Opinion

Taggart, J.

By the act for the better security of mechanics and others, erecting buildings in the city and county of New York, passed April 20, 1830, it is provided by § 1, that every mechanic, workman or other person, doing or performing any work towards the erection, construction or finishing of buildings in the city of New York, erected under a contract in writing between the owner and builder or other person whether such work shall be performed as *384 journeyman, laborer, cartman, subcontractor or otherwise, and whose demand for work and labor done and performed towards the erection of such buildings has not been paid and satisfied, may deliver to the owner of such building an account of the amount and value of the work and labor thus performed and remaining unpaid; and thereafter such* owner shall retain out of his subsequent payments to the contractor the amount of such work and labor, for the benefit of the person so performing the same.

Section 2 provides that whenever any account of labor performed on a building erected under a contract in writing, as provided by the first section, shall be placed in the hands of the owner of such building or his authorized agent, it shall be the duty of such owner or agent to furnish his contractor with a copy of such papers in order that if there should be any disagreement between such contractor and his creditor they may be amicably adjusted between themselves, or that by arbitration they may ascertain the true sum due; and if the contractor shall not within ten days after the receipt of such papers give the owner written notice that he intends to dispute the claim, or if in ten days after giving such notice he shall refuse or neglect to have the matter adjusted as aforesaid, he shall be considered as assenting to the demand and the owner shall pay the same when it becomes due.

Section 3, provides that if any such contractor shall dispute the claim of his journeyman or other person for work and labor performed as-aforesaid, and if the matter cannot be adjusted amicably between themselves, it shall be submitted on the agreement of the parties to the arbitrament of three disinterested persons, one to be chosen by each of the parties, and one by the two thus chosen, and the decision in writing of such three persons or any two of them shall be final and conclusive in the case submitted.

Section 4 provides that where the amount due shall be adjusted and ascertained as before provided, if the contractor shall not within ten days after it is so adjusted and *385 ascertained, pay the sum due to his creditor, with the costs incurred, the owner shall pay the same out of the fund as before provided, and which amount due may be recovered from the owner by the creditor of the contractor in an action for money had and received to the use of the said creditor, and to the extent in value of any balance due by the owner to his contractor under the contract with him at the time of the notice first given as before provided or subsequently, to such contractor under the same, if the amount shall be less than the sum due from said contractor to his creditor.

• Chapter 120 of the Laws of 1832, applies the provisions of the above cited statute to materials furnished, and to verbal or parol contracts or agreements, as well as written contracts.

Under these statutes the supreme court held in case of Wood v. Donaldson, (17 Wendell, 550,) that the provisions of the act of 1830, and the amendment of 1832, did not apply to debts or demands due to creditors of subcontractors. The court in that case says that the first section of the statute in terms includes every laborer upon the building, without any limitation in respect to the person who employed him, or the character of his' contract. If he has labored towards the erection of the building, or furnished materials, enough is shown to entitle him to a lien upon the fund in the hands of the owner, and payment can be enforced. But we must look at all the provisions of the statute and construe this section, if possible, according to the intent of the legislature as gathered from the whole, reconciling apparent discrepancies, and making all consistent and practicable as far as possible. The subsequent sections of the act clearly show that this new and extraordinary remedy was intended to be limited to the persons employed by him who contracted with the owner.” The cause was removed into the court of errors, and the judgment of the supreme court was there affirmed. (22 Wendell, *386 395.) It is true the chancellor in delivering his opinion in the court of- errors says, “ I also think the statutes extend to all such work as is usually done under building contracts in the city of New York; although it is not done upon the building itself, in the strict sense of the terms prescribed such work is embraced in the contract for the erection of the building.”

It is difficult to discover why the statute should have restricted construction as to the persons who claim protection under it, 'and be confined to the contractors of the original contractor, and yet have a more liberal construction as to the kind of labor and materials it embraces. The first section furnishes a remedy for those who have demands for the erection, construction and furnishing any building. The chancellor says these words may be construed so as to include all such work as is usually included in building contracts, and is within the contract in question. If this view is correct, the court must assume to decide what labor, exclusive of the erection, construction and furnishing the building it is usual to insert in a building contract. Does it include flagging the sidewalks and yards? Does it include leveling and grading the street? I am at a loss to discover what labor is included within building contracts in the city of New Yoxk. and am not prepared to say that the court should be called upon to decide that question. If such construction was correct, where was the necessity of the act of 1832, extending the provisions of' the act of 1830, so that it should include materials. Does it require a greater latitude of construction to say that work and labor includes materials and the labor of preparing them from the earth and wood, than that the erection, construction or furnishing a building includes the clearing, grading, and leveling the lot, flagging the sidewalk and yard, and leveling, grading and paving the street?

The language of the chancellor in that case, was a mere dictum. It did not arise in the case, and was thrown in .apparently without any conceivable object. It is not *387 therefore authority, and not being founded on substantial reasons we are not required to adopt it.

For a legislative construction of the act, reference may be had to the lien law, passed April 99,1844. (Laws of 1844, page

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Houston Petroleum Co. v. Automotive Products Credit Ass'n, Inc.
87 A.2d 319 (Supreme Court of New Jersey, 1952)
Hercules Powder Co. v. Knoxville, La Follette & Jellico Railroad
113 Tenn. 382 (Tennessee Supreme Court, 1904)
Putnam v. Putnam
77 A.D. 554 (Appellate Division of the Supreme Court of New York, 1902)
Pike v. Scott
60 N.H. 469 (Supreme Court of New Hampshire, 1881)
McDermott v. Palmer
1 Seld. Notes 124 (New York Court of Appeals, 1853)

Cite This Page — Counsel Stack

Bluebook (online)
8 N.Y. 383, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcdermott-v-palmer-ny-1853.