Upson v. United Engineering & Contracting Co.

72 Misc. 541, 130 N.Y.S. 726
CourtNew York Supreme Court
DecidedJune 15, 1911
StatusPublished
Cited by13 cases

This text of 72 Misc. 541 (Upson v. United Engineering & Contracting Co.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Upson v. United Engineering & Contracting Co., 72 Misc. 541, 130 N.Y.S. 726 (N.Y. Super. Ct. 1911).

Opinion

Pound, J.

The defendant United Engineering and Contracting Company, on or about Hovember 27, 1908, entered into a contract known as Contract Ho. 40, Section 10, with the people of the State of Hew York, for the improvement of the Erie canal from Lockport to Sulphur Springs guard lock, a distance of four and eighty-four hundredths miles, for the sum of $2,166,298.

The defendant Rochester Construction Company, on or about July 17, 1909, entered into a subcontract with defendant United Engineering and Contracting Company, whereby [543]*543the Rochester company undertook to do the excavation, channeling and embankment work required by the principal contract, between stations Ros. 5926 and 5952, extending a distance of 2,600 feet west from Hitchens Bridge.

The Rochester company entered upon the performance of the subcontract, and prosecuted the same until on or about February 5, 1910, when it ceased work thereunder and abandoned same.

On February 7, 1910, the plaintiff Upson verified a notice-of lien in the sum of $503.40 and interest, for coal furnished the Rochester company on its subcontract, and filed same in the office of the Superintendent of Public Works, the State Engineer and Surveyor and the Comptroller, on February 9, 1910.

On February 8, 1910, plaintiff McGrath verified a notice of lien in the sum of $858.23 and interest, for lumber and timber furnished the Rochester company on its subcontract, and filed same in said last above named offices on February 9, 1910.

Various defendants filed liens at the times, in the amounts, for services and materials furnished the Rochester company on the subcontract, as follows:

[544]*544The claims of Dussault Foundry Works and Kugler ■Brothers were paid subsequently to the commencement of this action.

The United company, pursuant to section 21 of the Lien Law, subdivision 4, deposited with the Comptroller the following amounts, on the following dates, on the following liens, to obtain discharge of the same, viz.:

And gave undertakings, with the United States Fidelity and Guaranty Company as surety, to secure discharge of the following liens, pursuant to section 21 of the Lien Law, subdivision 5:

The other material facts are hereinafter stated and are not in dispute.

The right of laborers and material-men to liens for the improvement of real property is regulated by the terms of the contract, and whether any fund exists -to which the liens attach is dependent upon its provisions. Larkin v. McMullen, 120 N. Y. 206.

All persons furnishing labor or materials to the sub[545]*545contractor under a contract for a public improvement have a right to inspect the subcontract and are chargeable with notice of its contents and with knowledge of their rights thereunder as against the claim of the contractor.

But it is contended, on the outset, that there is a distinction between liens for the improvement of real property under section 4 of the Lien Law and liens for public improvements under section 5 of the Lien Law, and that the lienors herein have a lien on -the funds due the principal contractor from the State regardless of whether any moneys are due from the contractor to the subcontractor.

Section 5 of the Lien Law reads as follows:

“ § 5. Liens under contracts for public improvements. A person performing labor for or furnishing materials to a contractor, his sub-contractor or legal representative, for the construction of a public improvement pursuant to a contract by such contractor with the state or a municipal corporation, shall have a lien for the principal and interest of the value or agreed price of such labor or materials upon the moneys of the state or of such corporation applicable to the construction of such improvement, to the extent of the amount due or to become due on such contract, upon filing a notice of lien as prescribed in this article.”

One contract .alone is mentioned in the section and that is the contract “ by such contractor with the state.” If the language is taken literally, the lien attaches to the amount due on that contract in favor of a person performing labor for or furnishing materials to a subcontractor. It would follow that the contractor who had paid his subcontractor in full might also be compelled to satisfy subsequent liens filed by the subcontractor’s laborers, and material-men.

