Close v. Clark

9 N.Y.S. 538, 16 Daly 91, 30 N.Y. St. Rep. 671, 1890 N.Y. Misc. LEXIS 256
New York Court of Common Pleas·Decided April 7, 1890·Published·Cited by 11 cases

Opinion

Larremore, C. J.

This action was brought for the foreclosure of a mechanic’s lien. The complaint, among other things, alleged that plaintiffs “did and performed certain work, labor, and services, and furnished necessary materials therefor, which work and materials consisted of building and erecting on the premises above described a house or building according to the terms and conditions of the said contract. ” We think the learned referee erred in his findings as to what the contract referred to in the complaint actually was. This agreement was in writing, and was executed in duplicate. The copies correspond, except that after the signatures in the one retained by defendants, and produced by them at the trial, was added the following; “P. 5. The whole building to be finished on or before the 1st day of January, [539]*5391888, A. D.” We think the weight of evidence is strongly in favor of the view that this postscript was added after the signing, doubtless, but still upon the same occasion, and in the presence and with the consent of all the parties. Such postscript, being orally assented to, was therefore as binding as the foregoing instrument actually subscribed, and in reality became an integral part of the agreement under which the work was done. Dutch v. Mead, 36 N. Y. Super. Ct. 427, 59 N. Y. 628. But though the weight of evidence substantiates defendants’ claim as to the contract, and though the referee erred in this respect, we cannot see that any actual harm resulted from such an error, and we should not reverse upon this ground.

It appears that there were departures by mutual consent from the original plan, and, furthermore, that after the time prescribed by the contract had expired the defendant Clark notified plaintiffs to go on and complete. Under competent authorities either of these circumstances would operate as a waiver of the time conditioned in the contract. It has also been directly held that in a contract of this character a provision that the work shall be completed by a certain date, and paid for upon completion, does not make time of the essence of the contract, and that, if the builder proceeds afterwards with the assent of the other party, he may recover at the contract price. Dillon v. Masterton, 39 N. Y. Super. Ct. 133.

This lien was filed for the unpaid balance of the whole contract price. In the notice of lien it is stated that all the work and materials had been actually performed and furnished. Leaving out of consideration a large number of departures from the contract which the referee finds were waived or assented to, he finds directly that in several particulars, more or less substantial, the contract was not completed. He finds that work and materials to the value of $93 were required to complete the same. I cannot see why, on respondent’s own showing, the present case does not come squarely within the reasoning of Foster v. Schneider, 2 N. Y. Supp. 875. The material fact is not that the builders had completed their contract, but in an inferior manner; it is that they had not completed it at all. The referee’s sixth finding of fact specifies several omissions, all of them of some importance. The plaintiffs entirely failed to supply these articles, although notified to do so. They cannot argue from their statement, that referee disagreed with and found against them only as to the quality of their work. Confessedly they had not attempted to provide several things called for by the contract. We think, therefore, the allegation in the notice was untruthful, and might have been misleading to subsequent lienors and the public, and, for the reasons given in the opinion in Foster v. Schneider, supra, the lien must be declared invalid.

Free access — add to your briefcase to read the full text and ask questions with AI

Close v. Clark, 9 N.Y.S. 538, 16 Daly 91, 30 N.Y. St. Rep. 671, 1890 N.Y. Misc. LEXIS 256 (N.Y. Super. Ct. 1890).

9 N.Y.S. 538 (Close v. Clark) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Edmunds v. Welling
110 P. 533 (Oregon Supreme Court, 1910)
Bossert v. Happel
40 Misc. 569 (New York Supreme Court, 1903)
Aeschlimann v. . Presbyterian Hospital
59 N.E. 148 (New York Court of Appeals, 1901)
In re Emslie
98 F. 716 (S.D. New York, 1900)
Burke v. Educational Alliance
23 Misc. 163 (Appellate Terms of the Supreme Court of New York, 1898)
Ringle v. . Wallis Iron Works
44 N.E. 175 (New York Court of Appeals, 1896)
Murphy v. Stickley-Simonds Co.
31 N.Y.S. 295 (New York Supreme Court, 1894)
Ringle v. Wallis Iron Works
28 N.Y.S. 107 (New York Supreme Court, 1894)
Hutton Bros. v. Gordon
23 N.Y.S. 770 (New York County Courts, 1893)
Mull v. Jones
18 N.Y.S. 359 (New York Court of Common Pleas, 1892)
Brandt v. Verdon
18 N.Y.S. 119 (New York Court of Common Pleas, 1892)