Hercules Powder Co. v. Knoxville, La Follette & Jellico Railroad

113 Tenn. 382
CourtTennessee Supreme Court
DecidedSeptember 15, 1904
StatusPublished
Cited by21 cases

This text of 113 Tenn. 382 (Hercules Powder Co. v. Knoxville, La Follette & Jellico Railroad) is published on Counsel Stack Legal Research, covering Tennessee Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hercules Powder Co. v. Knoxville, La Follette & Jellico Railroad, 113 Tenn. 382 (Tenn. 1904).

Opinion

M’r. Justice Wilkes

delivered the opinion of the Court.

This hill seeks to fix a lien upon the railroad company for the cost of powder and other blasting material furnished to construct the railroad and blast a tunnel on its line known as “Dossett’s Tunnel.”

[385]*385Mason, Hoge & Co. bad a contract with tbe railroad company to build the road, excavate the tunnel, and furnish all the necessary material for that purpose. They sublet the excavating and boring of this tunnel to Cole & Co., who in terms agreed to do all the work and furnish all necessary material and labor for that purpose. Cole & Co. made a contract with each of the complainant companies, to wit, the Hercules Powder Company and the Repauno Chemical Company, by which they agreed to buy from these companies all of the explosives and explosive supplies Avhich would be required in the excavation or boring of said tunnel.

The powder company furnished under its contract four bills or lots — one October 13, 1902, amounting to $2,200; one May 27, 1903, $2,200; one July 8, 1903, $480; and the last September 18, 1903, $384.36.

Cole & Co: paid on account $721.46, leaving due $4,543.90. All of the material bought by this company was used in the construction and boring of this tunnel.

The chemical company furnished in March, 1903, $4,534.03 of explosive material, and Cole & Co. paid it on account $3,636.76, leaving a balance unpaid of $897.36.

About October 1, 1903, Cole & Co. announced to its creditors that they were insolvent, and could not complete their contract with the railroad.

On October 10, 1903, each of complainant companies notified the railroad company that they had furnished [386]*386explosive materials to Cole & Co., for which they had not been paid, as before stated, and that they claimed liens upon the railroad company for the amounts due them.

Upon the hearing the chancellor held that complainants had no lien for the explosive materials furnished Cole & Co. as against the railroad, and dismissed the bill, and complainants appealed.

In the court of chancery appeals the majority of that court were of the opinion that explosives used in excavating a roadway through a tunnel in building a railroad was material within the meaning of the Acts of 1883 and 1891, and that complainants under these acts were entitled to liens upon the railroad property, provided proper notices were given the railroad as provided by those acts.

It held, however, that the Repauno Chemical Company had not given such notice, and was entitled to no lien, and that the Hercules Powder Company was entitled only to a lien for the explosives furnished Cole & Co. within ninety days of November 10, 1903, when notice of the lien was given the railroad company; and under this holding adjudged the powder company entitled to a judgment for $384.36.

The Hercules Powder Company assigns as errors that part of the holding and decree of the court of chancery appeals which finds and adjudges that it is only entitled to a lien upon the Knoxville, Lafollette & Jellico Railroad Company’s railroad and property for the blasting [387]*387materials furnished to Cole & Co. within ninety days from November 10, 1903, the date of said notice, and that it is not entitled to a lien for the whole balance due to it for blasting materials furnished under its said contract with Cole & Co., amounting to $4,543.90.

The court of chancery appeals found that G. H. Cole & Co. agreed and contracted with the Hercules Powder Company to buy from! it all of the explosives needed in the excavation of Dossett’s tunnel under their contract with Mason, Hoge & Co.; that said explosives were to be furnished in the quantities and as ordered by G. H. Cole & Co., and were to be paid for within thirty days after they were used; that the Hercules PoAvder Company actually delivered goods to Cole & Co. under said contract on September 18, 1903, and that on October 10, 1903, the Hercules Powder Company gave the notices required by the Acts of 1891 of the fact that it had furnished said material and claimed said lien.

