Robertson Companies, Inc. v. Kenner

311 N.W.2d 194, 32 U.C.C. Rep. Serv. (West) 387, 1981 N.D. LEXIS 391
CourtNorth Dakota Supreme Court
DecidedOctober 23, 1981
DocketCiv. 9953
StatusPublished
Cited by24 cases

This text of 311 N.W.2d 194 (Robertson Companies, Inc. v. Kenner) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robertson Companies, Inc. v. Kenner, 311 N.W.2d 194, 32 U.C.C. Rep. Serv. (West) 387, 1981 N.D. LEXIS 391 (N.D. 1981).

Opinion

PEDERSON, Justice.

Three basic questions presented in this case are: (1) was the unrequested remedy of rescission properly granted; (2) does the remedy of rescission preclude allowing damages for lost profits; and (3) was there sufficient evidence to prove lack of substantial performance. In addition, we are asked to determine whether or not the trial court properly granted interest on loss of profits.

We conclude that the unrequested remedy of rescission was properly granted and that rescission and damages are not mutually exclusive remedies under the Uniform Commercial Code. We further conclude that there was sufficient evidence to prove lack of substantial performance of Robertson’s obligation, and that interest was properly granted on the award of damages. The judgment is affirmed.

In June, 1977, Robertson Companies, Inc. (Robertson), contracted with Kenner to build two galvanized steel buildings on Kenner’s farm. 1 These new buildings were to be completed for October storage of the 1977 sunflower crop. The contract specified that Kenner was to lay the two concrete slabs for the buildings. The concrete slabs were apparently ready for further construction by the end of July, 1977. In mid-September, 1977, a contractor (Contractor I) hired by Robertson appeared at the Kenner farm to proceed with the construction. Contractor I visually inspected the concrete slabs and concluded that one of the slabs was unfit for immediate construction. Whereupon, Contractor I and his crew departed from the Kenner farm, never to return. The deficiencies in the one slab required only minor repairs and were corrected in a couple of hours. The other slab did not require any repair and was ready for construction when Contractor I first arrived at the Kenner farm.

At the time of the 1977 sunflower harvest, the steel buildings had not been erected. Kenner, accordingly, was forced to use temporary storage facilities which were unfit for long-term storage.

Contractor II arrived at the Kenner farm in October or November, 1977, and began erecting the new buildings. One of the two buildings was partially completed when the work was interrupted by a heavy snowstorm. Contractor II left the Kenner farm to complete - another project. He did not return.

Out of the state during the pouring of the slabs and the ensuing events, Kenner returned to North Dakota in mid-November, 1977, to find only one of the two buildings partially completed. Shortly thereafter, Robertson telephoned Kenner to discuss the completion of the buildings. Following the telephone conversation, Robertson sent Contractor III to the Kenner farm to dismantle the partially completed building. The evidence is in dispute as to who wanted the construction halted. The building materials were stored on the Kenner farm for the duration of the winter. Some of the materials were stored in an existing building and the remainder was left outside.

Because the 1977 sunflower crop had to be stored in existing temporary facilities unfit for long-term storage, 2 Kenner was forced to market his crop in an unfavorable winter market. It had previously been the *197 practice of Kenner to store some of his crop through the winter in order to take advantage of higher commodity prices in the spring. Kenner marketed 500,000 pounds of sunflowers in a depressed winter market. 3

In May of 1978, Robertson hired Contractor IV to complete the construction of the new buildings. During this construction, Kenner noticed considerable amounts of white rust on the construction material and so informed Robertson by telephone. Ken-ner also informed Robertson that he would not accept the buildings in their defective condition. Robertson employees visited the Kenner farm to inspect the buildings but took no corrective action. Payment of the unpaid balance on the contract was demanded. Kenner refused to accept the buildings and refused to make the requested payment. There were no further contacts between the two parties until the commencement of this lawsuit on December 8, 1978.

