Yorgo Foods v. Orics Industries

CourtDistrict Court, D. New Hampshire
DecidedSeptember 29, 2011
Docket08-CV-438-SM
StatusPublished

This text of Yorgo Foods v. Orics Industries (Yorgo Foods v. Orics Industries) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yorgo Foods v. Orics Industries, (D.N.H. 2011).

Opinion

Yorgo Foods v. Orics Industries 08-CV-438-SM 09/29/11 UNITED STATES DISTRICT COURT

DISTRICT OF NEW HAMPSHIRE

Yorgo Foods, Inc., Plaintiff

v. Case No. 08-cv-438-SM Opinion No. 2 011 DNH 145 Orics Industries, Inc., Defendant

MEMORANDUM OF DECISION

The plaintiff, Yorgo Foods, Inc., ("Yorgo"), is in the

business of producing and selling Middle Eastern food products

(hummus, tabbouleh, etc.). The defendant, Orics Industries, Inc.

("Orics"), manufactures and sells food packaging equipment.

Seeking to increase productivity, Yorgo purchased a food

packaging machine from Orics. But, due to extended delays in

delivery, Yorgo cancelled the purchase. Yorgo requested return

of its substantial deposit and, when Orics failed to return the

funds, Yorgo brought suit, asserting breach of contract and

various related causes of action. Orics, in turn, counterclaimed

for breach of contract. The case was tried before the court on

the merits. The pertinent facts are largely uncontested, with

some exceptions related to alleged oral conversations and other

interactions between the parties. Relevant Facts

On December 12, 2006, Yorgo agreed to buy an S-40-DX

automated cup filling and sealing machine from Orics, for

$150,000.00. That agreement was memorialized in a document

entitled "Proposal for S-40-DX-lup Packaging Machine, Quote

#62890" (hereafter referred to as the "Agreement").

The Agreement called for payment in several stages: 50% of

the purchase price was due immediately as a down payment; 40% was

due on "acceptance prior to shipment," and the remaining 10% was

due 30 days after shipment. The Agreement also provided that

"[d]elay in receipt of down payment and/or delay of subsequent

progress payments may cause production and/or shipment delays."

Completion of the machine and shipment was to occur in "14 to 16

weeks based on removal of all contingencies," though the

Agreement provides no hint as to what "removal of all

contingencies" means.

Shortly after Yorgo signed the Agreement, Orics sent an

invoice and, on January 3, 2007, Yorgo made the required down

payment. Orics began the design and fabrication process, but at

some point after February of 2007, an Orics salesman, Kevin Meek,

suggested an addition that would allow the machine to not only

fill containers with flowable products (e.g., hummus), as

2 originally contemplated, but also with non-flowable products like

salads (e.g., tabbouleh). Mr. Bechara El-Khoury, Yorgo's

principal, had several conversations with Orics' sales

representative about the potential change. Eventually, El-Khoury

agreed to add the additional component, an integrated scale and

vibratory filler for non-flowable product. That modification

required some redesign by Orics, as well as mechanical

alterations to the S-40-DX.

Yorgo could have reasonably expected the machine, as

originally ordered, to be completed by either the end of March,

or the end of April, 2007 (depending on whether Orics began work

when the Agreement was signed by Yorgo, on December 12, 2006, or

after the down payment was received, on January 4, 2007) . But,

by May it was still not completed. Given the discussions about a

potential change, however, Orics says it justifiably stopped

working on the machine at some point after March, awaiting El-

Khoury' s final decision about adding the vibratory filler and

scale.

The specified time for delivery of the original machine

expired in April, but the Agreement was amended on July 12, 2007,

as documented by a "Revised Order," which was sent to Yorgo. The

Revised Order referenced the original order date of December 13,

3 2006, and the original order number: #6289C. It recited that

Orics would "[u]pgrade equipment to new customer request" by

incorporating the vibratory filler and scale [to be obtained from

a third party supplier — Ohlson Co.] and Orics would "extend

machine length to fit Net-Weigh System." Def. Ex. A, p. 178.

The changes increased the total purchase price to $252,000.00,

and Orics expected an additional down payment of $51,250.00. The

original delivery term of 14 to 16 weeks was not specifically

modified. Yorgo made the additional down payment on September

21, 2007. Orics says that "[o]nce [it] received the additional

down payment money, work on the machine continued in earnest."

Defendant's Post-Trial Brief, at 5.