It is assigned as error that under these facts the court of chancery appeals should have held, and erred in not holding, that the' contract to furnish said blasting material was an entirety, and that the Hercules Powder Company had ninety days from the date that the last material was delivered under said contract within which to give said notice; and that the giving of said notice on October 10, 1903, entitled the complainant to a lien for the full balance due to it for the material furnished as aforesaid, which is found by the court of chancery .appeals to be the sum of $4,543.90.*

[388]*388The Repauno Chemical Company assigns as error that part of the decree of the court of chancery appeals which finds and adjudges that it is not entitled to a lien upon the Knoxville, Lafollette & Jellico Railroad Company’s railroad and property for the balance due it for the materials furnished by it to Cole & Co., with which to excavate said Dossett’s tunnel. It is claimed that said court should have held, and erred in not holding, that the Repauno Chemical Company was entitled to a lien upon said railroad company’s railroad and property under chapter 220, page 296, of the Acts of 1883, as amended' by chapter 98, page 215, of the Acts of 1891, and should have decreed, and erred in not decreeing, that complainant was entitled to have said railroad company’s railroad and property sold for the satisfaction and payment of complainant’s said claim.

The court of chancery appeals based its decree denying the Repauno Chemical Company said lien on the ground that it did not deliver any of said material within ninety days of the date of its said notice to the railroad company that it claimed said lien. With reference to the facts governing this claim the court of chancery appeals said:

“The complainant Repauno Chemical Company made a contract with Cole & Co., as before stated, to furnish all the explosives and explosive supplies needed in their contract with Mason, Hoge & Co., and all the material actually furnished under this contract by the Repauno Chemical Company waá shipped on March 9 and March [389]*38917,1903, to Cole & Co., and aggregated in value the sum of $4,534.03. Under its contract with Cole & Co. the powder used in each month was to be paid for by'Cole & Co. in the following month. Cole & Co. are entitled to credit on said amount of $3,636.76, leaving a balance due the Repauno Chemical Company of $897.27.

“About October 1,1903, Cole & Co. announced to their creditors that they were insolvent, and could not com-píete their contract. At this time Cole & Co', had ordered other goods from the Repauno Chemical Company under their contract with it, and said goods were-in transit to Cole & Company. The delivery of the same, however, was stopped by the R.epauno Chemical Company upon receiving information that. Cole & Co. were insolvent, and they afterwards sold to Mason, Hoge & Co.”

The Repauno Chemical Company gave its notice October 10, 1903. , . . ]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jankowitz v. Morristown
161 A. 819 (New Jersey Court of Chancery, 1932)
Consolidated Engineering Co. v. Wedow & Myers Inc.
289 S.W. 507 (Tennessee Supreme Court, 1926)
Fidelity & Deposit Co. of Maryland v. Bailey-Spencer Hardware Co.
133 S.E. 799 (Supreme Court of Virginia, 1926)
Hoier v. Kaplan
145 N.E. 243 (Illinois Supreme Court, 1924)
Giant Portland Cement Co. v. . State
134 N.E. 322 (New York Court of Appeals, 1922)
Herman Tapp Construction Co. v. Paul
131 N.E. 536 (Indiana Court of Appeals, 1921)
Bird Bros. v. Southern Surety Co.
139 Tenn. 11 (Tennessee Supreme Court, 1917)
Pittsburg Coal Co. v. Southern Asphalt & Construction Co.
138 Tenn. 154 (Tennessee Supreme Court, 1917)
Johnson v. Starrett
149 N.W. 6 (Supreme Court of Minnesota, 1914)
Chicago Lumber Co. v. Douglas
131 P. 563 (Supreme Court of Kansas, 1913)
National Surety Co. v. Bratnober Lumber Co.
122 P. 337 (Washington Supreme Court, 1912)
Empire State Surety Co. v. City of Des Moines
152 Iowa 531 (Supreme Court of Iowa, 1911)
Barker & Stewart Lumber Co. v. Marathon Paper Mills Co.
130 N.W. 866 (Wisconsin Supreme Court, 1911)
Voightman & Co. v. Southern Railway Co.
123 Tenn. 452 (Tennessee Supreme Court, 1910)
George H. Sampson Co. v. Commonwealth
88 N.E. 911 (Massachusetts Supreme Judicial Court, 1909)
S. B. Luttrell & Co. v. Knoxville, La Follette & Jellico Railroad
119 Tenn. 492 (Tennessee Supreme Court, 1907)
Schaghticoke Powder Co. v. Greenwich & Johnsonville Railway Co.
76 N.E. 153 (New York Court of Appeals, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
113 Tenn. 382, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hercules-powder-co-v-knoxville-la-follette-jellico-railroad-tenn-1904.