Biondo v. City of Rochester

18 A.D.2d 78, 238 N.Y.S.2d 7, 1963 N.Y. App. Div. LEXIS 4311
CourtAppellate Division of the Supreme Court of the State of New York
DecidedFebruary 21, 1963
StatusPublished
Cited by6 cases

This text of 18 A.D.2d 78 (Biondo v. City of Rochester) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Biondo v. City of Rochester, 18 A.D.2d 78, 238 N.Y.S.2d 7, 1963 N.Y. App. Div. LEXIS 4311 (N.Y. Ct. App. 1963).

Opinion

Bastow, J.

On February 28, 1958 the defendant, City of Rochester, (herein “ city”) and defendant, Rae-Bon Construction, Inc. (herein Rae-Bon ”) entered into a contract in writing for the performance by Rae-Bon of certain work, including excavation, laying of sewers, paving and installation of concrete curbs, gutters and sidewalks on a public street in the city. The contract price, as adjusted, was $32,070.17. There is no dispute that plaintiff performed a portion of Rae-Bon’s contract and installed the concrete curbs, gutters and sidewalks.

In this action plaintiff seeks to enforce a lien against the public improvement for a claimed unpaid balance of $2,452.82 for such labor and services. It is not disputed that this amount remains [80]*80unpaid. The area of disagreement is whether plaintiff performed the work as a subcontractor of Rae-Bon or as a subcontractor of a third party, Case Excavating, Inc. (herein “ Case ”), which in turn was a subcontractor of Rae-Bon.

Following a nonjury trial, the court found that in April, 1958 Rae-Bon and Case entered into a written agreement by the terms of which Case agreed to perform in its entirety Rae-Bon’s prime contract with the city. The latter instrument contained provisions that the contractor might not assign or sublet the contract without the previous written consent of the City Comptroller and that “All sub-contractors must be approved by the Commissioner ” of Public Works of the city. The trial court found that such approval had been granted and made a further finding that the provision requiring “ written approval of performance ” had been waived. It was further found that in May, 1958 Case “ sublet ” to plaintiff the portion of the work for installation of cement curbs, gutters and sidewalks.

We conclude that these findings of fact are against the weight of the credible evidence and must be reversed. Justification for this action requires a recital of some of the pertinent facts. The sole stockholders of Rae-Bon were Raymond Chinappi, his wife and mother-in-law. The three were also the officers and directors. The corporation was in the general construction business and had an office in the City of Rochester. Case, on the other hand, during its short existence in 1958 was somewhat illusory. It was organized on April 28,1958 by one Eric Ruble, Chinappi and their respective wives. Each group owned 50% of the outstanding stock and the four constituted the board of directors. Case rented an office in the Rae-Bon building from April, 1958 to January, 1959 but the monthly rental of $75 was not agreed upon until November, 1958 and no rental statements were rendered by Rae-Bon or paid by Case until the “ arrangement ” between the two corporations terminated in January, 1959. Case was not identified by a sign or in any other manner in the office or building of Rae-Bon.

■ Case owned no equipment except some surveying instruments and a station wagon. Upon formation of the corporation it purchased a power shovel for $3,000 from Rae-Bon and in two or three weeks traded the shovel for a new one purchased on credit. In January, 1959 Avhen the relationship between Rae-Bon and Case ended, the latter Avas unable to make the monthly payments of $780. Thereupon Rae-Bon took possession of the shovel and assumed the balance due under the contract but paid Case nothing for. its equity in the shovel. The other equipment used by Case Avas rented from Rae-Bon but the monthly payments of [81]*81$1,828.67 were not fixed until November, 1958 when the relationship between the two corporations was near its end. The total of all rental accounts was deducted from the moneys Rae-Bon owed Case when they parted company in January, 1959.

