Hanover Insurance Company v. Ameribuilt Buildings, Inc.

CourtDistrict Court, D. North Dakota
DecidedJuly 27, 2022
Docket1:19-cv-00046
StatusUnknown

This text of Hanover Insurance Company v. Ameribuilt Buildings, Inc. (Hanover Insurance Company v. Ameribuilt Buildings, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hanover Insurance Company v. Ameribuilt Buildings, Inc., (D.N.D. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NORTH DAKOTA

The Hanover Insurance Company, as Subrogee of Estvold Oilfield Services, Inc. and Estvold Hot Oil Service, Inc.,

Plaintiff, ORDER

vs. Case No. 1:19-cv-46

Ameribuilt Buildings, Inc., Lake Country Contractors, John Bouvette, Construction With R&R, LLC, and Dave Rud,

Defendants.

Before the Court are two motions for summary judgment.1 The first motion was filed by Defendant Ameribuilt Buildings, Inc. (“Ameribuilt”) on September 9, 2021. Doc. No. 38. On September 30, 2021, Plaintiff The Hanover Insurance Company, as Subrogee of Estvold Oilfield Services, Inc., and Estvold Hot Oil Service, Inc. (collectively, “Hanover”) filed its response. Doc. No. 48. Ameribuilt filed its reply on October 13, 2021. Doc. No. 54. The second motion was filed by Lake Country Contractors (“Lake Country”) and John Bouvette (“Bouvette”) (together, “Lake Country/Bouvette”) on September 13, 2021. Doc. No. 44. Hanover filed its response on October 6, 2021. Doc. No. 52. On October 29, 2021, Lake Country/Bouvette filed its reply. Doc. No. 56. For the reasons below, the motions are granted in part and denied in part. I. BACKGROUND This action centers on the collapse of a pole barn during a high windstorm in July 2016. The parties dispute, among other things, what caused the collapse of the pole barn. Hanover asserts

1 Defendants Construction With R&R (“R&R”) and Dave Rud (“Rud”) (collectively, referred to as “R&R/Rud”) filed a motion for summary judgment on September 9, 2021 (Doc. No. 42), but later withdrew the motion. Doc. No. 84. that the pole barn’s collapse was caused by the allegedly negligent construction of the truss-to- column connections and the Defendants’ failure to identify these allegedly negligent connections. See Doc. No. 19, ¶¶ 20-21, 29, 34-35, 40, 42-47. Accordingly, Hanover initiated the action, asserting contract and tort claims against Ameribuilt, R&R/Rud, and Lake Country/Bouvette. Ameribuilt is a corporation that provides materials for buildings. Ameribuilt sold the

materials for the pole barn at issue here and hired a subcontractor to construct the pole barn. Lake Country/Bouvette provides construction services and was hired by Ameribuilt to construct the pole barn. Doc. No. 46-1, p. 6. R&R/Rud sold Ameribuilt buildings, and in this case, sold the pole barn to Estvold Oilfield Services, Inc. and Estvold Hot Oil Service, Inc. (collectively, the “Estvold Corporations”) and/or Jake Estvold (“Estvold”).2 Doc. No. 49-5, p. 4. The Estvold Corporations insured the pole barn, through an insurance policy with Hanover.3 Doc. No. 40-4, pp. 3-4. The Sale of the Pole Barn. At some point, Estvold called Rud wanting to purchase a building. Rud sells Ameribuilt buildings, so he inquired about certain building specifications and filled out a customer proposal, dated February 20, 2012.4 Doc. No. 49-4, p. 1.

The customer proposal lists a “90 mph wind load” under the Accessories section. Doc. No. 49-4, p. 1. The 90 mile an hour wind load was in the proposal “[t]o assure the customer that’s what

2 In the amended complaint, Hanover alleges that the Estvold Corporations contracted with Ameribuilt for the construction of the pole barn at issue. Doc. No. 19, ¶ 9. Rud and Bouvette, however, considered Jake Estvold as the customer of the project. Doc. No. 49-5, p. 4; 46-1, p. 7.

3 Pursuant to this insurance policy, when the pole barn collapsed, Hanover paid money to or on behalf of the Estvold Corporations and became the subrogee to their rights and claims. See Doc. No. 19, ¶¶ 16-17. As such, Hanover brings tort and contract claims against the Defendants. See Doc. No. 19, ¶¶ 18-48.

