, or as soon thereafter as practical, on estimates made by the subcontractor and approved by the contractor. It also incorporated the provisions of the base contract with respect to labor, wages, and such matters. It provided that except where otherwise specifically provided, whenever the contractor and subcontractor were unable to agree on any question of fact arising under the contract, the dispute should be submitted to the contracting officer who signed the principal contract, or his duly authorized representative, whose decision should be final and conclusive upon the parties. In the interim the subcontractor was required to diligently proceed with the work as directed. The contract also provided that if a performance bond was required by the government, the subcontract- or was to furnish the same.

On October 17, 1946, the subcontractor submitted to Ernie C. Bartlett, project engineer for the United States, an estimate for work done in the amount of $17,846.60. The material part of this estimate is as follows:

“I hereby certify that 20% of the plumbing and heating work on the following * * * has been done to this date Oct. 17, 1946.
“(S) Ernie C. Bartlett, “Project Engineer.
“Date received........... Received by (s) Scot H. Cross (Contractor’s representative). Date inspected..............Inspected by.......... (Government representative).”’

A second estimate for an additional amount of $17,846.80, representing a purported additional 20% of the plumbing and heating work was submitted to Bartlett on November 4, 1946. It was signed by Ernie C. Bartlett, Project Engineer, and by Scot H. Cross, Contractor’s representative, in identical language with estimate number one. Cross, who acknowledged receipt of these estimates, was the representative of the contractor at the demolition site and had full authority to act for the contractor.

Pollia transmitted the first of these estimates to J. B. Steele, the contractor’s representative at Laramie, Wyoming, who was in charge of the work, and requested payment. He had, however, failed, as required by the contract, to submit a payroll with the estimate. Steele notified him by letter to comply with this provision of the contract. Pollia thereupon sent the pay *163 rolls signed by Sharar. They were not in compliance with the requirements of his contract and were returned to him for correction. The payrolls also showed that the wages were not being paid in accordance with the terms of the base contract. Steele then became doubtful of Pollia’s credit standing and conveyed that information to the Regional Office of F.P.H.A. On October 31, 1946, Frank Eubin, a representative of F.P.H.A., wired Nickel to require a performance and payment bond as required by the terms of the subcontract. On November 1, 1946, Pollia was notified by letter that it was necessary for him to furnish this bond and that no payment would be made until such bond was furnished.

The second estimate also was not accompanied by a certified payroll. After the receipt of this estimate, Steele went to Seattle to discuss the matter with Lubin. Lubin was a contracting officer representing the Government. Steele was informed that if payment of the estimate was made without the posting of the bond, it would be Steele’s responsibility and that reimbursement would not be made until the bond was furnished. On the same day, Steele had a conference with Smith, Pol-lia’s attorney and was advised that he doubted Pollia’s ability to make a bond. An attempt was made to raise money for Pol-lia, but it failed when it was discovered that items which Pollia claimed had been paid were in fact not paid. On December 23, 1946, Pollia wired Steele as follows:

“San Francisco, Calif., Dec. 23, 1946.
“J. P. Steele, 617 Grand Ave.
“Due to failure on your part after making numerous promises to make payments to us that are past due we have advised the regional office today by wire that we were stopping operation of work covered by our contract.
“Andrew A. Pollia.”

On December 30, 1946, Steele advised Pollia by letter that his subcontract was terminated in accordance with paragraph three thereof because of his continued refusal to diligently prosecute the work in accordance with the terms of the subcontract.

The trial court’s ruling that the -F.P.H.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Florida Power Corp. v. United States
33 Fed. Cl. 107 (Federal Claims, 1995)
Eastern Trans-Waste of Maryland, Inc. v. United States
27 Fed. Cl. 146 (Federal Claims, 1992)
The United States v. Johnson Controls, Inc.
713 F.2d 1541 (Federal Circuit, 1983)
Health Application Systems v. Hartford Life
381 So. 2d 294 (District Court of Appeal of Florida, 1980)
Parker v. Department of Health, Education, & Welfare
478 F. Supp. 1156 (M.D. Tennessee, 1979)
Gardiner Manufacturing Co. v. United States
479 F.2d 39 (Ninth Circuit, 1973)
H. K. Ferguson Co. v. Nickel Processing Corp.
33 F.R.D. 268 (S.D. New York, 1963)
Sharar v. Pollia
191 F.2d 116 (Tenth Circuit, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
179 F.2d 160, 1950 U.S. App. LEXIS 3683, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nickel-v-pollia-ca10-1950.