Dinnie v. Lakota Hotel Co.

186 N.W. 248, 48 N.D. 657, 1921 N.D. LEXIS 142
CourtNorth Dakota Supreme Court
DecidedDecember 13, 1921
StatusPublished
Cited by1 cases

This text of 186 N.W. 248 (Dinnie v. Lakota Hotel Co.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dinnie v. Lakota Hotel Co., 186 N.W. 248, 48 N.D. 657, 1921 N.D. LEXIS 142 (N.D. 1921).

Opinions

Statement.

Bronson,- J.

This is an action upon a building contract. In the trial court the jury returned a verdict for the plaintiff. Upon motion, judgment notwithstanding the verdict was entered for the defendant. The plaintiff has appealed from the judgment and the order therefor. The facts necessary to be stated are as follows:

Pursuant to a builder’s contract and certain plans and specifications, the plaintiff contracted to erect a certain hotel building at Dakota, N. D., for a stated consideration of $28,800. In his complaint, the plaintiff alleges that he has performed the conditions of the contract, and that there is due thereon $6,656.83; further, that he furnished certain extras of the value of $750. In his answer, the defendant alleges, in addition to the assertion of certain payments and existence of certain liens, that plaintiff did not perform the contract according to the terms and conditions thereof; that the plaintiff performed the work in an unworkmanlike manner and left the building unfinished, and employed incompetent and negligent workmen, and failed to properly construct or com-píete such building, although repeatedly notified by the architect to so do; that plaintiff has failed to produce a certificate from the architect showing compliance with the contract, and the arohitect has refused so to make a certificate by reason of plaintiff’s failure and refusal to complete the contract. In counterclaims, the defendant further alleges [660]*660loss of rents and profits in the amount of $3,000 through failure to complete the building at the time provided in the contract; that the defendant was compelled to pay out for materials and labor, in order to complete the building, $1,982.72, and that it will cost further to complete the building in accordance with the contract at least $6,000; that much work must be'taken out and replaced in order that the building may comply, with the contract, which will cost at least-$3,000; that the building as constructed, even after doing the work possible so as to make the building usable, will be worth at least $5,000 less than if it had been’ constructed according to the contract. The defendant accordingly asked for damages in the sum of $17,000.

The contract is dated June 7, 1917. Aynong other things, it provides:

“It is understood between the parties hereto that the work included in this contract is to be done under the direction of the said architect, and that his decision as to the true construction and meaning of the drawings and specifications shall be final.” “No alterations shall be made in the work except upon written order of the architect; the amount to be paid by the owner or allowed by the contractor by virtue of such alterations to be stated in said order.” “Should the contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in the performance of any of the agreements herein contained, such refusal, neglect, or failure being certified by the architect, the owner shall be at liberty, after three days’ written notice to the contractor, to provide any such • labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract, and if the architect shall certify that such refusal, neglect, or failure is sufficient’ ground for such action, the owner shall also be at liberty to terminate the employment of the contractor for the said work, and to enter upon the premises and take possession, for the purposes of completing the work included under this contract, of all materials, tools, and appliances thereon, and to employ any other person or persons to finish the work and to provide the materials therefor; and in case of such discontinuance of the employment of the contractor, he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the con[661]*661tractor, but if such expense shall exceed such unpaid balance, the contractor shall pay the difference to the owner. The expense incurred by the owner as herein provided, either for furnishing materials or for finishing the Work, and any damage incurred through such default, shall be audited and certified to by the architect, whose certificate thereof shall be conclusive upon the parties.”

The contract also provides for payment of the contract price in current payments and a final payment upon the certificate of the architect. During the course of the work the plaintiff had a foreman on the job; the architect also had a superintendent. In September, 1917, the architect complained of unsatisfactory work, due to incompetent workmen, principally concerning plaster work, lintels, coping on the east and south Avails, failure to waterproof cistern in accordance with specifications, and other particular items; also, in another letter in September, the architect complained of the work of the painter, subcontractors, of the ventilators not being installed according to specifications, and the omission of an angle. Again, on October 4, 1917, the architect in a letter advised the plaintiff that some of the work was unsatisfactory; that the ventilators on the roof were not pursuant to specifications; that the brickwork over the window in the lobby and a brick pier had not been reset. Again, on October 20, 19x7, the architect advised the plaintiff that the temporary roof on the building had been cut up and roof boards were buckling, and the plaster was damaged, necessitating resetting the roof boards and removing damaged plaster; that the plaster work was irregular and crooked and had cracked; that some brickwork had not been relaid; that the lathing in the basement was not being done properly. On November 8, 1917, the architect wrote Parsons, an employee of the plaintiff, that the roof was not laid pursuant to plans and specifications and that part of the roof over the kitchen was leaking; that the painting •of the fire escapes would not be accepted'; and that attention should be given to the screens lying about. Again, on December 17, 1917, he wrote Parsons to advise the painter not to do any more work, for the reason that he noticed that the floors were cross-scraped in a number of places and left very rough and irregular. In January, 1918, the architect made a list of the defects in the construction of the building and mailed the same to the plaintiff. In the list 43 items were specified; summarizing the same, they may be stated as folloxvfc:

Coping on south and east wall to be removed and new coping. [662]*662installed; roof to be given another layer of felt and two layers of asphalt; certain brickwork to be removed and reset; railings around areas not secured to the brick walls by expansion bolts; rubbish not removed [rom the site; plaster beams not finished; coal chute doors not properly set; window frames not properly caulked; stair stringers loose; fire escapes to be painted; fills around the wfalls not soaked and tamped; broken glass to be replaced; all glass to be cleaned; certain plastering to be replastered, and certain varnishing to be done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fargo Glass & Paint Co. v. Smith
266 N.W. 100 (North Dakota Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
186 N.W. 248, 48 N.D. 657, 1921 N.D. LEXIS 142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dinnie-v-lakota-hotel-co-nd-1921.