Olander Contracting Co. v. Gail Wachter Investments

2002 ND 65, 643 N.W.2d 29, 2002 N.D. LEXIS 80, 2002 WL 554733
CourtNorth Dakota Supreme Court
DecidedApril 16, 2002
Docket20010086
StatusPublished
Cited by75 cases

This text of 2002 ND 65 (Olander Contracting Co. v. Gail Wachter Investments) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olander Contracting Co. v. Gail Wachter Investments, 2002 ND 65, 643 N.W.2d 29, 2002 N.D. LEXIS 80, 2002 WL 554733 (N.D. 2002).

Opinions

SANDSTROM, Justice.

[¶ 1] The City of Bismarck (“Bismarck”) appealed a judgment and orders entered in an action brought by Olander [32]*32Contracting Co. (“Olander”) against Bismarck, Gail Wachter d/b/a Gail Wachter Investments (‘Wachter”), and Dakota Sand and Gravel, Inc.1 Wachter and Olan-der cross-appealed. We affirm.

[¶2] In 1997, Olander, Wachter, and Bismarck entered into a water and sewer construction contract including, among other things, connecting a ten-inch sewer line from Wachter’s housing development to Bismarck’s existing 36-inch concrete sewer main and installing a manhole at the connection, to be paid for by Wachter. Olander installed the manhole, but it collapsed within a few days. Olander installed a second manhole, with a larger base supported by pilings, but it failed a few days after it was installed. Olander then placed a rock bedding under the sewer main, replaced 78 feet of the existing concrete pipe with PVC pipe, and installed a manhole a third time on a larger base.

[¶ 3] Olander sued Wachter and Bismarck for damages of $456,536.25 for extra work it claims it was required to perform to complete its contract. Wachter answered, counterclaimed against Olander, and cross-claimed against Bismarck. Bismarck answered, counterclaimed against Olander, cross-claimed against Wachter, and demanded a jury trial on all issues.

[¶ 4] The jury returned a special verdict finding Olander performed “extra work/unforeseen work ... for which it is entitled to be compensated in excess of the contract price” in the amount of $220,849.67, to be paid by Bismarck; Wachter was not required to pay Olander any of the $6,600 it had withheld for delay in completing the project; neither Olander nor Wachter breached its contract with Bismarck; and Olander should be paid interest on its damages. The trial court denied Bismarck’s post-trial motion for judgment as a matter of law or a new trial. Judgment was entered in favor of Olander against Bismarck for $275,462, which included $220,850 on the jury verdict, prejudgment interest of $44,544 from November 11, 1997, and costs of $10,068. The judgment dismissed Olander’s claims against Wachter, Bismarck’s claims against Wachter, and Wachter’s claims against Bismarck. Bismarck appealed, and Olander and Wachter cross-appealed.

[¶ 5] On appeal, Bismarck contends Olander’s claims against it should be dismissed because Bismarck owed Olander no duty under the contract and Olander failed to satisfy its burden of proof, and contends it should be granted a new trial because the court erred in dismissing Bismarck’s negligence claims, the court erred in conducting the trial, and the verdict was inconsistent with the evidence.

[¶ 6] On cross-appeal, Olander contends the trial court erred in dismissing its argument that under United States v. Spearin, 248 U.S. 132, 54 Ct.Cl. 187, 39 S.Ct. 59, 63 L.Ed. 166 (1918), the contract included implied warranties of fitness and suitability of the plans and specifications furnished by Bismarck, and the court erred in interpreting and applying this State’s prompt payment statute in N.D.C.C. ch. 13-01.1.

[¶ 7] On cross-appeal, Wachter contends there was no reversible error below. Alternatively, Wachter contends that (1) the trial court erred in dismissing Wachter’s cross-claim against Bismarck, (2) Olander had a duty to insure and indemnify Wachter, and (3) Wachter had no duty to pay for extra work.

[33]*33[¶ 8] The trial court had jurisdiction under N.D. Const, art. VI, § 8, and N.D.C.C. § 27-05-06. The appeals were timely under N.D.R.App.P. 4(a). This Court has jurisdiction under N.D. Const, art. VI, §§ 2 and 6, and N.D.C.C. § 28-27-01.

I

A

[¶ 9] Bismarck contends it should have been granted summary judgment. Summary judgment is a procedural device for speedy disposition of a controversy without a trial if no dispute exists as to either the material facts or the inferences to be drawn from undisputed facts, or if resolving disputed facts would not change the result, and either party is entitled to judgment as a matter of law. Jaskoviak v. Gruver, 2002 ND 1, ¶ 11, 638 N.W.2d 1. On appeal, we review the evidence in the light most favorable to the party opposing a motion for summary judgment, giving that party the benefit of all favorable inferences that reasonably can be drawn from the evidence. Id. If a case goes to trial after a motion for summary judgment is denied, the question of whether the trial court erred in denying summary judgment is moot; the appropriate question on appeal is whether the trial court erred in denying the movant’s subsequent motion for judgment as a matter of law. Berg v. Dakota Boys Ranch Ass’n, 2001 ND 122, ¶¶ 10-11, 629 N.W.2d 563.

