W. A. Brockhurst Co., Inc. v. City of Yonkers

150 Misc. 623
CourtNew York Supreme Court
DecidedNovember 15, 1933
StatusPublished
Cited by5 cases

This text of 150 Misc. 623 (W. A. Brockhurst Co., Inc. v. City of Yonkers) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. A. Brockhurst Co., Inc. v. City of Yonkers, 150 Misc. 623 (N.Y. Super. Ct. 1933).

Opinion

Morschauser, J.

In this action the plaintiff and various defendants seek to foreclose thirty-seven liens against the city of Yonkers and the board of education of the city of Yonkers arising out of the general contract made with Kenneth MacKay & Co., Inc., general contractor, for the construction of the Longfellow Junior High School.

The contract price was $654,113.65. By omissions this was reduced to $652,879.32. Against this sum, the defendant city is credited with undisputed payments amounting to $550,828.89, leaving a balance of $102,050.43. From this balance should be deducted the fair and reasonable cost of completion which is found to be the sum of $2,105.67, reducing said balance to $99,944.76, which represents the fund applicable to the payment of valid liens provided: (a) Plaintiff’s contentions are sustained that $75,000 was improperly paid to the general contractor for which it is not entitled to credit, and that (b) no deduction be allowed on counterclaim under the liquidated damage clause of-the contract.

Consideration will first be given to the disputed payments of $75,000 on account of retained percentages. Plaintiff claims these payments were not made in good faith; that they were advance payments made to avoid the provisions of article 2 of the Lien Law (§ 3 et seq.) to enable the contractor to pay debts other than those incurred for the erection of said school; that contractor falsely and fraudulently represented that it had no unpaid labor or material bills; that the board and city knew such representations to be false, but nevertheless in contravention of the contract and the rights of creditors paid said contractor $25,000 on August 21, 1930, and $50,000 on September 19, 1930, out of the retained percentage fund without requiring releases of lien or receipts of payments from materialmen and subcontractors in either instance.

[625]*625The claim of bad faith on the part of the board and city arises out of the following situation: On March 22, 1930, the contractor assigned to the First National Bank and Trust Company of Yonkers all its right, title and interest in and to all retained percentages that should accrue to the contractor under the provisions of said contract in consideration of which the assignee agreed from time to time to loan the contractor upon its promissory note or notes or renewals or substitutions a sum not exceeding $50,000 inclusive of moneys already advanced. It is provided that said agreement should be subject to the approval of the board of education and the corporation counsel of Yonkers “ as to its form.” The assignment was received by the board March 28, 1930, with directions from contractor that the board deliver warrants or drafts only to the bank, although payable to the contracting corporation, until further notice. This assignment was not filed as required by section 16 of the Lien Law and was invalid.

Plaintiff claims that at the date of the execution of this assignment the balance due contractor for work done and extras exceeded $216,329.40 and that the failure to file said assignment as a public record as provided by the Lien Law lulled the creditors into a sense of fancied security prompting the unsuspecting subcontractors to continue construction to substantial completion at the time such payments were made. This is denied by defendants who claim that the provisions of the contract were explicitly followed in that before making such payments they had (a) proper certificate from the architect, (b) satisfactory evidence that no liens were filed or would be filed, and (c) approval of corporation counsel. They also assert that such payments were not hurriedly or secretly made but, on the contrary, pursuant to appropriate resolutions adopted at public meetings of the board of education and further deny that any fraud or collusion can be imputed from the circumstances attending the payments. A determination of the good faith of the board and city requires a construction of the provisions of the contract specifically with respect to their duties under and in relation to same.

The contract of February 15, 1929, by paragraphs 1 and 10, specifically provides that the plans and specifications, etc., should be a part thereof. General Conditions B, subdivision (e) of specifications relating to payment to subcontractors, provides that, when payment is made to contractor for work done or material furnished by subcontractors, the contractor shall pay subcontractors amounts due before he shall be entitled to receive a succeeding payment. It further provides: “ A sufficient reason for refusal on the part of the architect to issue the certificate shall be evidence of any lien or claims properly chargeable to the contractor for which if established [626]*626the owner of the premises might become hable. The evidence above referred to shall be construed to mean the receipt by the architect of a statement from any party or parties furnishing work or material * * * to the effect that the contractor has failed to properly indemnify or compensate them therefor, * * * whether or not any hen or hens therefor have been filed by the said party or parties.” (General Conditions B, subd. e, p. 15.)

Paragraph 12 of the contract, relating to semi-monthly payments, and paragraph 4, relating to retained percentages, must be read in connection with paragraph 18, relating to hens, as well as with the general conditions of specifications, relating to payments to subcontractors, and to hens. (General Conditions B, subd. i.) Specification provision relating to hens differs in context from the contract provision, paragraph 18, in that it refers to the “ refusal ” rather than the “ failure ” of the subcontractor to furnish release or receipt in full. Refusal contemplates action rather than inaction; a refusal after demand. Subcontractors had right to expect demand before certificate was issued.

Paragraph 13 provides for submission by contractor to architect of written apphcation for each payment accompanied, if required, by receipts or vouchers from subcontractors showing payment to them, and gave architect supervisory power with respect to apportionment of payments by contractor to subcontractors.

These provisions contemplated a scheme for the protection of subcontractors by placing the supervision and control of ah payments to general contractor under the power and direction of the architect and to circumvent his disposition thereof to the detriment of subcontractors furnishing material and labor on the job.

By recent enactment such moneys paid to a contractor are declared to constitute trust funds in his hands. (Lien Law, § 25-a, added by Laws of 1932, chap. 627, § 8.)

When apphcation was made for the withdrawals from the retained percentage fund in each instance, the architect knew there were outstanding unpaid claims of subcontractors for material and labor furnished to said job. It is immaterial that such claims were not reduced to filed hens. The architect properly interpreted his duty to refuse certificate in the face of claims outstanding and unpaid to subcontractors and not only brought the situation to the attention of the board, but sought advice of the corporation counsel, who interpreted the architect’s duty only according to the provisions of the resolution of the board of education. That resolution provided for payment of $50,000 to the general contractor among other things, “ provided a certificate is obtained from the architect.”

On September 17, 1930, the architect called to the attention of [627]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

N. W. Developers, Inc. v. Jeremiah Burns, Inc.
55 A.D.2d 580 (Appellate Division of the Supreme Court of New York, 1976)
Biondo v. City of Rochester
18 A.D.2d 78 (Appellate Division of the Supreme Court of New York, 1963)
W. A. Brockhurst Co. v. City of Yonkers
180 Misc. 820 (New York Supreme Court, 1942)
Hernandez v. First Nat. Bank & Trust Co.
27 F. Supp. 874 (S.D. New York, 1939)
Barclay v. Corn Exchange Bank Trust Co.
155 Misc. 684 (New York Supreme Court, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
150 Misc. 623, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-a-brockhurst-co-inc-v-city-of-yonkers-nysupct-1933.