John J. Kirlin, Inc. v. Gaco Systems, Inc.

565 A.2d 114, 80 Md. App. 506, 10 U.C.C. Rep. Serv. 2d (West) 124, 1989 Md. App. LEXIS 180
CourtCourt of Special Appeals of Maryland
DecidedNovember 1, 1989
Docket86, September Term, 1989
StatusPublished
Cited by2 cases

This text of 565 A.2d 114 (John J. Kirlin, Inc. v. Gaco Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John J. Kirlin, Inc. v. Gaco Systems, Inc., 565 A.2d 114, 80 Md. App. 506, 10 U.C.C. Rep. Serv. 2d (West) 124, 1989 Md. App. LEXIS 180 (Md. Ct. App. 1989).

Opinion

KARWACKI, Judge.

This controversy arose from a contract for the design, manufacture and installation of a water purification system at a Howard County facility being constructed for the Bendix Corporation (Bendix). Appellant John J. Kirlin, (Kirlin), the mechanical and plumbing subcontractor for that construction project, entered into a contract with Gaco Systems, Inc. (Gaco), the appellee, by which Gaco agreed to design, fabricate, install and render operational a Deionizing Reverse Osmosis (DIRO) System. Disputes arose during the early stages of performance under the contract. Eventually, Gaco filed a Petition in the Circuit Court for Howard County to Establish a Mechanic’s Lien against Bendix. Kirlin intervened in the action and filed a counterclaim against Gaco for breach of contract. Gaco filed an amended Petition to Establish a Mechanic’s Lien and Complaint in which it asserted a breach of contract claim directly against Kirlin. After Kirlin posted a surety bond to secure payment of any successful claims of Gaco, the court removed the lien against Bendix’s property, and the case *508 proceeded on Gaco’s breach of contract claim and Kirlin’s counterclaim.

At a bench trial, the court concluded that Kirlin had breached the contract by failing to make timely payments to Gaco for services rendered and materials supplied. Judgment in the amount of $138,657.75 was entered in favor of Gaco.

On appeal from that judgment, Kirlin raises the following issues:

I. Did the trial court err in concluding that Kirlin was in breach of the contract and therefore that Gaco’s stoppage of performance was not a repudiation?
II. Did the trial court properly exclude evidence from meetings held by the parties in March of 1986?

In addition, Gaco raises the following issue on cross-appeal:

III. Did the trial court abuse its discretion by not awarding prejudgment interest on damages?

Because we hold that the court improperly excluded relevant evidence as to what transpired at meetings attended by representatives of the parties on March 26 and 27, 1986, we shall vacate the judgment entered against Kirlin and remand the case for further proceedings.

FACTS

On April 17, 1985, Gaco agreed for a price of $645,000 to design, manufacture and install an operational DIB.0 System at Bendix. Payments on account of the contract price were to be made by Kirlin as follows:

—10% of the contract price ($64,500) upon submission of major drawings
—50% of the contract price ($322,500) upon the procurement of vessels and internals
—35% of the contract price ($225,750) upon shipment of equipment
*509 —5% of the contract price ($32,250) upon acceptance of the system, not to exceed 90 days from the date of shipment

The first of the major design drawings submitted by Gaco were rejected by Bendix’s project engineer on May 14, 1985. These were revised and resubmitted by Gaco on June 17, 1985. Other major design drawings were not submitted until September, 1985; nevertheless, Gaco submitted an invoice for the first progress payment due under the contract on June 17, 1985. Gaco procured the vessels and internals for the DIRO System and billed Kirlin for $322,-500 on July 30, 1985.

By the latter part of September 1985, major portions of the DIRO System were ready for shipment to the construction site; however, Kirlin had not made payment on either of the outstanding invoices submitted by Gaco despite repeated demands made by Gaco’s representatives that these delinquencies be remedied. At that point, Gaco insisted that the overdue invoices be satisfied before it would ship any components of the DIRO System. Notwithstanding this threat, Gaco shipped major sections of the DIRO system to Kirlin on or about September 20, 1985, after receiving assurances from Kirlin’s project manager that the overdue account would be promptly satisfied.

On September 25, 1985, Kirlin sent Gaco an unsigned check for $322,500, the amount of the second invoice. Gaco officials testified that, although the check was unsigned, Kirlin’s representatives advised them to deposit the check and that it would be honored by the drawee, Riggs National Bank (Riggs). Gaco negotiated the check on September 27, 1985. The same day Kirlin sent Gaco a second check, this one signed, for the same amount. Gaco negotiated that check on October 3, 1985.

Without advising Kirlin that it had been paid twice on its invoice of $322,500, Gaco continued to press for the payment of its other outstanding invoices ($64,500 for the major drawings and $225,750 following the shipment of the *510 DIRO equipment.) On October 17, 1985, Kirlin issued two more checks, one for $118,680 and the other for $171,500, totalling the $290,250 due on Gaco’s outstanding invoices. Gaco deposited both of these checks and then advised Kirlin that it had negotiated both of its $322,500 checks.

When Riggs learned of its error in honoring Kirlin’s unsigned check for $322,500, it credited Kirlin’s account for that amount on October 28, 1985. Meanwhile, Kirlin learned from its bank that Gaco had failed to endorse its $118,680 check which Gaco had deposited for collection. Kirlin instructed its bank not to honor the check pending further discussion with Gaco.

Representatives of Kirlin and Gaco met on October 30, 1985, to discuss a refund by Gaco of the overpayment it had received. Kirlin demanded that Gaco refund $296,700 which would have left Gaco fully satisfied on the amounts it had invoiced under the original contract plus paying $12,000 on a. disputed change order where Gaco claimed $40,800 for polishing storage tanks. Gaco would only agree to refund $235,000. After Gaco delivered its check to Kirlin in the amount of $235,000, Kirlin stopped payment on its earlier $118,680 check issued to Gaco which had been presented to its bank for collection but which had not been honored pursuant to Kirlin’s instruction. When Gaco learned of this stop payment order, it stopped payment on its $235,000 check.

By letter of December 12, 1985, Kirlin notified Gaco that Riggs had recognized its error in honoring the unsigned check for $322,500 and that Kirlin’s account at Riggs had been re-credited with that amount. Kirlin advised Gaco that it should therefore reimburse Riggs. Gaco refused to do so, and Riggs sued Gaco in Niagara County, New York to recover the $322,500 which Gaco had received as the result of Riggs’s error. The New York Court entered summary judgment against Gaco on March 6, 1986, in the amount of $322,500 together with interest thereon of $6,679.73 and costs. That judgment was satisfied by Gaco.

*511 On March 20, 1986, Gaco advised Kirlin that it was discontinuing work on the Bendix project and that it would not return unless Kirlin immediately paid $205,530.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Waller v. Maryland National Bank
620 A.2d 381 (Court of Special Appeals of Maryland, 1993)
Burwell v. Easton Memorial Hospital
577 A.2d 394 (Court of Special Appeals of Maryland, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
565 A.2d 114, 80 Md. App. 506, 10 U.C.C. Rep. Serv. 2d (West) 124, 1989 Md. App. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-j-kirlin-inc-v-gaco-systems-inc-mdctspecapp-1989.