Larkin v. . McMullin

24 N.E. 447, 120 N.Y. 206, 25 Abb. N. Cas. 108, 30 N.Y. St. Rep. 902, 75 Sickels 206, 1890 N.Y. LEXIS 1247
CourtNew York Court of Appeals
DecidedApril 15, 1890
StatusPublished
Cited by24 cases

This text of 24 N.E. 447 (Larkin v. . McMullin) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Larkin v. . McMullin, 24 N.E. 447, 120 N.Y. 206, 25 Abb. N. Cas. 108, 30 N.Y. St. Rep. 902, 75 Sickels 206, 1890 N.Y. LEXIS 1247 (N.Y. 1890).

Opinion

Bbadlbt, J.

The only question upon the trial was whether the notices of the liens were effectual to charge the premises with the claims of the honors, and that was dependent upon the further question whether at the time they were filed, anything was due or remained unpaid for the work the defendant McMullin had performed under the contract with the defendant Kahn. The purpose of the statute known as that relating to mechanic’s liens is to enable those doing work or furnishing materials to be used upon structures on real estate, to obtain security and payment through the means and in the cases provided by it; but in no case shall the owner of the premises be liable to pay by reason of liens filed pursuant to the act “ a greater sum than the price stipulated and agreed to be paid in such contract and. remaining unpaid at the time of filing such hen, or in case there is no contract, than the amount of the value of such labor and material then remaining unpaid.” (Laws of 1885, chap. 342, § 1.) In the present case the work was done and materials furnished by McMullin in performance of a contract between him and the owner, Kahn, providing for certain compensation and designating the terms of payment regulated by the work performed in its stages to completion. The referee found that McMullin performed the work entitling him to the first and second payments, and received them in full; that although he received $100 on the third payment July 10, 1.886, he failed to continue the work to entitle him to that or the fourth payment, but in the latter part of July he abandoned the work; that after such abandonment neither McMullin or anyone acting for him or in his behalf performed *209 the contract, and it has not been performed; and that the defendant Kahn performed all the terms of the contract on his part to be performed. It thus appears by the findings of the referee that nothing was due McMullin at the time the liens' were filed. It is, however, urged that because there ivas evidence tending to prove that the completion of the contract would cost less than the amount unpaid to McMullin of the contract price for the entire work, the liens should be effectual to reach such difference. So far as the question is presented by exceptions to findings and to refusals to find of the referee, it may be considered, but no further, as questions of law only can have consideration on this review, since it does not appear by the order appealed from, that the judgment was reversed and a new trial granted on questions of fact. (Code, § 1338.) The amount of compensation and the right to it were regulated by the terms of the contract, and whether anything remained unpaid ivas dependent on its provisions. As found by the referee, McMullin received all he was entitled to under the agreement, and $100 more before either of the liens was filed. In that view nothing then remained unpaid. The right of the oAvner as Avell as that of McMullin rested in the contract between them, and whether anything was due to the latter was dependent upon its terms. And to enable a sub-contractor, laborer or person furnishing material to the contractor or subcontractor to act advisedly, he is given the right on demand to the inspection of the contract under which the work is being done. (Laws of 1885, chap. 342, § 3.) Their rights for the purposes of a lien as against the OAvner, are mainly dependent upon those which the contractor takes by the contract, and whether anything is due upon it is governed by its provisions. As a general rule, therefore, it cannot be said that anything remains unpaid Avhich the owner is not by the terms of contract and does not become liable to pay. While the rule, in all its force applicable as between the owner and contractor, may not be applied as between the former and a third party who asserts a lien for labor or materials, at least in so far as relates to the question of good faith of the contractor, the owner cannot be *210 required to perform any other than the contract he has made with the contractor. The mere fact that the completion of work abandoned by the contractor, when nothing is due to him, may cost something less than the amount unpaid of the contract price for the entire work, does not necessarily support the claim of a lienor. That rule is applied to determine the amount unpaid for the purposes of a lien and to give effect to it as to any difference in favor of the contractor, so produced, when by means of the contract the contractor has taken the equitable title, and such contract, by reason of his failure to perform it, is forfeited, or in any manner terminated by the owner of the legal title. In such case the latter or any party through him, takes the property, subject to the lien. (Hackett v. Badeau, 63 N. Y. 476; Rollin v. Cross, 45 id. 766.) The same rule is also applicable when the right is reserved to the owner by the terms of the contract to complete the work on failure of the contractor to do so. In such case the work of completion by the owner is performed pursuant to the contract. (Murphy v. Buckman, 66 N. Y. 297.) Also, where the contractor abandons the work by reason of default of the owner, who goes on and completes it. (Graf v. Cunningham, 109 N. Y. 369.)