[¶ 10] Bismarck contends it should have been granted summary judgment of dismissal, arguing (a) the trial court erred in refusing to interpret the contract and in “passing] the task of interpreting the contract to the jury”; (b) Bismarck had no duty to pay for dander’s work, because the contract placed responsibility for payment for all work on Wachter, and Wachter paid for extra work before the manhole failures; (c) the contract required Olander “to complete the work. on time and in accordance with project specifications” and “[n]o language in the contract allowed extra payments to Olander for mere completion of the contract work”; and (d) the contract made Olander responsible for job delays and costs associated with job delays.

[¶ 11] We recently addressed the construction of written agreements:

If the intent of the parties can be ascertained from the agreement alone, interpretation of the contract is a question of law. Thus, an unambiguous contract is particularly amenable to summary judgment. However, if the terms of the contract are ambiguous, extrinsic evidence regarding the parties’ intent may be considered, and the terms of the contract and parties’ intent become questions of fact. When two good arguments can be made for either of two contrary positions as to the meaning of a term in a document, an ambiguity exists.

Garofalo v. Saint Joseph’s Hosp., 2000 ND 149, ¶ 7, 615 N.W.2d 160 (citations omitted). “Whether or not a contract is ambiguous is a question of law.” Des Lacs Valley Land Corp. v. Herzig, 2001 ND 17, ¶ 9, 621 N.W.2d 860. “A determination of ambiguity is but the starting point in the search for the parties’ ambiguously expressed intentions, which are questions of fact to be determined with the aid of extrinsic evidence.” Bohn v. Johnson, 371 N.W.2d 781, 788 (N.D.1985).

[¶ 12] Section (6) of the contract provides, in part:

The DEVELOPER [Wachter] will be responsible to pay the CONTRACTOR [Olander] for all of the contract work in accord with the plans, specifications, and [34]*34proposal prepared by the DEVELOPER’S Representative made a part of this contract.

Section (9) of the contract provides, in part:

The CONTRACTOR shall guarantee all work against faulty materials and workmanship for a period of one year from the date of final payment.

Section (13) of the contract provides:

The Board of City Commissioners reserves the right to make any necessary changes in the alignment, grade, or design of the proposed work deemed by them advisable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ziemann v. Grosz
2024 ND 166 (North Dakota Supreme Court, 2024)
Berger v. Sellers
2023 ND 171 (North Dakota Supreme Court, 2023)
Twete v. Mullin
2019 ND 184 (North Dakota Supreme Court, 2019)
Bakke v. Magi-Touch Carpet One Floor & Home, Inc.
2018 ND 273 (North Dakota Supreme Court, 2018)
Adoption of A.S.
2018 ND 265 (North Dakota Supreme Court, 2018)
Adoption A.S. C.N.D. v. C.M.A.S.
2018 ND 265 (North Dakota Supreme Court, 2018)
Nelson v. McAlester Fuel Company
2017 ND 49 (North Dakota Supreme Court, 2017)
Bjorneby v. Nodak Mutual Insurance Company
2016 ND 142 (North Dakota Supreme Court, 2016)
Border Resources, LLC v. Irish Oil & Gas, Inc.
2015 ND 238 (North Dakota Supreme Court, 2015)
Chapman v. Hiland Partners GP Holdings, LLC
49 F. Supp. 3d 649 (D. North Dakota, 2014)
C&C Plumbing and Heating, LLP v. Williams County
2014 ND 128 (North Dakota Supreme Court, 2014)
Kartes v. Kartes
2013 ND 106 (North Dakota Supreme Court, 2013)
Specialized Contracting, Inc. v. St. Paul Fire & Marine Ins. Co.
2012 ND 259 (North Dakota Supreme Court, 2012)
Interest of J.N.
2012 ND 256 (North Dakota Supreme Court, 2012)
Sprague v. Evanson
2012 ND 28 (North Dakota Supreme Court, 2012)
State v. Bruederle
2012 ND 23 (North Dakota Supreme Court, 2012)
Morgan v. Vestre
2011 ND 144 (North Dakota Supreme Court, 2011)
Vanlishout v. N.D. Department of Transportation
2011 ND 138 (North Dakota Supreme Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
2002 ND 65, 643 N.W.2d 29, 2002 N.D. LEXIS 80, 2002 WL 554733, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olander-contracting-co-v-gail-wachter-investments-nd-2002.