Hernandez v. First Nat. Bank & Trust Co.

27 F. Supp. 874, 1939 U.S. Dist. LEXIS 2734
CourtDistrict Court, S.D. New York
DecidedJune 2, 1939
StatusPublished
Cited by2 cases

This text of 27 F. Supp. 874 (Hernandez v. First Nat. Bank & Trust Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hernandez v. First Nat. Bank & Trust Co., 27 F. Supp. 874, 1939 U.S. Dist. LEXIS 2734 (S.D.N.Y. 1939).

Opinion

GALSTON, District Judge.

An action somewhat unusual in nature is brought by the plaintiff in the effort to secure payment for labor and materials which he supplied as a sub-contractor in connection with the construction of the Longfellow Junior High School in Yonkers, New York. A contract for the construction of that school was entered into on February 15, 1929, between the contractor, Kenneth McKay & Co., Inc., and the Board of Education of the City of Yonkers. The contract price was $611,660. It is alleged that there was owing to the sub-contractor, the plaintiff herein, from Kenneth McKay & Co., Inc., as a balance due on September 17, 1930, the sum of $32,081.58. On May 21, 1931, plaintiff filed in the office of the Comptroller of the City of Yonkers an alleged notice of lien.

The contract with the Board of Education provided that neither the final payment nor any part of retained percentages of instalment payments should become due unless the contractor, if required, should deliver to the Board a complete release of all liens arising out of the contract.

It is alleged that on March 22, 1930, and before the completion of the building, the contractor executed an assignment in favor of the First National Bank & Trust Company of Yonkers, one of the defendants herein, of the retained percentages and monies payable for extra work on said contract, to cover a loan of the maximum amount of $50,000. It is alleged that this assignment was secretly filed by the Bank with the Board of Education of the City of Yonkers and was not filed with the Comptroller of the City of Yonkers, the chief fiscal officer pf the City 'of Yonkers.

Thereafter, in August 1930, the Board of Education paid to the contractor out of the retained percentage funds, $25,000, from which sum the defendant bank received $7,000; and in the month of September 1930 the Board paid and the bank received, under the aforesaid assignment, the sum of $50,000.

It is alleged that at the time of making these payments in August and September 1930 the defendants knew that the monies thus advanced were trust funds within the meaning of Sec. 36-a of the Lien Law of the State of New York, Consol.Laws, c. 33, and that they both knew that the [876]*876contractor had creditors whose claims 'for work, labor and services had not been paid.

It appears, now, from the complaint and the proof in this case, that an action was instituted for the benefit of unpaid lienors, .entitled William A. Brockhurst Co., Inc., Plaintiff, against the City of Yonkers, New York, et al., wherein it was alleged that aforesaid sums of $25,000 and $50,000, aggregating $75,000, were applied for and used by Kenneth McKay & Co., Inc., the general contractors, for the payment of obligations other than those of materialmen and sub-contractors. In that action the plaintiff sought and obtained judgment, Brockhurst v. City of Yonkers, 150 Misc. 623, 268 N.Y.S. 637; Id., 244 App.Div. 799, 280 N.Y.S. 982; Id., 270 N.Y. 459, 1 N.E.2d 965, that there was owing from the defendant, the Board of Education of the City of Yonkers, in connection with the construction of the Longfellow High School, the sum of $99,944.76 with interest; but the alleged lien of the plaintiff herein was disallowed for failure to comply with Sec. 21, subdivision 2, of the Lien Law of the State of New York, as amended by Laws 1930, c. 859, § 12. That act provides in part that a lien may be discharged “when three months have elapsed since the filing of the notice of lien, unless, before the expiration thereof, either an order continuing said lien has been filed * * * or a notice of the pendency of an action to enforce said lien has been filed.”

Following the entry of that judgment payments were made pursuant thereto and the records of the Comptroller’s office show that lienors received against this balance of $99,944.76 the sum of $88,796.74. Now this plaintiff seeks to obtain the balance— $11,148.02 — and in addition sufficient from both defendants to pay its judgment of $38,369.56 with interest against the contractor.

So far as the plaintiff’s claim against the City of Yonkers for the alleged balance of the $99,944.76 is concerned, its difficulty arises from the confusion in the language of paragraph 22 of the complaint with the actual finding of the state court. It is alleged by the plaintiff here that the judgment in that action ordered the Board of Education to pay “to the contractors’ job creditors” the sums therein provided,” but the fact is that the judgment said nothing about job creditors but made provision for the payment of lien creditors. The following finding of fact appears in the printed case on appeal in the Brockhurst case: “18. That at the time of the filing by the various defendants of their respective liens * * * there was due from the Board of Education * * * to the defendant Kenneth McKay & Co., Inc. * *' *• the sum of $99,944.76, and which sum is applicable to the payment of the liens and claims hereinafter provided for, and only to such extent.” And — “311. That to the extent to which the fund herein shall not be exhausted by the payment of the various valid liens hereinafter provided for with interest, costs and allowances, the said fund shall revert to the said Board of Education of the City of Yonkers.”

In Brockhurst v. City of Yonkers, 270 N.Y. 459, 1 N.E.2d 965, the lien of the plaintiff herein is specifically disallowed.

Referring again to the record in the Brockhurst case the following conclusions of law were found: “1. There is now due and owing from the defendants, the Board of Education * * * to the holders of valid liens, as herein found, * * * so much of the sum of $99,944.76 as shall be necessary to pay the amount of allowances, costs and disbursements herein provided and filed, and subsisting liens herein found with interest on each.” (Italics mine). And — “69. That the City of Yonkers and the Board of Education of the City of Yonkers, New York, are not entitled to credit for the payment of $75,000. * * * except as such amount as there shall be a surplus thereof in said fund after the provision has been made for the payment of all sums by way of valid liens * *

It must be recognized at once that the use of the term “fund” in connection with the balance of the amount paid by the Board to the lien holders is not quite accurate. The contract price for the building was $654,113.65. By omissions that sum was reduced to $652,879.32. Against that sum there were undisputed payments amounting to $550,828.89, leaving a balance of $102,050.43. The trial court in the Brockhurst case said that there should be deducted from that balance the fair and reasonable cost of completion which was found to be the sum of $2,105.67, thus “reducing said balance to $99,944.76”. It was because the Board of Education was given no credit for the payment of $75,-000 made to the general contractor and by it in part paid to the defendant bank [877]*877that it was adjudged to pay the balance of $99,944.76, or such part of it as valid lienors were entitled to receive. Now in this case the Comptroller’s statement shows that there was paid to valid lien creditors in full all that they were entitled to receive and said payments of interest and principal amounted to $88,796.74. Beyond that the Board of Education had no liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peters v. Griffin (In Re Griffin)
111 B.R. 42 (W.D. New York, 1990)
W. A. Brockhurst Co. v. City of Yonkers
180 Misc. 820 (New York Supreme Court, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
27 F. Supp. 874, 1939 U.S. Dist. LEXIS 2734, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hernandez-v-first-nat-bank-trust-co-nysd-1939.