The power of the Legislature to provide for a direct mechanic’s lien, independent of the indebtedness between owner and contractor, or between contractor and subcontractor, has been seriously questioned, although generally upheld. Jones v. Hotel Co., 86 Fed. Rep. 310; reversed on other grounds, 111 U. S. 449. See same case, 116 Fed. Rep. 793. Under the Lien Law in force in New York, it has, however, been uniformly held that the right to a lien is dependent upon [546]*546something being dne or becoming due to the contractor or furnished under his contract.

The rule is well stated by Grover, J., as follows: “A party furnishing materials or doing work, relying upon the lien given by statute for security, must examine the contract'with the owner; for it is only to the extent of what is due or to become due upon this contract that his lien can attach. If he furnishes the material or does the work for a sub-contractor, in like reliance, he should not only examine the contract with the owner, but also that of the sub-contractor; for if the sub-contractor fails to perform his contract so that nothing becomes payable thereon, or is paid in full according to its terms in case of performance, -there can be no lien. * * * There is no reason for protecting an owner against a lien who has paid the contractor in full pursuant to the contract, not equally applicable to a contractor, who in like manner has paid his sub-contractor. It would be equally unjust to compel a contractor to pay again through the enforcement of a lien as it would the owner. It is no more essential to the security of material-men and laborers in the one case than in the other.” Lumbard v. Syracuse, B. N. Y. R. R. Co., 55 N. Y. 491, 494; French v. Bauer, 134 id 548.

I find no reported case in which it has not been assumed that the same rule applied to liens under contracts for public improvements as to liens for the improvement of real property. While the question is not very plainly stated in Wright v. Schoharie Valley R. Co., 116 App. Div. 542; affd., 191 N. Y. 549, it is there squarely held that liens for material furnished to the subcontractor on a public improvement can be enforced only to the extent of the moneys found to be due him from the contractor. This rule.is in accord with the established policy of the State and is controlling here. An unprofitable contract or subcontract for a public improvement becomes a dubious security for material-men.

It follows that the main question here presented for decision is to what extent -the liens as filed attached, to the moneys earned by the subcontractor and unpaid.

■The following rules determine the extent to which a mechanic’s lien, filed by a subcontractor or a material-man, attaches to the locus in quo:

[547]*547“ 1. If anything is due to the contractor, pursuant to the terms of the contract, when the lien is filed, it attaches to that extent. =

“ 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Koenig v. McCARTHY CONSTR. CO., INC.
100 N.E.2d 338 (Appellate Court of Illinois, 1951)
Moribella v. Depew Paving Co.
176 Misc. 866 (New York Supreme Court, 1941)
Devitt v. Schottin
8 N.E.2d 481 (New York Court of Appeals, 1937)
Hampton v. Incorporated Village of Freeport
244 A.D. 815 (Appellate Division of the Supreme Court of New York, 1935)
Lackawanna Steel Construction Corp. v. State
244 A.D. 831 (Appellate Division of the Supreme Court of New York, 1935)
Globe Plaster Co. v. Seaboard Surety Co.
153 Misc. 415 (New York Supreme Court, 1934)
Butts v. Randall
145 Misc. 708 (New York Supreme Court, 1932)
Glens Falls Portland Cement Co. v. Van Wirt Construction Co.
132 Misc. 95 (New York Supreme Court, 1928)
Giant Portland Cement Co. v. . State
134 N.E. 322 (New York Court of Appeals, 1922)
Rukeyser v. Fountain & Choate, Inc.
185 A.D. 263 (Appellate Division of the Supreme Court of New York, 1918)
Audley Clarke Co. v. W. F. Plass & Bro.
107 Misc. 722 (New York Supreme Court, 1918)
American Radiator Co. v. City of New York
177 A.D. 578 (Appellate Division of the Supreme Court of New York, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
72 Misc. 541, 130 N.Y.S. 726, Counsel Stack Legal Research, https://law.counselstack.com/opinion/upson-v-united-engineering-contracting-co-nysupct-1911.