All Seasons Water Users Ass'n v. Northern Improvement Co.

399 N.W.2d 278, 1987 N.D. LEXIS 237
CourtNorth Dakota Supreme Court
DecidedJanuary 6, 1987
DocketCiv. 11,256
StatusPublished
Cited by23 cases

This text of 399 N.W.2d 278 (All Seasons Water Users Ass'n v. Northern Improvement Co.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All Seasons Water Users Ass'n v. Northern Improvement Co., 399 N.W.2d 278, 1987 N.D. LEXIS 237 (N.D. 1987).

Opinion

VANDE WALLE, Justice.

All Seasons Water Users Association, Inc. (All Seasons), appealed from the amended judgment of the district court of Bottineau. County which awarded All Seasons $105,372 in damages plus $5,798.48 for costs and disbursements. Northern Improvement Company (Northern) and Firemen’s Insurance Company (Firemen’s) filed a cross-appeal. We affirm in part and remand the case for further consideration by the trial court.

This appeal arises out of a contract entered into between Northern and All Seasons in which Northern agreed to construct and install a rural water pipeline for All Seasons. During the summer of 1977, pursuant to the contract, Northern installed approximately 425 miles of plastic pipe in Bottineau County. The plastic pipe was generally in 40-foot lengths, joined together by a solvent-welding technique. Testimony at trial indicated, and the trial court found, that Northern used excessive solvent or solvent cement in the welding process, and that this caused the pipe to be weakened and led to numerous leaks. The contract required the pipe to be buried at a depth of 7.0 feet; however, numerous sections of the pipeline were buried at more shallow depths.

In its complaint, All Seasons asked for $100,000 in actual damages plus an unspecified amount to compensate it for future damage, interest, attorney fees, and costs and disbursements. It asked that the trial court order replacement of 10 miles of shallowly laid pipe, for replacement of 21 miles of pipe which it claimed had been welded in a negligent manner, and for damages for expenses it had incurred in repairing and replacing sections of the pipe. All Seasons also asked that the bond issued by Firemen’s be liquidated.

The trial court found that 10 miles of pipe was buried at depths more shallow than the 7.0 feet required by the contract, but stated that the pipe was within an acceptable tolerance and thus did not need to be replaced or lowered. The trial court awarded $70,000 to All Seasons for the cost of replacing 3½ miles of pipe which had been welded improperly. The trial court also awarded $16,000 to All Seasons for pipe it had already replaced, and $19,372 for breaks in excess of 20 per year, which number the court found was acceptable. Upon entry of judgment, All Seasons filed a statement of costs and disbursements, claiming $9,415.84, which the court taxed against Northern. Northern filed an objection to many of the costs and the trial court decreased the amount of allowable costs *280 and disbursements to $5,798.48, and entered an amended judgment to reflect the change.

All Seasons raises the following issues on appeal:

1. Whether a contractor who breaches a construction contract by violating the contract specifications regarding the depth pipe is to be buried for a rural water system is liable for damages for the shallow pipe.
2. Whether a rural water system is entitled to damages for replacement of 22 miles of pipe which have repeated breaks due to sloppy workmanship.
3. Whether a rural water system is entitled to damages for repair of breaks in the water line when the breaks are caused by sloppy workmanship.
4. Whether a contractor’s bond should be forfeited as liquidated damages when the contractor breaches the contract and causes significant past and probable future damage.
5. Whether the trial court erred in denying costs for the expenses of expert witnesses.

The trial court made several findings regarding the first issue. It found that 10 miles of pipe is buried above the 7.0-foot depth required by the contract. The court concluded that this constituted a breach of the contract and that Northern was responsible for it. However, the trial court went on to find that the shallowly laid pipe did not need to be replaced or lowered because it was “within an acceptable tolerance.” The court also concluded that All Seasons substantially received the system it had intended.