Robertson claims to be entitled to the unpaid balance of the contract purchase price, compensation for dismantling the 1977 partial construction, and other additional erection costs for the work completed in May, 1978. Kenner denys owing anything to Robertson because of the latter’s breach of contract. Kenner claims that Robertson’s delay in erecting the buildings, resulting in disruption of the marketing of the 1977 sunflower crop, and the furnishing of defective materials resulting in exorbitant future maintenance costs, amounts to a substantial breach of contract. Kenner also counterclaimed for loss of profits because of the early sale of the 1977 sunflower crop.

The suit was tried to the court without a jury. The court found that Robertson had not substantially performed the contract and ordered rescission thereof. Although rescission had not been requested by either party, the court based its decision on that part of Rule 54(c), NDRCivP, which provides “every final judgment shall grant the relief to which the party in whose favor it is rendered is entitled, even if the party has not demanded such relief in his pleading.” The court awarded Kenner damages of $12,500 as compensation for losses suffered in the marketing of his sunflower crop during unfavorable conditions in early 1978. This appeal by Robertson followed.

I. RECESSION

The right to rescind a contract is governed by statute. 4 A party is entitled to rescind only if he uses reasonable diligence to rescind promptly and to restore to the other party everything of value which was received under the contract. 5 This court has held that compliance with these rules is a condition precedent to the maintenance of *198 an action to rescind. Volk v. Volk, 121 N.W.2d 701, 706 (N.D.1963). The rule pertaining to prompt rescission, however, does not operate where legal excuse or justification for delay is shown. Lanz v. Naddy, 82 N.W.2d 809 (N.D.1957).

Robertson contends that Kenner failed to comply with the statutory requirement of prompt rescission. The determination of prompt rescission does not depend alone upon the lapse of time, but also upon the circumstances of each particular case. Lanz v. Naddy, supra. The contractual relationship between Kenner and Robertson extended over a considerable period of time. The contracted-for buildings which could have been built in six days were completed almost one year after the execution of the contract. Upon noticing the white rust on the steel panels, Kenner telephoned Robertson informing the latter that he would not accept buildings in that condition. Ken-ner’s refusal to accept such defective buildings was sufficiently prompt to satisfy the statutory requirements. 6 Whether or not notice of rescission is timely is a question of fact. Gimbel v. Kuntz,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yorgo Foods v. Orics Industries
D. New Hampshire, 2011
Overboe v. Odegaard
496 N.W.2d 574 (North Dakota Supreme Court, 1993)
Cober v. Corle
610 A.2d 1036 (Superior Court of Pennsylvania, 1992)
Husky Spray Service, Inc. v. Patzer
471 N.W.2d 146 (South Dakota Supreme Court, 1991)
CHECK CONTROL. INC. v. Shepherd
462 N.W.2d 644 (North Dakota Supreme Court, 1990)
Kline Iron & Steel Co. v. Gray Communications Consultants, Inc.
715 F. Supp. 135 (D. South Carolina, 1989)
Bellemare v. Gateway Builders, Inc.
420 N.W.2d 733 (North Dakota Supreme Court, 1988)
All Seasons Water Users Ass'n v. Northern Improvement Co.
399 N.W.2d 278 (North Dakota Supreme Court, 1987)
D.G. Porter, Inc. v. Fridley
373 N.W.2d 917 (North Dakota Supreme Court, 1985)
Holcomb v. Zinke
365 N.W.2d 507 (North Dakota Supreme Court, 1985)
Heinsohn v. William Clairmont, Inc.
364 N.W.2d 511 (North Dakota Supreme Court, 1985)
Blair v. Boulger
358 N.W.2d 522 (North Dakota Supreme Court, 1984)
Alton's, Inc. v. Long
352 N.W.2d 198 (North Dakota Supreme Court, 1984)
Warren Ehrichs v. Robert D. Kearney
730 F.2d 1170 (Eighth Circuit, 1984)
Cook v. Jacklitch & Sons, Inc.
315 N.W.2d 660 (North Dakota Supreme Court, 1982)
Northwestern Equipment, Inc. v. Cudmore
312 N.W.2d 347 (North Dakota Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
311 N.W.2d 194, 32 U.C.C. Rep. Serv. (West) 387, 1981 N.D. LEXIS 391, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robertson-companies-inc-v-kenner-nd-1981.