It is against this background that we evaluate the sharply conflicting testimony of plaintiff on the one hand that he contracted with Rae-Bon and the testimony of Chinappi and Ruble that the contract was made with Case. The trial court, as stated, passed upon findings and conclusions submitted by the parties but wrote no decision so we do not have the benefit of his evaluation of this and other conflicting testimony on the several issues presented. We believe the testimony of plaintiff that he contracted with Rae-Bon to perform as subcontractor a portion of the contract with the city. This agreement was reached at a meeting of the three men (plaintiff, Chinappi and Ruble) in Rae-Bon’s office. The documentary evidence establishes that plaintiff was to receive from Rae-Bon $1.70 per lineal foot for installing curbs and gutters and $1 per square foot for sidewalks. The testimony of Ruble that the price for the gutters was $1.65 per foot and that there was no conversation about the sidewalks is unbelievable. He gave no testimony as to the agreed price of the sidewalk work or when and under what circumstances agreement was reached on this portion of the work Avhich concededly plaintiff performed.

This conclusion is fortified by the subsequent conduct of RaeBon. When plaintiff went to the improvement to start work he Avas told by a City Inspector that he could not proceed unless certified by the city as a subcontractor. This was in May, 1958 — a month after the date of the contract between Rae-Bon and Case. Received in evidence Avas a letter of May 27, 1958 addressed to the City Engineer by Rae-Bon and signed by Chinappi requesting permission to use Biondo “as a subcontractor for gutters and walks on Jay Street.” Such permission was granted by letter of May 28, 1958.

It is true that certain payments on account to plaintiff were made by checks drawn by Case and on one occasion one of Case’s suppliers was paid by check of Case at the request of Biondo. This, however, has small probative weight once it is determined there was a contract between Biondo and Rae-Bon. The same may be said about the certificate of insurance issued by plaintiff’s insurance agent to Case and not to Rae-Bon. Biondo told Chinappi to telephone the former’s agent and the certificate Avould be issued. There is no proof that plaintiff directed his insurance agent to issue a certificate describing Case as a party to Biondo’s subcontract. This was an ex parte act on the part [82]*82of Chinappi and it cannot be found that it was done with the knowledge and consent of Biondo.

In any event the standing of Case to enter into a subcontract with plaintiff is based upon findings that Bae-Bon and Case made a written contract that the latter should perform the entire prime contract between Bae-Bon and the city and that the city waived the contract provision requiring written approval of such subcontracting. Both findings are against the weight of the credible evidence.

There is documentary proof that on April 10, 1958 Bae-Bon and Case agreed that the latter would perform all of the Jay Street improvement for the total prime contract price of $32,070.17. But the truth as to the work actually to be performed by Case emerges from the certificate of insurance issued to Bae-Bon on behalf of Case. Therein the work to be performed is described as “ sewer construction “ street or road paving or repaving ”. This is the remaining portion of work to be done under the prime contract that had not been subcontracted to plaintiff. Buhle admitted on cross-examination that he always knew that the curbs, gutters and sidewalks would be performed ‘ ‘ by someone else because Case Excavating was not competent to do this kind of work.” All of this fortifies the view that Bae-Bon entered into two subcontracts — one with plaintiff for installation of curbs, gutters and sidewalks; the other with Case for the remainder of the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Munoz Trucking Corp. v. Darcon Construction, Inc.
2017 NY Slip Op 6283 (Appellate Division of the Supreme Court of New York, 2017)
Schenectady Municipal Housing Authority v. Keystone Metals Corp.
245 A.D.2d 725 (Appellate Division of the Supreme Court of New York, 1997)
Metivier v. Sarandrea
154 Misc. 2d 355 (New York Supreme Court, 1992)
N. W. Developers, Inc. v. Jeremiah Burns, Inc.
55 A.D.2d 580 (Appellate Division of the Supreme Court of New York, 1976)
Ingalls Iron Works Company v. Fehlhaber Corporation
327 F. Supp. 272 (S.D. New York, 1971)
Ingalls Iron Works Co. v. Fehlhaber Corp.
275 F. Supp. 623 (N.D. New York, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
18 A.D.2d 78, 238 N.Y.S.2d 7, 1963 N.Y. App. Div. LEXIS 4311, Counsel Stack Legal Research, https://law.counselstack.com/opinion/biondo-v-city-of-rochester-nyappdiv-1963.