Anticipating the addition of a vibratory scale, Orics had

already contacted Ohlson Scales, in May of 2007, to discuss

procurement of the necessary component. Ohlson is a well-known

manufacturer of such equipment, and Orics planned to buy the

component from Ohlson, then integrate it into the S-40-DX

machine. Ohlson provided Orics with an initial quote for the

scale in May and, after some exchange of technical data between

Orics and Ohlson, Ohlson sent a revised proposal to Orics in July

of 2007. Ohlson was prepared to build and deliver the required

filler and scale in 12 to 14 weeks. But, although the Agreement

between Yorgo and Orics was amended in July, and Yorgo paid the

4 additional deposit on September 21, Orics did not actually place

an order for the Ohlson filler and scale until November 16.

El-Khoury was anxious to take delivery of the machine and

probably expected that integration of the Ohlson scale would not

delay completion by more than a few weeks. He was not told by

anyone at Orics that work on his machine would stop and not begin

again until an additional deposit was received, or that an

extended delay in delivery would necessarily accompany the

modification. By November of 2007, El-Khoury was particularly

upset that nearly a year had passed and the machine he ordered

was not yet complete, even allowing for additional time to make

the requested modification. (He of course did not know that the

Ohlson scale had just been ordered that month.)

On December 6, 2007, Attorney Victor Dahar wrote to Orics on

behalf of Yorgo to notify Orics that, due to its failure to

deliver the ordered machine, Yorgo was cancelling the contract

and requesting a refund of its deposit. Mr. Ori Cohen, President

of Orics, testified that he did not recall seeing that letter,

but Kevin Meek, the Orics' salesperson, said he received a copy

of the letter and discussed it with Cohen. Whether Cohen did or

did not see the letter, it was ignored by Orics.

5 A month later, on January 9, 2008, El-Khoury's niece, who

worked for Yorgo, sent an email to Cohen, inquiring, again, as to

when the ordered machine would be finished. Cohen responded on

January 11 that Orics was still waiting for the Ohlson scale,

which was expected to take another three to four weeks. Cohen

did not disclose that Orics had yet to review and approve

engineering drawings Ohlson had submitted to Orics in December —

a necessary prerequisite to Ohlson's completing the filler/scale.

Orics did not provide Ohlson with approved drawings until January

29, 2008. Yorgo, however, did not press its previously announced

election to cancel the Agreement for failure to deliver, and both

parties continued on, tacitly agreeing that the cancellation

communicated by Attorney Dahar was withdrawn and the deal

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wortley v. Camplin
333 F.3d 284 (First Circuit, 2003)
Lanners v. Whitney
428 P.2d 398 (Oregon Supreme Court, 1967)
Griswold v. Heat Corporation
229 A.2d 183 (Supreme Court of New Hampshire, 1967)
Spring Motors Distributors, Inc. v. Ford Motor Co.
489 A.2d 660 (Supreme Court of New Jersey, 1985)
Clapp v. Goffstown School District
977 A.2d 1021 (Supreme Court of New Hampshire, 2009)
Indiana Glass Co. v. Indiana Michigan Power Co.
692 N.E.2d 886 (Indiana Court of Appeals, 1998)
Superior Boiler Works, Inc. v. R.J. Sanders, Inc.
711 A.2d 628 (Supreme Court of Rhode Island, 1998)
Robertson Companies, Inc. v. Kenner
311 N.W.2d 194 (North Dakota Supreme Court, 1981)
Adams v. Bradshaw
599 A.2d 481 (Supreme Court of New Hampshire, 1991)
J & M Lumber & Construction Co. v. Smyjunas
20 A.3d 947 (Supreme Court of New Hampshire, 2011)
Hydraform Products Corp. v. American Steel & Aluminum Corp.
498 A.2d 339 (Supreme Court of New Hampshire, 1985)
Centronics Corp. v. Genicom Corp.
562 A.2d 187 (Supreme Court of New Hampshire, 1989)
Guaraldi v. Trans-Lease Group
617 A.2d 648 (Supreme Court of New Hampshire, 1992)
Bailey v. Sommovigo
631 A.2d 913 (Supreme Court of New Hampshire, 1993)
Daigle v. City of Portsmouth
630 A.2d 776 (Supreme Court of New Hampshire, 1993)
Thompson v. H.W.G. Group, Inc.
664 A.2d 489 (Supreme Court of New Hampshire, 1995)
Business Publication, Inc. v. Stephen
666 A.2d 932 (Supreme Court of New Hampshire, 1995)
Barrows v. Boles
687 A.2d 979 (Supreme Court of New Hampshire, 1996)
Milford Lumber Co. v. RCB Realty, Inc.
780 A.2d 1259 (Supreme Court of New Hampshire, 2001)
Town of Nottingham v. Newman
785 A.2d 891 (Supreme Court of New Hampshire, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Yorgo Foods v. Orics Industries, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yorgo-foods-v-orics-industries-nhd-2011.