Donald G. Cousineau v. Norstan, Inc.

322 F.3d 493, 2003 U.S. App. LEXIS 3918, 2003 WL 882355
Court of Appeals for the Eighth Circuit·Decided March 6, 2003·No. 01-3505·Published·Cited by 14 cases

Opinion

RILEY, Circuit Judge.

Norstan, Inc. (Norstan) appeals the district court’s 1 grant of summary judgment in favor of Donald G. Cousineau (Cousi-neau). Cousineau sought damages from Norstan relating to a dispute over sales commissions. Norstan contractually agreed to pay Cousineau twenty-five percent of the gross margin on-all “guaranteed revenue” from the equipment and service outsourcing contracts Cousineau negotiated for Norstan. Norstan argues two of the three sales contracts Cousineau negotiated had lower “guaranteed revenue” than asserted by Cousineau, thereby reducing the commissions owed to Cousi-neau. We disagree and affirm.

I. BACKGROUND

Norstan provides telecommunication equipment and consulting and management services. Cousineau marketed outsourcing contracts for Norstan’s services. In 1997, Cousineau transferred from Nor- *495 stan’s Montreal, Quebec, office to its Plymouth, Minnesota office. Cousineau’s title became Director of Strategic Alliances; however, he continued to focus exclusively on selling outsourcing contracts. At that time, the parties negotiated a new contract (Letter Agreement) dated July 25, 1997, providing that Cousineau would receive twenty-five percent of the gross margin on all “guaranteed revenue” for the initial term of the outsourcing contracts he negotiated for Norstan. The Letter Agreement further provides that any changes made to the outsourcing contracts within ninety days of execution are included in the final commission calculation.

Cousineau negotiated three outsourcing contracts before leaving Norstan. Cousi-neau alleged Norstan breached the Letter Agreement by failing to pay him all the commissions owed on two of the contracts: (1) the Grandview contract, and (2) the AmerUs contract. Cousineau filed claims for breach of contract, unjust enrichment, and failure to pay wages promptly in violation of Minn.Stat. § 181.14 (1998). Nor-stan counterclaimed, contending Cousineau was overpaid and had misrepresented the commissions and information to both Grandview and AmerUs. Specifically, Norstan alleged fraud, fraudulent concealment, negligent misrepresentation, breach of fiduciary duty, unjust enrichment, and breach of contract.

The district court granted Cousineau summary judgment on his breach of contract and section 181.14 claims, while dismissing Cousineau’s unjust enrichment claim and Norstan’s counterclaims. The district court awarded Cousineau $699,817.85, which included unpaid commissions, prejudgment interest, penalties, attorney fees and costs.

On appeal, Norstan contends the district court erred in granting Cousineau summary judgment because (1) a modification to the Grandview contract reduced the amount of commissions owed, and (2) the AmerUs contract did not contain a required minimum number of long distance minutes, which reduced the commissions sought by Cousineau. Norstan also argues the district court erred in dismissing Norstan’s counterclaims and in awarding Cousineau prejudgment interest, penalties, attorney fees and costs.

II. DISCUSSION

We review the grant or denial of summary judgment de novo. See Calder v. TCI Cablevision of Mo., Inc., 298 F.3d 723, 728 (8th Cir.2002). “Summary judgment is proper where the evidence, when viewed in the light most favorable to the nonmoving party, indicates that no genuine issue of material fact exists and that the moving party is entitled to judgment as a matter of law.” Id.; Fed.R.Civ.P. 56(c).

A. Grandview Contract

Over the course of several months, Cousineau negotiated a contract with Grandview for telecommunication services and equipment. The primary contact person from Grandview with whom he negotiated was Martina Clemens (Clemens). Clemens was a vice president at Grand-view, the sister-in-law of Grandview’s president and CEO, and responsible for Grand-view’s contract negotiations with Norstan. At the conclusion of the negotiations, the contract contained a “termination for convenience” clause, whereby Grandview could terminate the contract at the end of two years, without cause, by giving six months notice. In that event, Grandview would be subject to a specified amount of “stranded costs.” Otherwise, the contract contemplated a service agreement for six years.

After executing the contract on June 11, 1998, Cousineau submitted his commission *496 request based on a calculation of the revenue for the full six years of the contract. However, Norstan determined the “guaranteed revenue” based on only two years because of the termination clause. Cousi-neau then sought and received permission from Norstan to negotiate with Grandview to eliminate the termination clause from the contract. Cousineau talked to Clemens, and Clemens agreed to eliminate the termination clause. On August 13, 1998, Clemens initialed a single redlined page from the contract, which contained the deleted termination clause. On August 25, 1998, Jim Guthrie, Cousineau’s supervisor, also initialed the redlined page, after speaking to Clemens, who confirmed she intended to delete the termination clause in exchange for other contract provisions. Norstan suggests Cousineau and Clemens actually negotiated some additional changes at the same time, which never took effect and were not part of the -written redlined page. In mid-September 1998, Norstan understood Grandview did not want the two-year termination for convenience clause in the contract. However, by September 24, 1998, Grandview sought to reinstate the termination clause, and Norstan decided that it was “in the best interests of both parties that the clause for convenience be kept in the contract.”

Did the August actions constitute an effective modification of the contract for purposes of calculating Cousineau’s commissions, as a matter of law? Cousineau argues the redlined page of the contract is unambiguous and the changes speak for themselves; therefore, no extrinsic evidence need be considered. Norstan contends the modification was ineffective because it violated the contract’s modification procedure. Cousineau argues an executive from each company responsible for negotiating the contract initialed and dated the appropriate portion of the redlined page, thereby effecting a binding modification. Cousineau further replies that the modification procedure was not utilized, in this instance, because that procedure required use of a committee, which had not yet been formed, and later modifications were made without using a committee.

“We review the district court’s interpretation of the contract and the grant of summary judgment de novo. ‘Unambiguous contract language must be construed according to its plain and ordinary meaning.’” Ma pes v. MTR Gaming Group, Inc., 299 F.3d 706, 707 (8th Cir.2002) (citing Minnesota state law) (internal citations omitted). “We review de novo the trial court’s determination that the contracts were unambiguous.” Winthrop Res. Corp. v. Stanley Works,

Free access — add to your briefcase to read the full text and ask questions with AI

Donald G. Cousineau v. Norstan, Inc., 322 F.3d 493, 2003 U.S. App. LEXIS 3918, 2003 WL 882355 (8th Cir. 2003).

322 F.3d 493 (Donald G. Cousineau v. Norstan, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Honda v. Yoshida
Superior Court of Guam, 2012
American Steamship Co. v. Hallett Dock Co.
862 F. Supp. 2d 919 (D. Minnesota, 2012)
Sandra Kemper v. St. Louis County
365 F. App'x 37 (Eighth Circuit, 2010)
Harold H. Huggins Realty, Inc. v. FNC, INC.
575 F. Supp. 2d 696 (D. Maryland, 2008)
Bancinsure, Inc. v. Marshall Bank, N.A.
453 F.3d 1073 (Eighth Circuit, 2006)
Abc, Inc. v. Nameloc, Inc.
362 F.3d 449 (Eighth Circuit, 2004)
Yoram Raz v. United States
Eighth Circuit, 2003