4 The parties dispute whether Rud is an Ameribuilt employee. The Court addresses the facts supporting each party’s arguments more in depth in its analysis. he was going to get,” according to Rud. Doc. No. 49-5, p. 3. Rud acknowledged, however, that without stamped engineer plans, there was no way to verify if the building meets the wind load requirement. Id. Although Rud offered Estvold stamped plans for the pole barn, Estvold declined to get stamped plans. On or about March 30, 2012, Ameribuilt and Estvold executed a contract, numbered 3621

(the “March 30 Contract”). Doc. No. 40-1, p. 1. The March 30 Contract described the pole barn as an “AB 80 Heated Shop.” Id. Additionally, Ameribuilt agreed to “to furnish labor and materials” for $301,598, paid as follows: Down Payment (to sales representative) $31,598 On Delivery $200,000 Frame Up $65,000 On Completion $5,000

Id. The March 30 Contract also provides that Ameribuilt “is not liable under any circumstances for consequential damages, including, but not limited to, any damages relating to the completion date.” Id. While it does not name a specific subcontractor, Lon Isaacson, who is Ameribuilt’s President, acknowledged that Ameribuilt’s job was to “provide the materials and bring on an erector to actually build the building.” Doc. No. 43-5, p. 10. Indeed, typically after the parties sign this type of contract, Ameribuilt then schedules a date for the “delivery of the building” and hires a subcontractor for the project. Id., p. 12. The Construction of the Pole Barn. Ameribuilt ultimately retained Lake Country/Bouvette as the subcontractor to construct the pole barn. Doc. No. 46-1, p. 7. To that end, Ameribuilt and Lake Country/Bouvette executed a building labor proposal (the “Lake Country Subcontract”). In the Lake Country Subcontract, Lake Country/Bouvette agreed “to erect per specifications on contract #3621 the Jake Estovold [sic] building project located at New Town N.D.”5 Doc. No. 40-3, p. 1. For the work, Lake Country would be paid somewhere between $85,000-$88,000. Id. During the construction phase, Ameribuilt, Lake Country/Bouvette, R&R/Rud,6 and Estvold each had different roles. For example, Ameribuilt provided Lake Country/Bouvette with general instructions as to how to construct the pole barn in the form of building drawings, which

provided the spacing between poles and the height of the rafters, among other things.7 Doc. No. 46-1, p. 13. In addition to the building drawings, Ameribuilt provided Lake Country/Bouvette with the materials to build the pole barn. Doc. No. 46-1, p. 12. More specifically, Ameribuilt provided columns, trusses, steel, insulation, and nails. Most of these materials were shipped to the building site, and all the materials were onsite once Lake Country/Bouvette arrived to begin construction. Doc. No. 46-1, p. 12. For its part, Lake Country/Bouvette erected the pole barn which included “drilling the holes, setting the poles, squaring up the building, putting all the purlins on, rafters on, the steel on the outside, the garage doors, the windows, insulating it and tinning the inside.” Doc. No. 46-1,

p. 11. Additionally, Lake Country/Bouvette attached the trusses to the columns of the structure, in what is called a “truss-to-column” connection.8 Id., p. 12. The parties dispute how many and what type of nails Lake Country/Bouvette used in the truss-to-column connections in this case.

5 The parties dispute whether Lake Country/Bouvette knew about any specific purposes for which the pole barn was intended. The Court addresses the facts supporting each party’s arguments more in depth in its analysis.

6 The parties dispute R&R/Rud’s role in the construction of the pole barn. The Court therefore will address the facts supporting each party’s arguments more in depth in its analysis.

7 Apart from the drawings, however, no one from Ameribuilt told Lake Country/Bouvette how to construct the buildings. Doc. No. 46-1, p. 13.

8 To complete a truss-to-column connection, generally, a builder cuts two pieces out of the column, drops the truss into the opening, and then secures the truss with nails. Doc. No. 46-1, p. 13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Torgerson v. City of Rochester
643 F.3d 1031 (Eighth Circuit, 2011)
Merle A. Glawe v. George Rulon
284 F.2d 495 (Eighth Circuit, 1960)
Nunn v. Noodles & Co.
674 F.3d 910 (Eighth Circuit, 2012)
Donald G. Cousineau v. Norstan, Inc.
322 F.3d 493 (Eighth Circuit, 2003)
Paul Schilf v. Eli Lilly & Company
687 F.3d 947 (Eighth Circuit, 2012)
Larson v. Kubisiak
1997 ND 22 (North Dakota Supreme Court, 1997)
Clarys v. Ford Motor Co.
1999 ND 72 (North Dakota Supreme Court, 1999)
Steiner v. Ford Motor Co.
2000 ND 31 (North Dakota Supreme Court, 2000)
Rogstad v. Dakota Gasification Co.
2001 ND 54 (North Dakota Supreme Court, 2001)
Doan Ex Rel. Doan v. City of Bismarck
2001 ND 152 (North Dakota Supreme Court, 2001)
Olander Contracting Co. v. Gail Wachter Investments
2002 ND 65 (North Dakota Supreme Court, 2002)
Kimball v. Landeis
2002 ND 162 (North Dakota Supreme Court, 2002)
Superior, Inc. v. Behlen Mfg. Co.
2007 ND 141 (North Dakota Supreme Court, 2007)
Barbie v. Minko Construction, Inc.
2009 ND 99 (North Dakota Supreme Court, 2009)
Leno v. K & L Homes, Inc.
2011 ND 171 (North Dakota Supreme Court, 2011)
Gronneberg v. Hoffart
466 N.W.2d 809 (North Dakota Supreme Court, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
Hanover Insurance Company v. Ameribuilt Buildings, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/hanover-insurance-company-v-ameribuilt-buildings-inc-ndd-2022.