Hutton Bros. v. Gordon

23 N.Y.S. 770, 2 Misc. 267
CourtNew York County Courts
DecidedFebruary 15, 1893
StatusPublished
Cited by2 cases

This text of 23 N.Y.S. 770 (Hutton Bros. v. Gordon) is published on Counsel Stack Legal Research, covering New York County Courts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hutton Bros. v. Gordon, 23 N.Y.S. 770, 2 Misc. 267 (N.Y. Super. Ct. 1893).

Opinion

WEIANT, J.

This action is brought to foreclose a mechanic’s lien on land of the defendant Lizzie S. Gordon. The defendant Gordon, being the owner of certain lots at Congers, in this county, on December 11, 1890, entered into a written contract with Butler & Thurston, a firm of builders, whereby they agreed to construct a dwelling for her upon said lots on or before April 15, 1891, for the consideration of $1,700. This agreement was, on or about August 13, 1891, superseded by a new contract, in writing, entered into between the same parties, whereby said Butler & Thurston agreed to construct said dwelling, and furnish all materials, for the like consideration, to be paid to them in three equal payments,—one when the house was “raised, framed, and inclosed;” the second, “when the plastering is all complete;” and the third, “when the house is finished and completed according to the plans and specifications.” The house was to be erected and finished on or before November 15, 1891. The work was to be done to the satisfaction, and under the direction, of one David L. Allen. The contract provided that at any time during the progress of constructing the building the owner might request any alteration of, addition to, or omission from, the contract, and that the same should in no way affect the contract, but that a reasonable valuation should be added to or deducted from the contract price, accordingly. It was also provided that should the contractors, at any time during the progress of the work, refuse or neglect to supply a sufficiency of materials or workmen, the owner should have power to provide materials and workmen, after three days’ notice, in writing, being given the contractors to finish the said work, and the expense should be deducted from the amount of the contract. The contract also contained a covenant on the part of the contractors to pay to the owner $10 for every day the said building should be incomplete after November 15, lc91. The contractors proceeded with the construction of the building under this agreement until about the [772]*7721st of December, 1891. The work had been sufficiently advanced to entitle the builders to the first two installments of payment, and the owner had made the same, in compliance with the contract, amounting to $1,133.33, the latter one of which was made September 26,1891. The builders proceeded with their work some time thereafter,- and now claim that at the time they ceased they had done work and supplied materials to the value of $1,200, $1,300, or $1,400. Differences arose between the builders and the owner as to whether or not the work and materials were in compliance with the contract, and as to changes and alterations in portions of the structure. The work was delayed, and finally the builders refused to proceed with the work and complete the building, and finally ceased, the latter part of November, or 1st of December, 1891. Negotiations and conferences followed between the parties for the purpose of adjusting these differences, and bringing about the completion of the building. On or about December 29, 1891, it appears that at a conference in New York city an. amicable arrangement was reached, under which the builders were to proceed and finish the building under the contract, with certain alterations. This arrangement was reduced to writing, but the contractors refused to execute the same, or to proceed with their work, unless the owner, Mrs. Gordon, would release them from any liability for the $10 a day that they were obligated to pay, under the contract, for failure to complete the building within the time required by the contract. Thereupon, about January 5, 1892, the owner caused a written notice to be served upon the contractors, in which she stated that unless they proceeded within three days to the completion of the building, as provided by the plans and specifications, she would proceed to complete the building, and hold them responsible for all expense thereof. The contractors refused to proceed, and the owner then proceeded to complete the building, and for the same incurred an expenditure and cost of about $685. The plaintiff, a corporation, under purchases made by Butler & Thurston, the contractors, between August 22 and December 15, 1891, furnished materials, and delivered the same, to be used in the construction of this building in question, to the amount and value of $329.20, of which $100 was paid by such contractors. Upon January 16, 1892, it filed a notice of lien for $229.20 for materials delivered to said Butler & Thurston to be used in the construction of said building. There is not sufficient evidence to connect the owner, Mrs. Gordon, with the furnishing or use of these materials, so as to establish a personal liability against her. The plaintiff must therefore rest, as to the liability of the lands in question, upon the relations established between her and the contractors, Butler & Thurston. It is therefore necessary that we should first give consideration to the legal status of the contractors and owner.

It is conceded that Butler & Thurston did not complete their contract, and abandoned the construction of the building. This I. do not think they were justified in doing, under the facts and circumstances, even if their contention be true, that Mrs. Gordon. [773]*773was wrong in her claims as to the alterations, deviations from, or failures to comply with, the plans and specifications; for, as appears, the contract provided for all such contingencies, and did not authorize an abandonment of the work for any differences such as arose between these parties. If Mrs. Gordon were in error in her claims, the contractors were not relieved from carrying out the agreement on their part. Upon their refusal to proceed and complete the building, Mrs. Gordon, in accordance with the right given her under the contract, proceeded to complete the building; and, pursuant to its provisions, she is entitled to deduct the expense thereof from the amount of the contract price, or any moneys Butler & Thurston may have earned. She thereafter, in January, 1892, entered into a written contract with one Theodore A. Dubois to complete the building, (meaning the carpenter work,) in accordance with the same plans and specifications, for the sum of $195, but not including a claim of Mead Sc Taft, for materials, of $83.39. The evidence shows that she actually paid out, or legally obligated herself to pay, in the aggregate, to thus complete the building, the sum of about $685, excluding certain several .omissions that were supplied to conform the building to the contract, which together exceeded the entire amount of the last payment and extras, if any, under the contract, by at least the sum of $100, which would have been due and payable to Butler & Thurston if they had performed their contract, and even with such extra compensation, if any, as had been earned by them in addition. Under such circumstances, Mrs. Gordon’s lands cannot be subjected to the lien of the plaintiff, although Butler & Thurston had done work and furnished materials after the second payment under their contract. Cheney v. Hospital Ass’n, 65 N. Y. 282; Larkin v. McMullin, 120 N. Y. 206, 24 N. E. Rep. 447, and cases there cited; Foshay v. Robinson, (Sup.) 16 N. Y. Supp. 817; Van Clief v. Van Vechten, 130 N. Y. 572, 29 N. E. Rep. 1017. In the latter case it is said that “they [meaning subcontractors] are under the same obligations to prove performance, and to the same extent, that he [the contractor] would be. Their rights as lienors are measured by his rights under the contract.”

The plaintiff delivered some materials after Butler & Thurston ceased work, which were subsequently used in the completion of the building by Mrs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wiley v. Hart
132 P. 1015 (Washington Supreme Court, 1913)
Terwilliger v. Wheeler
81 A.D. 460 (Appellate Division of the Supreme Court of New York, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
23 N.Y.S. 770, 2 Misc. 267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hutton-bros-v-gordon-nycountyct-1893.