This court will not reverse a trial court’s finding of fact unless it is clearly erroneous. Rule 52(a), N.D.R.Civ.P. Whether or not a contract has been substantially performed is a question of fact. Robertson Companies, Inc. v. Kenner, 311 N.W.2d 194 (N.D.1981). Thus the trial court’s finding in this regard will not be reversed unless it is clearly erroneous. Cook v. Jacklitch & Sons, Inc., 315 N.W.2d 660 (N.D.1982). A finding of fact is clearly erroneous when the reviewing court considering the entire evidence' is left with a definite and firm conviction that a mistake has been made. Gross v. Sta-Rite Industries, Inc., 336 N.W.2d 359 (N.D.1983). Whether or not the contract has been performed must be determined in view of the entire contract and not one specification. Merrill Iron & Steel, Inc. v. Minn-Dak Seeds, Ltd., 334 N.W.2d 652 (N.D.1983).

Testimony at trial indicated that All Seasons had checked the depth of the pipe at approximately 33 locations. Of these, 22 were buried at 6 feet 6 inches or less. However, there was also testimony that changes in topography due to tillage, erosion, and settling could have contributed to a ground cover of less than the contract-mandated 7.0 feet. In addition, testimony by Ronald French, the project engineer for KBM for the pipeline, Robert Aberle of Northern, and John Madden, a consulting engineer, indicates that the pipe did not need to be lowered.

In determining that the 10 miles of pipe did not need to be replaced or lowered, the trial court found that Northern had breached the contract by burying the pipe at less than the contract-mandated depth. But the trial court implied that Northern had substantially performed the contract and that the proper measure of damages is the cost of making the work conform to the contract because the breach can be remedied without substantial reconstruction of the project. However, the court concluded that the pipe which was too shallowly buried need not be replaced or lowered because it is within an acceptable tolerance. This appears to be a holding by the trial court under the substantial performance doctrine.

The doctrine of substantial performance was commented on by this court very early in its history. In Anderson v. Todd, 8 N.D. 158, 160, 77 N.W. 599, 600 (1898), we stated:

“It is true that the early rule, requiring a technical and literal compliance with the contract as a condition precedent to re *281

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Global Acquisitions, LLC v. Broadway Park Ltd. Partnership
2001 ND 52 (North Dakota Supreme Court, 2001)
Wachter v. Gratech Co., Ltd.
2000 ND 62 (North Dakota Supreme Court, 2000)
Webster v. Regan
2000 ND 18 (North Dakota Supreme Court, 2000)
Towne v. Dinius
1998 ND 162 (North Dakota Supreme Court, 1998)
Jarvis v. Jarvis
1998 ND 163 (North Dakota Supreme Court, 1998)
Circle B Enterprises, Inc. v. Steinke
1998 ND 164 (North Dakota Supreme Court, 1998)
First American Bank West v. Berdahl
556 N.W.2d 63 (North Dakota Supreme Court, 1996)
Reinecke v. Griffeth
533 N.W.2d 695 (North Dakota Supreme Court, 1995)
Throndset v. L.L.S.
485 N.W.2d 775 (North Dakota Supreme Court, 1992)
Ferguson v. Reed
822 P.2d 1287 (Wyoming Supreme Court, 1991)
Sweeney v. Hoff
478 N.W.2d 9 (North Dakota Supreme Court, 1991)
Garbe v. Garbe
467 N.W.2d 740 (North Dakota Supreme Court, 1991)
Ohio Historical Society v. General Maintenance & Engineering Co.
583 N.E.2d 340 (Ohio Court of Appeals, 1989)
All Seasons Water Users Ass'n v. Northern Improvement Co.
417 N.W.2d 831 (North Dakota Supreme Court, 1988)
Farmland Mutual Insurance Co. v. Farmers Elevator, Inc. of Grace City
404 N.W.2d 473 (North Dakota Supreme Court, 1987)
Herzog v. Yuill
399 N.W.2d 287 (North Dakota Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
399 N.W.2d 278, 1987 N.D. LEXIS 237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-seasons-water-users-assn-v-northern-improvement-co-nd-1987.