Morgan v. Stevens

6 Abb. N. Cas. 356
CourtNew York Court of Common Pleas
DecidedJune 15, 1878
StatusPublished
Cited by4 cases

This text of 6 Abb. N. Cas. 356 (Morgan v. Stevens) is published on Counsel Stack Legal Research, covering New York Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morgan v. Stevens, 6 Abb. N. Cas. 356 (N.Y. Super. Ct. 1878).

Opinion

R. S. Guernsey, Esq., Referee.

There was some conflict of' evidence as to the value of the material taken out of those houses, but I have regarded it mainly as a question of law. It not being mentioned in the written contract, it might well be questioned whether any evidence should have been allowed upon the subject, as the contract covered the matter, although set up by the owners as a counter-claim and recoupment against the contractor and those claiming under her. I have disposed of it by the finding of fact as to the value of those two houses and their use by Jones, the contractor, and the conclusion of law upon the' contract that the owners are not entitled to be allowed the value thereof as a counter-claim or deduction from the contract price for the erection of the new building. In other words, under the building contract, which did not mention these houses or the use of the materials in them, Jones became the owner of the materials upon taking possession and removing them, and could use them whenever and wherever she chose, either in the new building or elsewhere. The only question the owners can raise was—were the materials of good quality and condition to fulfill the terms of the building contract %

These two houses were standing upon the land at [360]*360the time of the making of this contract, and when the contractor took possession to commence work. It is a long-recognized principle of law that all contracts relating to real estate, and dealings with it, are presumed to be made with reference to the visible condition of it. The rule of caveat emptor applies the same as to personal property (Canaday v. Stiger, 55 N. Y. 452; Gwilhim v. Stone, 3 Taunt. 439 ; Long v. Warren, 68 N. Y. 426).

This is so in regard to physical incumbrances, boundaries-, watercourses, highways, surface, soil, location, surroundings, fixtures, &c. (See Long v. Warren, 68 N. Y. 426).

In the absence of fraud or special contract they all follow the realty, “for better or for worse,” running with the land as fixtures, without any special mention or exception. A building contract is governed by the same rule in regard to the condition of the property, and the disposition, use and furnishing of the materials and the preparation of it for the contract (Shute v. Hamilton, 3 Daly, 462). If the owners of the land had the right to the materials in the two houses, in this case it was waived by leaving them until the contractor took possession under her contract. Had the owners removed them before this, a different question would be presented. They were obstructions to Jones in the progress of the contract,, and she must remove them, whether to her benefit or otherwise. If they were high rocks instead of houses they must still be removed by the contractor, and it would be absurd to claim that the contractor could properly charge extra for such removal.

In this case each side claimed that the custom in regard to ownership was in their favor in such instances, and offered evidence to that effect, which was excluded. I think the question of custom cannot properly arise here, where there is an express and [361]*361plain written contract between the parties which relates to the subject matter. Evidence of custom or usage may be given to explain a written contract, but not to alter or change its plain terms or be inconsistent with it (Whart. Evi. §§ 958, 960, 961, 969, 970). Custom has not the same force in America as in England under the common law.

I have riot been able to find any decision directly in point on this question of ownership in any of the English or American reports, but I believe the doctrine is sound upon the recognized principles above stated.

Many of the claimants who are parties defendants and sub-contractors appeared at an early stage of this action and proved their claims, and then left the main contest of the issues which the owners set up as to payment, bad workmanship, defective materials, no extra work, and counter-claims for stipulated damages under the contract for delay, and the value of the materials taken out of the old buildings, and that nothing was due the contractor, and other deductions, which if allowed against the contractor would defeat the lienors. A few of the lienors persevered in this action, and two of them were settled with (their claims being purchased by the owners) and withdrew just before the case was closed, and only two continued the contest until the end. The contractor did not file any notice of lien, but appeared in aid of the claimants. All of those who, after appearance, allowed their liens to expire during the pendency of this action without an order of the court continuing them, as provided by the statute (act 1863, § 11), should be dismissed as to the owners with costs as for want of prosecution, they having actually abandoned their proceedings against the owners (Schacttler v. Gardiner, 41 How. Pr. 243 ; Huxford v. Bogardus, 40 Id. 94; O’Donnell v. Rosenberg, 14 Abb. Pr. N. S. 59). Such claimants are entitled to a judgment against the contractor, however, for [362]*362the amount of their claim (Grogan v. McMahon, 4 E. D. Smith, 754), and costs as upon failure to answer, because the contractor did not object to their claims. The lienors did not contest among themselves.

If for any canse a party wishes to withdraw his claim, he should apply to the court, which has the power to relieve him without costs in a proper case (De Barante v. Deyermand, 41 N. Y. 355).

A referee has the same power as a court in allowing costs as between the parties, where all the issues are referred (Barker v. White, 1 Abb. Ct. App. Dec. 95 ; Code, § 1022). Some claimants who did not appear and prove their claims should be dismissed as to all parties without costs, because they took no part in the action, except nominally.

Where there are several liens, each should be fully proved, because it may prejudice the rights of subsequent lienors. The owners and contractor cannot alone in such case admit the validity of the lien so as to affect others.

The claimants whose liens are established should have costs of this action against the owners, who alone contested them (Doughty v. Devlin, 1 E. D. Smith, 625 ; Dunning v. Clark, 2 Id. 535 ; Eagleson v. Clark, Id. 644), and costs as on failure to answer as against the contractor. The costs against an owner are chargeable against the property, and may constitute a specific lien thereon (Ib.; Althause v. Warren, 2 E. D. Smith, 657).

The two defendants who signed the Jones contract as trustees of Marietta R. Stevens, under the will of Paran Stevens, deceased, are personally liable for the amount due Jones on the contract, it being regarded as a personal contract with them, and not binding on the Stevens estate (Austin v. Munro, 47 N. Y. 360; New v. Nicholl, 73 N. Y. 127).

The contract contained a clause for stipulated [363]*363damages at $100 a day for each day after a specified date, when the building was to be completed notwithstanding extra work thereon.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Savage v. City of Buffalo
50 A.D. 136 (Appellate Division of the Supreme Court of New York, 1900)
Hutton Bros. v. Gordon
23 N.Y.S. 770 (New York County Courts, 1893)
Crane v. McDonald
2 Silv. Ct. App. 341 (New York Court of Appeals, 1890)
In re Sharp
5 Dem. Sur. 516 (New York Surrogate's Court, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
6 Abb. N. Cas. 356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morgan-v-stevens-nyctcompl-1878.