Stephens v. Essex County Park Commission

143 F. 844, 75 C.C.A. 60, 1906 U.S. App. LEXIS 3789
CourtCourt of Appeals for the Third Circuit
DecidedFebruary 27, 1906
DocketNo. 59
StatusPublished
Cited by9 cases

This text of 143 F. 844 (Stephens v. Essex County Park Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stephens v. Essex County Park Commission, 143 F. 844, 75 C.C.A. 60, 1906 U.S. App. LEXIS 3789 (3d Cir. 1906).

Opinion

DALLAS, Circuit Judge.

The plaintiff in error brought an action at law against the defendant in error, to recover a sum of money which the plaintiff averred was owing to him by the defendant, under two contracts in writing between them, dated,'respectively, March 2, 1899, and July 10, 1899. By the first of these contracts, the plaintiff agreed to construct two subways; and, by the second, to construct three shelters and one public lavatory building, in Branch Brook Park, Newark, N. J. For work and materials which he alleged he had furnished in pursuance and performance of these agreements, the plaintiff claimed that there was due him on subways account a balance of $4,345, with interest; and, on shelters and lavatory building account, a balance of $758.66, with interest—together amounting to the principal sum of $5,103.66. In and by the contract of March 2, 1899, the plaintiff agreed that he would fully complete the work to which it related on or before the expiration of three calendar months from the [845]*845■date thereof, not including, however, such time as the prosecution of the whole work might be suspended by direction of the defendant; and, following the statement of this agreement, the contract contained a clause in these words:

“Liquidated Damages. And the said contractor hereby further agrees that the said party of the first part shall be and is hereby authorized to deduct and retain out of the moneys which may be due or become due to the said ■contractor under this agreement, as liquidated damages and not as a penalty, for the noncompletion of the work aforesaid within the time heretofore stipulated for its completion, the sum of twenty-five dollars ($25) for each and every day after the expiration of said stipulated time—Sundays and holidays and such days as the prosecution of the whole work may be suspended by the direction of said architect excepted.”

It was admitted that the work was not completed until 159 days, exclusive of Sundays and holidays, after the expiration of three calendar months from the date of the contract, and the learned trial judge, being of opinion that the sum of $25 per day, which the defendant was authorized to retain for noncompletion of the work at the time stipulated, should be regarded as liquidated damages, and not as a penalty, instructed the jury that, as the plaintiff’s claim was for $4,-345, and as $25 per day for 159 days would amount to $3,975, the plaintiff was entitled to recover under the first contract only the difference between $4,345 and $3,975, to wit, $370, with interest.

This decision of th.e court below was required by that of the Supreme Court in Sun Printing & Publishing Ass’n v. Moore, 183 U. S. 642, 22 Sup. Ct. 240, 46 L. Ed. 366, in which it was argued by counsel that, even where a stipulated sum is stated to be liquidated damages, yet, if the amount is disproportioned to the loss, it should be regarded as a penalty; but the court said:

“The asserted doctrine is wrong in principle, was unknown to the common law, does not prevail in the courts of England at the present time, and it is ■not sanctioned by the decisions of this court.”

This statement will be found at page 60 of the report, and the consideration of the subject which thereafter follows leaves no room for doubt that the intention was to decide “that, whether a particular stipulation to pay a sum of money is to be treated as a penalty, or as an ■agreed ascertainment of damages, is to be determined by the contract, fairly construed; it being the duty of the court always, where the damages are uncertain and have been liquidated by an agreement, to enforce the contract.” We are therefore of opinion that, inasmuch as the legal effect of the contract now in question was perfectly plain upon its face, the court was right in excluding the testimony which was “offered for the purpose of showing that there was no real damage, but, if any, only nominal damage,” and in finally enforcing the plaintiff’s stipulation in accordance with its terms. Brooks v. City of Wichita, 114 Fed. 297, 52 C. C. A. 209; Wood v. Niagara Falls Paper Co., 121 Fed. 818, 58 C. C. A. 256.

The contract of July 10, 1899, included an agreement by the plaintiff to complete the items of work to which it related, at or before the expiration of the time which, as to each of them, was therein stated; and the court properly instructed the jury that it was for it to deter[846]*846mine to what extent the completion of any of the work had been delayed beyond the time limited by that agreement, and to apply to its finding upon that subject the stipulation respecting liquidated damages which the contract contained. That stipulation was not in all respects identical with the similar one in the contract of March 2, 1899; but, as the case is presented to this court, no question is involved which calls for the consideration of any difference between them. The only point to be decided with respect to the later contract is precisely the same as that which has been already decided with respect to the earlier one, and therefore, no further discussion of it is necessary.

All the specifications of error have now been disposed of, except those thaf go to the refusal of the learned judge to charge in accqrdance with three requests of the plaintiff for instructions, as follows :

“(1) That the jury may consider whether or not the work under the contract for subways Nos. 1 and 2 was suspended with the consent and approval of the architects pending the arrival of the granite from the Shea Pink Granite Company. That, if the jury find that the work was suspended with the consent and approval of the architect during the delay occasioned by the failure of the Shea Pink Granite Company to deliver the granite for the subways, the verdict should be for the plaintiff for the full amount of the balance claimed under that contract.

“(2) That it is for the jury to consider and decide whether the various delays that existed under both contracts were or were not with the consent and approval of the architects, and, if so, they may find that they were due to a direction by the architect and the park commission that the work should be suspended during such periods of delay.

“(3) That they (the jury) might consider the payment of §1,775 on the orders dated May 23, 1901, by the park commission, as evidence of a waiver by the commission for any delay on the part of the plaintiff, if it existed.”

1. The first of these requests assumes' that the architect’s consent to-a suspension of work, under the first contract, would alone suffice to justify such suspension, and it must be conceded that this assumption is not wholly groundless, for that contract did, in its clause respecting liquidated damages, except from the days of delay for which damages were to be computed “Sundays and holidays, and such days-as the prosecution of the whole work may be suspended by the direction of said architect.” This excepting provision, if alone considered,, would seem to imply that the architect might suspend the whole work, at his discretion. But at the outset of the contract, where the functions of the architects are particularly enumerated, no authority to suspend the work is given them, and the clause which immediately precedes-the one respecting liquidating damages is, in part, as follows:

“The prosecution of the work shall be suspended at such times and for such periods as the said commission may from time to time determine.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Le Roy Dyal Co., Inc
186 F.2d 460 (Third Circuit, 1950)
Consolidated Cut Stone Co. v. Seidenbach
1937 OK 701 (Supreme Court of Oklahoma, 1937)
Johnson v. Washington Phi Keia, Inc.
218 P. 263 (Washington Supreme Court, 1923)
Stewart v. Spalding
23 Haw. 502 (Hawaii Supreme Court, 1916)
Northwestern Terra Cotta Co. v. Caldwell
234 F. 491 (Eighth Circuit, 1916)
Union Pac. R. v. Mitchell-Crittenden Tie Co.
190 F. 544 (Eighth Circuit, 1911)
Turner v. City of Fremont
170 F. 259 (Eighth Circuit, 1909)
Turner v. City of Fremont
159 F. 221 (U.S. Circuit Court for the District of Nebraska, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
143 F. 844, 75 C.C.A. 60, 1906 U.S. App. LEXIS 3789, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stephens-v-essex-county-park-commission-ca3-1906.