Milliken Bros., Incorporated v. . City of N.Y.

94 N.E. 196, 201 N.Y. 65, 1911 N.Y. LEXIS 1215
New York Court of Appeals·Decided February 7, 1911·Published·Cited by 35 cases

Opinion

Cullen, Ch. J.

The ■ action was brought to foreclose a mechanics’ lien upon a public improvement, to wit, an armory constructed for the city of New York. The lienors were numerous, and all of them as well as the principal contractor, the James D. Murphy Company, and The City of New York, were .parties to the action. The respondent here is the contractor. The appellants are several lienors who have been denied any right to payment out of the fund deposited by the contractor to discharge the liens and as a condition of obtaining payment from the city, on the sole ground that the liens were filed too late in point of time.

The trial court found that on January 26th, 1904, the respondent, the James D. Murphy Co., entered into a contract with the city of New York, by the armory board of the city, for the erection of an armory building in the borough of Manhattan for the sum of $619,532.33; that the work under said contract was prosecuted until the 8tli of October, 1906, at which time the architects issued a certificate to the effect that, the contractor was entitled to the amount remaining unpaid on the contract, to wit, $96,091.24, less the sum of $2,000, to be retained as a guaranty under certain provisions of the contract, and less also the further sum of $1,000 to be retained for uncompleted work, leaving the amount certified for payment at $93,091.24; that on said date the armory board adopted the following resolution :

Resolved, that the Armory Board does hereby accept the *70 69th Regiment Armory from the contractors as completed with the reservation named-in this resolution ; that the Comptroller be authorized to pay to the James D. Murphy Company, contractors, the sum of Ninety-three thousand and ninety-one and TTT dollars ($93,091.24) for the execution of their contract for the erection of the 69tli Regiment Armory in the Borough of Manhattan, being a payment in full with a reservation therefrom of One thousand dollars ($1,000) until the marble tablet, etc., are properly installed ; and a further reservation of Two thousand dollars ($2,000) as provided in the contract under paragraph ‘ Z,’ for one year from the date of the issuance of the final certificate as a guarantee for the perfect working and efficiency of the steam heating apparatus; that the roofs of the building shall be made tight and any defects which may appear in the entire work; ” that said certificate and resolution were delivered to the comptroller of the city; that on November 17th the engineer in the department of finance reported to the comptroller that the electric work was defective and recommended that $3,091 be retained until such defective work should have been made good ; that thereupon the claim of the contractor was audited at $90,000, and in March following the comptroller drew his warrant for said sum.

As to the condition of the building the trial court refused to find that it was completed on the date of the certificate and resolution, but did find that it was then “ substantially completed” and that shortly thereafter it was occupied by the National Guard as an armory. It also found that on that date certain plumbing work required by the contract was uncompleted, to wit, the installation of water lines over the ammunition room in the armory and that subsequently the contractor caused said water lines to be installed; that such plumbing work consisted of about 100 feet of 2 or 3-inch pipe. The dates the respective liens of the several appellants were filed are as follows: Jerome A. Jackson, November 20,1906 ; Roebling Construction Co., November 21,1906 ; Baker, Smith & Go., November 22, 1906; Patrick II. McNulty, December *71 13, 1906. It further found that between January 31st, 1905, and November 16th, 1906, the appellant Baker, Smith & Co. performed and furnished labor, work and materials to the contractor in or about certain extra work in addition to that provided for by the contract between Baker, Smith & Co. and the James D. Murphy Co., which extra work, labor and materials “ were performed and furnished in conformity with the terms of and towards the performance and completion of the aforesaid contract between the said James D. Murphy Company and the city of New York * * * and were actually used in the execution and completion thereof.” On these facts the trial court decided that each of the appellants’ liens was invalid because not tiled within 30 days after October 8th, 1906, the date of the acceptance by the armory board, though it awarded the appellants personal judgment against the contractor for the amounts of their several liens.

Free access — add to your briefcase to read the full text and ask questions with AI

Milliken Bros., Incorporated v. . City of N.Y., 94 N.E. 196, 201 N.Y. 65, 1911 N.Y. LEXIS 1215 (N.Y. 1911).

94 N.E. 196 (Milliken Bros., Incorporated v. . City of N.Y.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Munoz Trucking Corp. v. Darcon Construction, Inc.
2017 NY Slip Op 6283 (Appellate Division of the Supreme Court of New York, 2017)
Schenectady Municipal Housing Authority v. Keystone Metals Corp.
245 A.D.2d 725 (Appellate Division of the Supreme Court of New York, 1997)
J. Castronovo, Inc. v. Hillside Development Corp.
160 A.D.2d 763 (Appellate Division of the Supreme Court of New York, 1990)
Tri-City Electric Co. v. People
473 N.E.2d 240 (New York Court of Appeals, 1984)
Tri-City Electric Co. v. People
96 A.D.2d 146 (Appellate Division of the Supreme Court of New York, 1983)
Bernardo v. Steelco, Division of Metropolitan Steel Industries, Inc.
115 Misc. 2d 1020 (New York Supreme Court, 1982)
N. W. Developers, Inc. v. Jeremiah Burns, Inc.
55 A.D.2d 580 (Appellate Division of the Supreme Court of New York, 1976)
Ingalls Iron Works Company v. Fehlhaber Corporation
327 F. Supp. 272 (S.D. New York, 1971)
Ingalls Iron Works Co. v. Fehlhaber Corp.
275 F. Supp. 623 (N.D. New York, 1967)
United States v. Certified Industries, Inc.
361 F.2d 857 (Second Circuit, 1966)
Reynolds Metals Co. v. People
41 Misc. 2d 694 (New York Supreme Court, 1963)
Biondo v. City of Rochester
18 A.D.2d 78 (Appellate Division of the Supreme Court of New York, 1963)
In re Flushing Asphalt Corp.
188 Misc. 304 (New York Supreme Court, 1946)
Battistelli v. Jacobson
13 Conn. Super. Ct. 196 (Connecticut Superior Court, 1944)
Battistelli v. Jacobson
13 Conn. Supp. 196 (Pennsylvania Court of Common Pleas, 1944)
Allison v. Schuler
36 P.2d 519 (New Mexico Supreme Court, 1934)
Schuessler v. Mack
240 A.D. 449 (Appellate Division of the Supreme Court of New York, 1934)
White Plains Sash & Door Co. v. Doyle
186 N.E. 33 (New York Court of Appeals, 1933)