Pittsburgh-Des Moines Steel Co., Plaintiff-Counter-Defendant-Appellant v. Brookhaven Manor Water Co., Defendant-Counter-Plaintiff-Appellee

532 F.2d 572, 18 U.C.C. Rep. Serv. (West) 931, 21 Fed. R. Serv. 2d 1007, 1976 U.S. App. LEXIS 12612
CourtCourt of Appeals for the Seventh Circuit
DecidedMarch 2, 1976
Docket75-1009
StatusPublished
Cited by89 cases

This text of 532 F.2d 572 (Pittsburgh-Des Moines Steel Co., Plaintiff-Counter-Defendant-Appellant v. Brookhaven Manor Water Co., Defendant-Counter-Plaintiff-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittsburgh-Des Moines Steel Co., Plaintiff-Counter-Defendant-Appellant v. Brookhaven Manor Water Co., Defendant-Counter-Plaintiff-Appellee, 532 F.2d 572, 18 U.C.C. Rep. Serv. (West) 931, 21 Fed. R. Serv. 2d 1007, 1976 U.S. App. LEXIS 12612 (7th Cir. 1976).

Opinions

PELL, Circuit Judge.

This is an appeal by the Pittsburgh-Des Moines Steel Company (hereinafter PDM) from the district court’s entry of a judgment notwithstanding the verdict against PDM on its complaint for repudiation of contract and for Brookhaven Manor Water Company (hereinafter Brookhaven) on its counterclaim for breach of contract and from the district court’s subsequent adjudgment of damages. The questions raised on appeal are whether the district court erred in entering judgment notwithstanding the verdict in favor of Brookhaven on the liability issue and whether error was committed in the district court’s subsequent assessment of damages against PDM.

The record discloses the following series of events. On July 24, 1968, PDM, a designer, fabricator, and engineer of steel products, submitted a proposal to Brookha-ven for the construction of a one-million-gallon water tank for $175,000. The original proposal incorporated, as terms of payment, 60 percent upon receipt of materials in PDM’s plant, 30 percent upon completion [574]*574of erection, and 10 percent upon completion of testing, or within 30 days after the tank had been made ready for testing. The original terms were not satisfactory to Brook-haven’s president, Irving Betke, and were subsequently changed. The altered payment term provided that 100% of the contract price was due and payable within 30 days after the tank had been tested and accepted. The altered proposal was signed and accepted by Brookhaven on November 26, 1968.

Sometime during the following month Norman Knuttel, PDM’s district manager who had prepared and signed the original and revised proposals, talked to a representative of the Arbanas Construction Company which company had contracted with Brook-haven for the construction of the tank foundation. Knuttel was informed that Brook-haven had received a loan from Diversified Finance Corporation. Although this information as to the receipt of the loan was incorrect, Brookhaven had negotiated with Diversified for a loan for the purpose of the construction which negotiations continued into the following year. Under date of January 3, 1969, PDM’s credit manager wrote Diversified with a copy to Betke which letter in part was as follows:

“[W]e hereby request a letter assuring that $175,000.00 for payment of the referenced project will be held in escrow and fully committed to payment to us upon completion of referenced elevated tank. “As a matter of good business we are holding this order in abeyance until receipt of such notification.”

The contract contained no provision for escrow financing. Brookhaven, through Betke, took no action upon the receipt of the copy of the letter. Subsequently, after further correspondence and meetings, resulting. primarily from Brookhaven’s not having secured a planned loan of $275,-000.00 from Diversified Finance, PDM’s credit manager sent an air mail, special delivery letter to Betke, dated March 19, 1969, which suggested that Betke “mail us your personal guarantee of payment of $175,000.00 as per the contract, to protect us in the interim between now and the time your loan is completed.”

While the contract specified the payment of the amount mentioned no later than 30 days after completion of the tank, it was silent as to any reference to a personal guarantee by Betke. The letter concluded as follows:

“Upon receipt of such guarantee, we could immediately set in motion our shop fabrication which would result in earlier completion of your new tank.
“When your loan is completed we will still require a letter of instructions to be forwarded from you to your bank, or other financial institution which extends this loan, that $175,000.00 is to be held in escrow for disbursement only to Pittsburgh-Des Moines Steel Company in accordance with our contract.”

