Wiley v. Hart

132 P. 1015, 74 Wash. 142, 1913 Wash. LEXIS 2011
CourtWashington Supreme Court
DecidedJune 13, 1913
DocketNo. 10729
StatusPublished
Cited by12 cases

This text of 132 P. 1015 (Wiley v. Hart) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wiley v. Hart, 132 P. 1015, 74 Wash. 142, 1913 Wash. LEXIS 2011 (Wash. 1913).

Opinion

Parker, J.

— The controversy involved in this appeal is between Wiley & Bevington, copartners, building contractors, the German-American Bank of Seattle, their assignee, and the National Surety Company, on the one side, and John B. Hart and wife, the owners of a building under contract for construction by Wiley & Bevington, on the other side. There are involved claims of the contractors against the owners for the balance of the contract price, and a large number of items for extra work and material claimed to have been put into the building by them during its construction at the instance of the architect; and, also, claims of the owners against the contractors for damages resulting from alleged defective construction of the building, and from failure of the contractors to finish the building within the time specified by the contract.

In March, 1911, the Dungeness Logging Company commenced an action in the superior court for King county against the owners, seeking foreclosure of a lien upon the building, and for material claimed to have been furnished for its construction. In July, 1911, the German-American Bank of Seattle, as assignee of the contractors for the balance claimed to be due them for the construction of the building, intervened in that action, seeking recovery of that balance from the owners and foreclosure of a lien claimed upon the building to secure the same, and also seeking to have brought into that action numerous other lien claimants and have their several claims adjusted therein. Thereafter, these several lien claimants filed their answers and cross-complaints in that [144]*144action, setting np their several claims of lien and praying foreclosure thereof. On August 1, 1911, the owners commenced an action in the superior court for King county against the contractors and the surety company, seeking recovery of damages claimed as a result of defective construction of the building and failure to complete the building within the time specified in the contract, and making the German-American Bank and the lien claimants defendants in that action, to the end that thei.r respective rights should be adjudicated therein. On August 3, 1911, the owners answered the complaint in intervention of the German-American Bank in the Dungeness Logging Company case, setting up in defense of the claims of the bank, as assignee of the contractors, in substance the same claims for damages as in the action against the contractors and the surety company two days previous, and also praying that the two actions be consolidated.

The action was manifestly commenced by the owners against the contractors and the surety company to recover an affirmative judgment for damages against them, in view of the fact that they could not be forced into the Dungeness Logging Company lien case for that purpose. This was at least true as to the surety company. The contractors and the surety company answered in the action commenced against them by the owners, and thereafter, on September 9, 1911, an order was entered consolidating the two actions. Thereafter, on November 7, 1911, the consolidated cases proceeded to trial before the court without a jury. The trial continued for several weeks, during which oral testimony was introduced occupying in this record over 4,000 typewritten pages. There were also exhibits introduced, and now in the record before us, numbering some 500 separate documents. Nearly all of this testimony and these documents relate to the controversy between the contractors, the bank and the surety company on the one side, and the owners on the other; there be[145]*145ing but little evidence required to establish the claims of the several lien claimants.

On January 5, 1912, the superior court rendered its decree, establishing the several lien claims of laborers and materialmen who had filed their answers and cross-complaints in the Dungeness Logging Company case, decreeing foreclosure thereof against the building, allowing certain portions of claims for extras made by the contractors against the owners, allowing certain portions of claims for damages made by the owners against the contractors, including damages resulting from defective construction, for failure to complete the building within the time agreed upon, and from liens established against the building; and adjudging that the owners, John B. Hart and wife, recover from the contractors, Wiley & Bevington, and the National Surety Company, their surety, the sum of $8,073.05, which sum the court concluded was the balance due to the owners on account of their damages sustained, after deducting the amount the contractors were entitled to credit for upon the original contract and for extra work and material put into the building by them. Thereupon the contractors, Wiley & Bevington, the German-American Bank, their assignee, the National Surety Company, their surety, and the owners, John B. Hart and wife, all appealed from this disposition of the cause.

We will’now notice some of the principal facts touching more directly the differences between these appellants, here involved. On October 17, 1910, John B. Hart entered into a contract with Wiley & Bevington, by which they agreed to construct an apartment building in Seattle upon a lot, the community property of Hart and wife, for the agreed price of $33,550, they to furnish all labor and material and construct the building “under the direction and to the satisfaction of H. Ryan, architect, acting for the purposes of this contract as agent for the owner,” and according to plans and specifications prepared by him therefor. It was agreed in this contract that the building should be completed on or before [146]*146February 20, 1911, and that “should the contractor fail or refuse to complete the work at the time as above stated, then he shall pay to the owner the sum of $30 per day as agreed, settled and liquidated damages for each and every day’s delay after the time fixed for completion.” The contractors were, however, to have allowance for delays arising from certain enumerated causes beyond their control, among which were neglect and fault of the architect. It was also agreed that:

“No alterations shall be made in the work shown or described by the drawings and specifications, except upon a written order of the architect.”

It was also agreed that payments should be made to the contractors from time to time as the building progressed, upon certificates of the architect, and further:

“That no certificate given in payment made under this contract, except the final certificate or final payment, shall be conclusive evidence of the performance of this contract, either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper material.”

It was also agreed that the contractor should furnish a surety bond to save the owners harmless from liens and from all losses or damages of whatsoever character arising in the execution of the contract. The bond having been executed accordingly with the National Surety Company, as surety thereon, the construction of the building was proceeded with by the contractors. The building was not completed on February 20, 1911, as agreed upon, nor was it completed to the satisfaction of the architect on May 24, 1911.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Eggers v. Luster
200 P.2d 520 (Washington Supreme Court, 1948)
Campbell Building Co. v. State Road Commission
70 P.2d 857 (Utah Supreme Court, 1937)
Bjerkeseth v. Lysnes
22 P.2d 660 (Washington Supreme Court, 1933)
Johnson v. Washington Phi Keia, Inc.
218 P. 263 (Washington Supreme Court, 1923)
Stimson Mill Co. v. Feigenson Engineering Co.
170 P. 573 (Washington Supreme Court, 1918)
Lindblom v. Mayar
142 P. 695 (Washington Supreme Court, 1914)
Ambaum v. State
141 P. 314 (Washington Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
132 P. 1015, 74 Wash. 142, 1913 Wash. LEXIS 2011, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wiley-v-hart-wash-1913.