And when the work is substantially performed by the contractor, the lien is effectual, subject to the right of the owner to recoup such damage as he may have sustained by the failure to entirely finish it. (Heckmann v. Pinkney, 81 N. Y. 211.)

As held in the case last cited, it is not essential that a liability to pay exists at the time of filing the notice of lien. It is sufficient that an. amount has then been, under the contract, earned by the contractor which is unpaid.

In the case at bar there was no provision in the contract for the completion of the work by the ■ owner in the event of failure by the contractor, nor was there any understanding between them thát the owner should proceed with the work, but, on the contrary, the contractor abandoned it against the protest of the owner and refused to go on with it. Upon that state of facts, without anything further, it is difficult to«ee *211 that there was, at the time of filing the notice of lien, anything unpaid or to become due for the work done by McMuliin under the contract. (Lumbard v. B. & N. Y. R. R. Co., 55 N. Y. 491; Grane v. Genin, 60 id. 121.) But it is claimed that the right of a lienor is something more and beyond that of subrogation to the rights of the contractor, and that if it can be ascertained that, at the time the lien is filed, the latter had earned any amount which was unpaid, the lien is effectual to reach it, although the contractor has, before such filing, abandoned the work, and is not entitled to assert any claim against the owner; and to support that proposition are cited Wright v. Roberts (43 Hun, 413); Van Clief v. Van Vechten (48 id. 304); Sheffield v. Loeffler (20 N. Y. S. R. 890).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Herbert G. Martin, Inc. v. Alperstein
277 A.D.2d 990 (Appellate Division of the Supreme Court of New York, 1950)
Cassino v. Yacevich
261 A.D. 685 (Appellate Division of the Supreme Court of New York, 1941)
Winter v. Hazen-Latimer Co.
42 App. D.C. 469 (District of Columbia Court of Appeals, 1914)
Ennis v. Parkhurst
89 A. 346 (Supreme Court of Connecticut, 1914)
Upson v. United Engineering & Contracting Co.
72 Misc. 541 (New York Supreme Court, 1911)
Dahlberg v. Girsch
107 P. 616 (California Supreme Court, 1910)
Tice v. Moore
73 A. 133 (Supreme Court of Connecticut, 1909)
Maneely v. City of New York
119 A.D. 376 (Appellate Division of the Supreme Court of New York, 1907)
Masons' Supplies Co. v. Jones
68 N.Y.S. 806 (Appellate Division of the Supreme Court of New York, 1901)
De Lorenzo v. Von Raitz
44 A.D. 329 (Appellate Division of the Supreme Court of New York, 1899)
Smith v. Sheltering Arms
35 N.Y.S. 62 (New York Supreme Court, 1895)
McKee v. Rapp
35 N.Y.S. 175 (Superior Court of New York, 1895)
McKee v. Rapp
69 N.Y. St. Rep. 291 (The Superior Court of New York City, 1895)
McChesney v. City of Syracuse
27 N.Y.S. 508 (New York Supreme Court, 1894)
Vogel v. Whitmore
25 N.Y.S. 202 (New York Supreme Court, 1893)
Kelly v. . Bloomingdale
34 N.E. 919 (New York Court of Appeals, 1893)
Robbins v. Arendt
23 N.Y.S. 1019 (New York Court of Common Pleas, 1893)
Hutton Bros. v. Gordon
23 N.Y.S. 770 (New York County Courts, 1893)
Blakeslee v. Fisher
21 N.Y.S. 217 (New York Supreme Court, 1892)
French v. . Bauer
32 N.E. 77 (New York Court of Appeals, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
24 N.E. 447, 120 N.Y. 206, 25 Abb. N. Cas. 108, 30 N.Y. St. Rep. 902, 75 Sickels 206, 1890 N.Y. LEXIS 1247, Counsel Stack Legal Research, https://law.counselstack.com/opinion/larkin-v-mcmullin-ny-1890.