Johnson v. Washington Phi Keia, Inc.

218 P. 263, 126 Wash. 434, 1923 Wash. LEXIS 1190
CourtWashington Supreme Court
DecidedSeptember 14, 1923
DocketNo. 17902
StatusPublished

This text of 218 P. 263 (Johnson v. Washington Phi Keia, Inc.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Washington Phi Keia, Inc., 218 P. 263, 126 Wash. 434, 1923 Wash. LEXIS 1190 (Wash. 1923).

Opinion

Mitchell, J.

— George Johnson and others, copartners doing business as the "Western Construction Company, built a fraternity chapter house and residence for the Washington Phi Keia, in Seattle. The contract was in writing, and provided that the building should be completed on or before March 1,1921. It was not completed until May 1,1921, at which time the construction company, claiming there was a balance due and unpaid, filed a lien upon the premises and commenced this action to foreclose it. In its answer the defendant claimed liquidated damages, under the terms of the contract, in the sum of $1,525, the same being $25 per day for 61. days delay in completing the building. The trial resulted in findings of fact and judgment in favor of the plaintiff in the sum of $1,525 and costs, and foreclosure of the lien. The defendant, upon taking proper exceptions, has appealed.

Counsel have interestingly presented a number of questions, but we are disposed to consider only one, spoken of by the respondent as the only point in the case, namely: Whether appellant is entitled to a deduction of $1,525 for 61 days’ delay, the fact of delay being admitted, the respondents ’ contention being that the deduction for delay was waived by the making of the payments during the period of delay without deducting at the time for the delay. That is, the making of payments during the period of delay without "deducting at the time for the delay, of itself, constituted a waiver or waivers of appellant’s right to deduct liquidated damages for the delay at the time of final accounting. The 6th paragraph of the contract provides :

[436]*436“It is mutually understood and agreed that time is the essence of this agreement and the contractor hereby distinctly agrees and guarantees to deliver the building complete and ready for occupancy by the owner on or before March 1, 1921, and in the event of his failure so to do agrees to forfeit to the owner as liquidated damages the sum of twenty-five dollars (25) per day for each and eyery day that thei building remains uncompleted beyond that date. ’ ’

The ninth paragraph of the contract provides:

“It is hereby mutually agreed between the parties hereto that the sum to be paid by the owner to the contractor for said work and materials shall be thirty-nine thousand nine hundred ninety-eight and fifty-seven hundredths dollars ($39,998.57), subject to additions and deductions as hereinbefore provided, and that such sum shall be paid in current funds by the owner to the contractor in installments as follows: On or about the first day of each month 85% of the value of the- materials, together with the labor employed thereon, as set in their permanent position in the building upon the certificate of the architect that such payments are due; the basis of said values of materials and labor to be in accordance with the stipulated amount herein set forth, and the remaining 15% within thirty days of the completion and final acceptance of the building by the architect on behalf of the owner. . . . The final payment to be made within thirty days after this contract is fulfilled. All payments shall be made upon written certificates of the architect to the effect that such payments have become due. ’ ’

The building was commenced and thereafter, during the months of October and November, 1920, and January and February, 1921, appellant paid several amounts in the total sum of $20,800, each payment being made upon the certificate of the architect as provided for by the terms of the contract. Thereafter, that is, after the time limit fixed in the contract for the completion of the house, the construction work continued, on which the owner made payments of $4,500, [437]*437$4,100 and $4,500 on certificates of the architect, dated March 7, April 8 and May 16, 1921, so that it clearly appears that, at the time of making each and all of these three last payments, there was reserved, by withholding fifteen per cent of the “value of the materials, together with the labor employed thereon, as set in their permanent position in the building,” more than enough at any and all times to cover the demurrage of $25 per day from and after March 1, 1921. The architect, upon making the estimate for the final payment, ascertained that, including a few hundred dollars for extras, about which the parties agreed, there was due the contractor, after deducting $25 a day for the 61 days delay, $4,575.47, in which amount he issued the final certificate on June 7, 1921. The money was promptly tendered by the owner and later accepted by the contractors, who refused to indorse the architect’s certificate, hence the filing of the lien and the bringing of the suit.

First we notice the cases relied on by the respondents ; they are Brodek v. Farnum, 11 Wash. 565, 40 Pac. 189; Erickson v. Green, 47 Wash. 613, 92 Pac. 449; Wiley v. Hart, 74 Wash. 142, 132 Pac. 1015; and Wright v. Tacoma, 87 Wash. 334, 151 Pac. 837.

The syllabus in the Brodek case that “where a payment is made on a building contract subsequent to the expiration of the time agreed upon for completion, the owner is not entitled to damages for loss of rents prior to the date of the payment by him,” supports the respondents here, but the opinion in that case, as we shall hereinafter see, is not quite so broad and is authority for the appellant under the facts in the present case.

The Erickson case, supra, involved a contract for the removal of earth. Payments were to be made in cash, one-third of the total when the work was half com[438]*438pleted, one-third when the work was eompleted, and the remainder upon proof that all claims of third parties, by reason of the work, were fully satisfied. The contract provided for a penalty of $10 per day for delay in completing the work within the time limited in the contract.

“The work under the terms of this contract should have been completed on September 25, 1904. It was not completed in fact until the 1st of March, 1905. On the 16th day of December, nearly three months after the failure to complete under the contract, the defendant paid to the plaintiff Erickson $565, being one-third of the contract price. Nothing further was paid upon the contract, and this action was brought to recover the remainder of the contract price. The defendant set up the contract in defense, demanding $10 a day for the whole time which had expired between the time when the contract should have been completed and the time when it was actually completed.”

The principal controversy in the case was whether or not the demurrage clause in the contract should be construed so as to provide for a penalty or liquidated damages. Upon the question of waiver, however, it was said:

“And we are not inclined to disturb the conclusion reached by the court that there was a waiver of the provisions of the contract in relation to liquidated damages for the time which had expired prior to the payment made to the contractor by the defendant.”

It is not clear if, by that language, it was meant that the payment of itself effected a waiver, but for the purposes of the present case we may assume that it was so intended, and yet it would not be authority for the judgment in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brodek v. Farnum
40 P. 189 (Washington Supreme Court, 1895)
Erickson v. Green
92 P. 449 (Washington Supreme Court, 1907)
Wiley v. Hart
132 P. 1015 (Washington Supreme Court, 1913)
Wright v. City of Tacoma
151 P. 837 (Washington Supreme Court, 1915)
Lawrence County v. Stewart
81 S.W. 1059 (Supreme Court of Arkansas, 1904)
Stephens v. Essex County Park Commission
143 F. 844 (Third Circuit, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
218 P. 263, 126 Wash. 434, 1923 Wash. LEXIS 1190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-washington-phi-keia-inc-wash-1923.