Giant Portland Cement Co. v. . State

134 N.E. 322, 232 N.Y. 395, 1922 N.Y. LEXIS 1134
CourtNew York Court of Appeals
DecidedJanuary 24, 1922
StatusPublished
Cited by21 cases

This text of 134 N.E. 322 (Giant Portland Cement Co. v. . State) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Giant Portland Cement Co. v. . State, 134 N.E. 322, 232 N.Y. 395, 1922 N.Y. LEXIS 1134 (N.Y. 1922).

Opinion

Hiscock, Ch. J.

This appeal deals with conflicting claims to a surplus arising under a contract for road construction between the plaintiff and various defendants and between defendants themselves. The parties all" claim under mechanics’ hens with the exception of the National Bank of Commerce which claims under an assignment by the contractor of moneys due and to grow due upon the contract.

In 1914 one Cowles entered into a contract with the state for the construction of a highway. Materials were sold to him and labor performed for him for the purpose of carrying out said contract by one Goodrich and by the parties to this appeal except the bank, which was an assignee of funds under his contract as above stated. After a while Cowles defaulted in the performance of the contract and the state completed the same at an expense which left a balance due to the contractor of $7,646.46. In due time to make them effective, hens were filed against this balance by Goodrich on October 30, 1914, for the sum of $206; by plaintiff, November 5th, 1914, at 10 a. m., for $8,668.84; by the Barber Asphalt Paving Company on November 5,1914, at 4.30 p. m., for $2,154.02, *400 and by Cowles and others on and subsequent to December 21, 1914, for various sums claimed to be due them respectively for labor. In addition the bank on October 31, and November 25, 1914, in the proper offices filed the assignment by the contractor above referred to. The Goodrich claim has been collected in full and is not a subject of dispute or consideration on this appeal.

In due time plaintiff commenced this action to foreclose its lien, duly filing notice of pendency and joining as defendants the various claimants now represented on this appeal. The judgment at the end of the resulting trial after providing for the payment of costs to various parties, in substance awarded to plaintiff payment in full of its claim after applying certain dredits which it conceded and thereafter in the order in which their notices of lien and assignment had been filed payment of their respective claims to the Barber Asphalt Paving Company, the National Bank of Commerce and the'labor lienors, the result as between the latter and the bank being accomplished in a somewhat circuitous manner, description of which is immaterial in this discussion. The Appellate Division modified this judgment by substantially reducing the amount awarded to plaintiff on the ground that part of the materials included in its claim had been retaken by it and should be credited upon its claim at the price at which they had been sold to the contractor rather than at the amount of the net proceeds realized upon the resale of such materials after retaking.

With this statement of the general facts we proceed to the consideration of the claim and rights of plaintiff and of the various labor claimants whose rights alone are in dispute upon this appeal, stating in connection therewith such further special facts as may be necessary to such consideration.

The plaintiff was a manufacturer of cement and it made a contract to furnish the contractor a large amount *401 of its product for use in the performance of his contract. Two distinct lots' of cement which it sold and delivered to the contractor under its contract were by him.never used thereon. One lot was by him diverted without knowledge or consent of plaintiff through sale to other parties, but whether before or after his default we are unable to determine. The other lot had been delivered by shipment to the contractor, but still rem’ained on board the cars at the time he defaulted and ceased building operations. After plaintiff had filed its hen for the full amount of its claim including both lots of cars, it made an arrangement with the contractor with respect of the last lot which read as fohows: “You (plaintiff) are authorized to retake 11 cars of cement shipped by you to H. M. Cowles * * * and to dispose of the same in the best market possible and apply the net proceeds on your account.” There seems also to have been some consultation between the plaintiff and the appehant bank on this subject but which we do not regard as important. Thereafter plaintiff did retake the cars of cement as stated, sold the cement and apphed the proceeds generally on its claim against the contractor. It is in substance found and seems to be conceded that it was desirable for all parties to sell this cement which would have deteriorated if allowed to stand and against which considerable track demurrage was running and that plaintiff acted in good faith in procuring as advantageous a price as it could for the cement. Nevertheless as the result of sale at a lower price than that at which the cement had been sold to the contractor and as the result of demurrage and various expenses the net proceeds received by the plaintiff and credited on its account were substantially less than the price at which the cement had been sold and at which it was included in plaintiff’s hen.

