Horton v. Emerson

152 N.W. 529, 30 N.D. 258, 1915 N.D. LEXIS 121
CourtNorth Dakota Supreme Court
DecidedApril 3, 1915
StatusPublished
Cited by8 cases

This text of 152 N.W. 529 (Horton v. Emerson) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Horton v. Emerson, 152 N.W. 529, 30 N.D. 258, 1915 N.D. LEXIS 121 (N.D. 1915).

Opinion

Eisic, Oh. J.

Plaintiff, as surviving partner of the firm of Lord & Plorton, seeks in this action to recover upon the quantum meruit for labor and material furnished to defendant at his request in the erection of a building in the city of Minot, known as the Arcade Building. A jury was expressly waived in the district court, and at the conclusion of the trial findings of fact and conclusions of law favorable to the plaintiff were made, and pursuant thereto plaintiff had judgment for the sum of $1,792.92 and interest, together with the costs. Thereafter defendant moved for a new trial, which motion was denied, and the case is here on appeal, both from the judgment and from such order.

Before noticing the specifications of error, a brief statement of the important facts will be made. On June 3, 1907, Lord & Horton, contractors and builders of Minot, entered into a written contract with the defendant, a resident of said city, whereby such contractors undertook [263]*263and agreed for and in consideration of the sum of $16,000 to erect for the defendant in such city, a two-story and basement brick structure according to certain plans and specifications therein referred to. Such contract price was to be paid as follows: $3,000 upon the completion of the foundation for such building, $6,000 when the brick work was completed and the roof on and the window openings closed up, and the final payment of $7,000 within thirty days after the completion of the building and when certificates for the same are issued.

That between June 15, 1907, and January 15, 1908, the said firm of Lord & Horton furnished the necessary labor and material for such building, and caused the same to be erected under the contract aforesaid, and shortly after the completion of such building the defendant went into possession thereof and occupied the same continuously until the trial. That he has made payments on such contract aggregating $13,600.

In March 1908, Lord & Horton commenced an action in the district court of Ward county against the defendant for the purpose of foreclosing a mechanic’s lien which they had theretofore filed against said building for the balance alleged to be due them under such written contract. Defendant answered the complaint in such action, and among other things alleged: “Defendant further alleges that heretofore, to wit, and on or about the 4th day of February, 1908, this defendant tendered in lawful money of the United States, to the said Lord & Horton, the sum of seventeen hundred ninety-two and ninety-two hundredth dollars ($1,792.92), that being the whole sum due and payable under the terms and conditions of said contract, after deducting the items of damage hereinbefore specified, and alloiuing for all just claims due to said plaintiffs, which said tender was by said plaintiffs refused, and thereupon this defendant did, on said 4th day of February, 1908, deposit in the Second National Bank of Minot the said sum last above mentioned to the order of said Lord & Horton; that said sum is at the date hereof on deposit in said bank, to the order of said plaintiffs, and is sufficient in amount to completely pay said plaintiffs all sums due and owing to said plaintiffs.” Also, “that the said sum so specified still remains on deposit in said bank, and this defendant now offers to produce the same in court, in full payment of all claims of said plaintiffs.” That as thus alleged defendant in fact made such tender and deposit, [264]*264but prior to tbe trial of said action withdrew the same and amended his answer accordingly. On February 4, 1908, defendant caused to be served upon Lord & Horton a written notice as follows: “You will please take notice that I have this day deposited to your credit in the Second National Bank of Minot, North Dakota, the sum of $1,792.92, and directed said bank to pay the said amount to you upon receipt from you in full for all accounts by me owing to you this day.”

Such foreclosure action came on for trial before the late Judge Charles F. Templeton of the first judicial district, and at the conclusion of the trial findings of fact and conclusions of law favorable to the defendant were made and judgment entered dismissing the action. The gist of these findings of fact is to the effect that Lord & Horton, the plaintiffs, failed to comply with the contract in numerous particulars detailed in such findings, clearly showing a failure to substantially perform the contract. It is a very significant fact which must not be overlooked that this distinguished jurist, who possessed a keen legal mind and a high sense of equity and justice, not only did not find as a fact that plaintiffs wilfully or intentionally departed from the terms of the contract, but he expressly refused to so find. We have examined his original findings of fact and conclusions of law, which disclose that he refused' to make the following finding: “The court further finds as conclusions of fact that the plaintiffs did not intend to comply with the contract and did intend in some particulars at least to deceive the defendant, Emerson, with reference to what was being furnished, and did endeavor to deliver second and third class work and material in place of first-class; that the plaintiff took no care, and, in places at least, did not intend to follow the plans and specifications with reference to the matters of construction resulting in a very inferior combination, greatly damaging the building; that the building is damaged by virtue of failure to comply with the plans and specifications in the sum of not less than $3,431.10, thus offsetting the whole amount claimed to be due by the plaintiffs.” The refusal to make such requested findings, as well as the refusal of various conclusions of law requested, unmistakably disclose that it was the intention .of Judge Templeton to hold merely that no recovery could be had by plaintiffs on the contract, and he studiously avoided making any finding or conclusion which would in the least hamper or interfere with plaintiffs’ right to recover upon the [265]*265quantum meruit. His letter addressed to plaintiffs’ counsel and which was introduced in evidence in the case at bar, fully corroborates us in the foregoing statement. The letter is as follows:

Grand Forks, N. D., Oct. 26-, 1908.

L. W. Gammons,

Minot, N. D.

Dear Sir:—

I have yours of the 24th regarding the case of Lord & Horton v. Emerson. My view of the case is that the present action should be dismissed upon the merits. The action is brought upon the contract to foreclose a lien. An action of this nature under the terms cannot be maintained, because there was not a substantial compliance with the contract, and the architect’s certificate was not fraudulently or arbitrarily withheld. That this action cannot be maintained under these circumstances, see Anderson v. Todd, 8 N. D. 158, 77 N. W. 599. As the lien cannot be upheld, plaintiffs cannot in this action recover a money judgment. Bray v. Booker, 6 N. D. 526, 531, 72 N. W. 933. I should not find all of the defendants proposed findings in any event. If you wish to submit a transcript of the testimony and argue the matter before I sign any findings, I will give you a reasonable time to do so.

Let me know your desire in the matter by early mail, as I am anxious to dispose of it.

'Tours truly,

Charles F. Templeton.

At the trial of the present action but little testimony was introduced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knutson v. Ekren
5 N.W.2d 74 (North Dakota Supreme Court, 1942)
Murie v. National Elevator Co.
236 N.W. 269 (North Dakota Supreme Court, 1931)
Gronseth v. Brubakken
228 N.W. 189 (South Dakota Supreme Court, 1929)
Power v. Williams
205 N.W. 9 (North Dakota Supreme Court, 1925)
Holtzman v. Bennett
229 P. 1095 (Nevada Supreme Court, 1924)
Lee v. Lee
188 N.W. 42 (North Dakota Supreme Court, 1922)
Stead v. Manhart
185 N.W. 1009 (North Dakota Supreme Court, 1921)
Kupfer v. McConville
185 N.W. 1005 (North Dakota Supreme Court, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
152 N.W. 529, 30 N.D. 258, 1915 N.D. LEXIS 121, Counsel Stack Legal Research, https://law.counselstack.com/opinion/horton-v-emerson-nd-1915.