The construction of the water tower was scheduled to begin on April 15, 1969. A crew had been scheduled for the site three months previously, and a crew was ready to appear there on April 15, 1969. As matters transpired, however, the tank was never installed at Brookhaven’s site. On March 31, 1969, Betke sent PDM Comptroller Harry Kelly his personal financial statement, but he did not send PDM his personal guarantee for the loan. After Betke failed to provide his personal guarantee of the $175,-000.00 contract price, PDM took no further steps toward performance.1 On April 22, 1969, Kelley, PDM Secretary-Treasurer Tom Morris, PDM Sales Manager Dwight Long, and Betke attended a meeting on the Brookhaven premises. Although the record reveals somewhat inconsistent versions of [575]*575the details of that meeting, it appears that Morris told Betke that PDM would complete the fabrication of the tank and deliver it to the job site within a matter of weeks but that Betke replied that he had no need for the tank until the following year.

Further efforts to implement the contract broke down completely after April 22, 1969. Brookhaven’s installation of the reinforced concrete foundation for the tank had been accomplished at a cost to it of $18,895. Subsequent to the March meeting, Brookha-ven purchased additional land and developed two wells which provided an adequate water supply. Brookhaven later sold all its assets, including both equipment and land, to the City of Darien. At the trial of the damages issue, an expert in demolition testified that the cost of removing the reinforced concrete foundation would be about $7,000. On the basis of this testimony, which was proffered upon the legal theory that Brookhaven had a right to recover the cost of the removal, the district court found that the total amount of damages sustained by Brookhaven was the sum of $25,895.00 and entered judgment in its favor for that amount.

1. The Grant of Judgment Notwithstanding the Verdict

A. Compliance with Rule 50(b)

The initial issue in this appeal is whether the district court erred in granting judgment notwithstanding the verdict in favor of Brookhaven. Citing appropriate authority, appellant PDM contends that a motion for directed verdict is a prerequisite to a motion for judgment n. o. v. and that the district court had no judicial power to enter judgment for Brookhaven, inasmuch as the latter had not renewed its motion for a directed verdict at the close of all the evidence nor had it moved for a directed verdict as to its counter-claim.2 Brookhaven argues that matters not raised below cannot be urged for the first time on appeal and that sound policy analysis should induce this court to prevent PDM from gaining a “tactical victor[y] at the expense of substantive interests.” 5A Moore, Federal Practice ¶ 50.08 at 2359 (2d ed. 1975).

We note that PDM, prior to raising on this appeal the question of compliance with Fed.R.Civ.P. 50(b), filed eight written mem-oranda, including one to this court in an earlier effort to gain appellate review, without any focus on the question of the lack of judicial power in the district court to grant judgment n.o.v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koursa, Inc. v. Manroland, Inc.
971 F. Supp. 2d 765 (N.D. Illinois, 2013)
Propulsion Technologies, Inc. v. Attwood Corp.
369 F.3d 896 (Fifth Circuit, 2004)
Reid v. State of New Hampshi
47 F. App'x 5 (First Circuit, 2002)
Top of Iowa Cooperative v. Sime Farms, Inc.
608 N.W.2d 454 (Supreme Court of Iowa, 2000)
Image Technical Services, Inc. v. Eastman Kodak Co.
125 F.3d 1195 (Ninth Circuit, 1997)
Horbach v. Kaczmarek
934 F. Supp. 981 (N.D. Illinois, 1996)
Tourist Village Motel, Inc. v. Massachusetts Engineering Co.
801 F. Supp. 903 (D. New Hampshire, 1992)
John J. Kirlin, Inc. v. Gaco Systems, Inc.
565 A.2d 114 (Court of Special Appeals of Maryland, 1989)
Kline Iron & Steel Co. v. Gray Communications Consultants, Inc.
715 F. Supp. 135 (D. South Carolina, 1989)
Lamborn v. Dittmer
688 F. Supp. 113 (S.D. New York, 1988)
Collins v. State
830 F.2d 692 (Seventh Circuit, 1987)
Collins v. State of Illinois
830 F.2d 692 (Seventh Circuit, 1987)
DeGroft v. Lancaster Silo Co.
527 A.2d 1316 (Court of Special Appeals of Maryland, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
532 F.2d 572, 18 U.C.C. Rep. Serv. (West) 931, 21 Fed. R. Serv. 2d 1007, 1976 U.S. App. LEXIS 12612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittsburgh-des-moines-steel-co-plaintiff-counter-defendant-appellant-v-ca7-1976.