Under the contract between plaintiff and the contractor the bags in which the former shipped its cement *402 could be returned by the latter and credited at a certain price per bag. At the same time at which the contractor authorized the plaintiff to retake the cement he also authorized it to retake such bags as it could find and credit them on the account. It thus recovered a large number of bags which it credited generally at the sum of $2,763.30 upon the indebtedness due from the contractor.

Upon these facts and independent of the claim of the labor lienors to a priority under the statute, which will be discussed hereafter, three questions arise in respect of plaintiff’s claim and its rights thereunder.

The first is the one arising in connection with the resale by the contractor of certain carloads of cement, as above stated, whether a materialman who in good faith furnishes materials to be used in the completion of a contract within the scope of the Mechanics’ Lien Law, loses his right to a lien therefor because the contractor without his knowledge or consent has diverted the materials to some other purpose and has not in fact used them in the construction of the improvement as contemplated. Strangely enough this question does not seem to have been decided by this court and the guide to the answer to be given of course must be found in the interpretation to be placed upon the statute covering hens.

That statute (L. 1911, ch. 873, as amended by L. 1916, ch. 507) provides (§ 5): 'A person performing labor for or furnishing materials to a contractor, his subcontractor or legal representative, for the construction of a public improvement pursuant to a contract by such contractor * * * shall have a lien ” therefor; (§ 12) the notice (of such lien) shall state * * * a description of the pubHc improvement upon which the labor was performed and materials expended, the kind of labor performed and materials furnished; ” (§ 1) “ The term ‘ materialman ’ * * * means any person who furnishes material for such improvement.”

*403 We have so often referred to the purpose of this act to protect materialmen and laborers who furnish either materials or labor for purposes of construction and have so often recognized that the statute is to be liberally construed to effect this purpose that it is unnecessary to say anything more along that line.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Materials, Inc. v. Universal Group of New York, Inc.
101 A.D.3d 1529 (Appellate Division of the Supreme Court of New York, 2012)
Claudio Perfetto, Inc. v. Waste Management
274 A.D.2d 389 (Appellate Division of the Supreme Court of New York, 2000)
Pennex Aluminum Co. v. International Fidelity Insurance
818 F. Supp. 772 (M.D. Pennsylvania, 1993)
Regal Lumber Co. v. Buck
157 Misc. 2d 376 (New York County Courts, 1993)
Niagara Venture v. Sicoli & Massaro, Inc.
162 A.D.2d 992 (Appellate Division of the Supreme Court of New York, 1990)
In re Wade Lupe Construction Co.
134 Misc. 2d 738 (New York Supreme Court, 1987)
P.T. & L. Construction Co. v. Winnick
59 A.D.2d 368 (Appellate Division of the Supreme Court of New York, 1977)
International Heating & Air Conditioning Corp. v. Rich Construction Co.
360 N.E.2d 636 (Massachusetts Supreme Judicial Court, 1977)
Fedders Central Air Conditioning Corp. v. Karpinecz & Sons, Inc.
83 Misc. 2d 720 (Civil Court of the City of New York, 1975)
American Blower Corp. v. James Talcott, Inc.
18 Misc. 2d 1031 (New York Supreme Court, 1959)
Tabet v. Davenport
260 P.2d 722 (New Mexico Supreme Court, 1953)
Merritt v. Dansmith Corp.
240 A.D. 338 (Appellate Division of the Supreme Court of New York, 1934)
In re Stamford Road Const. Co.
5 F. Supp. 650 (D. Connecticut, 1933)
Scarsdale National Bank v. United States Fidelity & Guarantee Co.
239 A.D. 100 (Appellate Division of the Supreme Court of New York, 1933)
National Lumber Co. v. F. Braun & Son, Inc.
237 A.D. 426 (Appellate Division of the Supreme Court of New York, 1932)
White v. C. M. McLean & Sons, Inc.
235 A.D. 342 (Appellate Division of the Supreme Court of New York, 1932)
Anderson v. John L. Hayes Construction Co.
153 N.E. 28 (New York Court of Appeals, 1926)
Rapid Fireproof Door Co. v. Largo Corp.
216 A.D. 395 (Appellate Division of the Supreme Court of New York, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
134 N.E. 322, 232 N.Y. 395, 1922 N.Y. LEXIS 1134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/giant-portland-cement-co-v-state-ny-1922.