Brandt v. Verdon

18 N.Y.S. 119, 44 N.Y. St. Rep. 885
CourtNew York Court of Common Pleas
DecidedMarch 7, 1892
StatusPublished
Cited by3 cases

This text of 18 N.Y.S. 119 (Brandt v. Verdon) is published on Counsel Stack Legal Research, covering New York Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brandt v. Verdon, 18 N.Y.S. 119, 44 N.Y. St. Rep. 885 (N.Y. Super. Ct. 1892).

Opinion

Bookstaver, J.

The defendant and appellant, Moses, in 1887 and 1888 was the owner of certain property in West 134th street, on which she erected five houses. The plaintiff and the other defendants were mechanics who did certain work and furnished certain material on those houses. The respondents Verdón and Knapp had commenced their separate action to foreclose their lien, but by an order of this court their action was consolidated with* the plaintiff’s, and they thereafter served a proper answer in that action,. The issues so joined were referred to Walton Storm, Esq., to hear and determine, and after hearing the evidence he reported in favor of all the lienors for amounts somewhat less than claimed by them respectively. On the argument appellant’s counsel did not specially point out any errors committed by the referee in the admission or exclusion of evidence, nor has he done so ini his brief. We have not, therefore, deemed it necessary to examine the exceptions to such admission or exclusion in detail.

The plaintiff Brandt filed his notice of lien on or about March 9,1888, which-contains the following: “The nature and amount of the labor and services-performed and the materials furnished are as follows: That on or about the 10th day of November, 1887, the said William H. Brandt entered into three several contracts with Lizzie M. Moses to do the slating, tinning, and iron [120]*120•work on the premises hereinafter mentioned and described, and said Moses promised and agreed to pay for said work the sum of twelve hundred and •fifty dollars. That said William H. Brandt has actually done said work on -said premises. That said Moses has paid on account of said contracts the -sum of $340, and there still remains due and unpaid the sum of $910.” The complaint, in substance, alleges the same thing. The referee has found, however, that instead of three there were four separate contracts, which in the aggregate amounted to the sum of $1,250; but the appellant has made no point of this variance, and we do not see that it could have been of any material injury to her. The referee has further found that two of the contracts were partly in writing and partly verbal, and the other two were wholly in paroi. He has also found that 75 per cent, of the amount of each contract was to be paid as the work advanced. To these findings the defendant Moses excepted, and on this appeal contends that the referee erred in this respect, especially as to the two contracts which she claims were wholly in writing; but what are called “contracts” consisted of letters which are only estimates by the plaintiff as to what certain work would cost, and acceptances by her of those estimates. None of them in any way mention the terms of payment, and it is quite probable these were agreed on verbally, as the plaintiff testified. There certainly is not that preponderance of evidence in favor of the appellant which would lead us to reverse the referee’s conclusion on these questions.

The referee has further found that the first, second, and fourth contracts were performed, with some trifling exceptions, for which proper deductions were made, and that they were not fully performed on account of defendant’s neglect. The evidence as to the performance was very contradictory, but we see no reason for disturbing his findings in respect to these contracts.

The third contract was one by which the plaintiff agreed to put up three bay-windows on the houses in question, according to plans submitted to him, for the sum of $490, payable as the others were. From the evidence it appears that the plans for these windows, as filed with the building department, were in accordance with the building law, requiring iron frame-work for the ■bays, but that the plans given to the plaintiff only called upon him to re-cover wooden frame-works with iron, making an outward appearance in conformity with the law, but in reality evading it. This, we think, must have been known to the plaintiff to have been an evasion. But, in the view we take of this case, it is not necessary for us to decide now whether or not a mechanic will be permitted to acquire a lien for work done by him contrary to law, and in order to evade it; for the referee has found the work called for under this contract was not fully completed, but that nearly one-third was left undone. He also fails to find that what was done was done in a good and workmanlike manner, and in his opinion says it was not. He, however, finds that, as the plaintiff at all times was ready and willing to complete the contract if the defendant would pay him according to its terms, he should have a lien for the amount of work actually performed by him, which he found to be $332. This is in conformity with the law. Haden v. Coleman, 73 N. Y. 567; Graf v. Cunningham, 109 N. Y. 369, 16 N. E. Rep. 551. This raises the only real questions of law in this branch of the case. As before stated, the plaintiff, in his notice of lien, claimed he had “actually done said work on said premises,” meaning that he had done all the work required by his contracts, and further ■claimed that there remained “due and unpaid the sum of $910,” being the full contract price for all the work. These statements, in view of the referee’s findings, are evidently untrue. All the work had not been done, and there was due on this contract, for all the work done by him under it, only $322, instead of $490, the contract price. Under precisely this state of facts, the supreme court, in Foster v. Schneider, (Sup.) 2 N. Y. Supp. 875, held that, where the whole of the work had not been performed, it was requisite [121]*121’that the notice of lien should state that fact, and state how much had been performed, and that a failure to conform to the statute in that respect made the filing of the notice invalid, so that it created no lien. This decision was followed by this court in Close v. Clark, (Cum. Pl.) 9 N. Y. Supp. 538, and the same doctrine was announced in Luscher v. Morris, 18 Abb. N. C. 67. We consider the rule extremely salutary and useful, in order that all parties may be apprised of the true state of affairs. In the case first cited, Daniels, J., delivering the opinion of the court, referring to the notices of lien, said: “They should have stated the extent of the services performed, and of the material used, and of the residue of the work remaining to be performed. * * * The legislature lias required this to be done, in clear and direct language. And it is one of the directions to be observed by the claimant to insure the creation of the lien for the amount of the indebtedness upon the property benefited by the work and material. * * * It was intended in this manner to exact a truthful statement of the facts to be contained in the notice, and that probably was intended for the benefit of other claimants as well as of the owner of the property, and the truthful information of the court; and the courts can no more dispense with the observance of this requirement in making and filing the notice than they can with any other direction required to be observed for the purpose of creating a lien upon the property.” And again: “This proceeding is wholly statutory, and, to entitle a claimant to its benefits, the directions of the statute must be substantially observed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Emslie
102 F. 291 (Second Circuit, 1900)
In re Emslie
98 F. 716 (S.D. New York, 1900)
Ringle v. Wallis Iron Works
28 N.Y.S. 107 (New York Supreme Court, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
18 N.Y.S. 119, 44 N.Y. St. Rep. 885, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brandt-v-verdon-nyctcompl-1892.