Brodek v. Farnum

40 P. 189, 11 Wash. 565, 1895 Wash. LEXIS 344
CourtWashington Supreme Court
DecidedApril 8, 1895
DocketNo. 1593
StatusPublished
Cited by7 cases

This text of 40 P. 189 (Brodek v. Farnum) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brodek v. Farnum, 40 P. 189, 11 Wash. 565, 1895 Wash. LEXIS 344 (Wash. 1895).

Opinion

The opinion of the court was delivered by

Scott, J.

This was an action for damages for breach of a contract entered into between the plaintiffs and the^ defendants for the erection of a building. The claim for damages is based upon the following grounds, in substance: (1) That the building was not completed within the time contracted for, whereby the plaintiffs lost certain rents; (2) that by the terms of the contract said building was to be constructed so that the first floor should he upon a level with the sidewalk, according to the established grade, and that it was not so constructed, but was erected so that the first floor was a foot or more higher than it should have been; (3) that the building was not constructed according to the plans and specifications, in that certain posts were placed therein, and was constructed of inferior materials, and that the work was defective, whereby it was rendered of much less value than it otherwise would have been.

The defendant Farnum made no answer. The defendant Reitze answered, denying certain matters [567]*567alleged in the complaint, and averring that Farnum was the principal contractor and that himself and Stetson were sureties, and that plaintiffs had knowledge thereof; that during the progress of the construction of the building one of the walls fell, without the fault of the defendants and because of the negligence and fault of the plaintiffs in failing to provide a suitable and sufficient foundation for said wall; and that thereupon said plaintiffs entered into a new contract with the defendant Stetson and extended the time for the completion of the building, whereby the defendant Stetson was to construct the same, and that Stetson did complete the building in accordance with such contract.

Defendant Stetson answered, denying certain matters alleged in the complaint and setting up several affirmative defenses, wherein it was in substance alleged that it was the duty of plaintiffs to provide the foundation for said building, and that the defendants entered upon the construction of the building according to the contract, but that the foundation therefor provided by the plaintiffs was insufficient and insecure; that after the building was partly constructed a portion of it fell, which was wholly due to the fault of the plaintiffs; and that he thereafter succeeded to all the right, title and interest of his co-defendants, Farnum and Reitze, in and to said contract, with the knowledge and consent of the plaintiffs, and entered into a contract with the plaintiffs to make the necessary repairs and complete the building, the time therefor being extended; and that he thereafter proceeded to and did construct the building in accordance with the contract and certain agreed alterations; and alleging that the posts aforesaid were put in said building and the lower floor raised in accordance with the plaintiffs’ directions. He also set up a counterclaim for certain extras furnished, [568]*568and for the balance of the contract'price dne for the erection of the building.

The plaintiffs replied, denying the affirmative matters pleaded. Verdict and judgment were rendered for plaintiffs upon the trial, and defendant Stetson appealed therefrom.

Some of the questions presented are complicated, owing to the contradictory character of the proofs and its insufficiency in some particulars, and it is difficult to determine all of them definitely. But we may perhaps indicate our views sufficiently for the guidance of the lower court in a further disposition of the cause.

The first point raised by appellant is that the court should have granted his motion for a non-suit. It appears that after the expiration of the time fixed for the completion of the building in the original contract, and while appellant Stetson was engaged in the construction of the same, the plaintiffs made several payments to him thereon, in all amounting to the sum of $9,480, and it is contended, accepting the plaintiffs’ view of the case and conceding th’ere was no second contract with Stetson, that this was a waiver of the time fixed for the completion of the building in the original contract; and, furthermore, that these payments were made with full knowledge that the building was being constructed above the grade; and that, having made these payments, the plaintiffs could not maintain an action for damages. As to this question, however, there was some proof to show that defective materials had been used in the construction of the building, and we are not satisfied from the proofs that the plaintiffs knew that such materials were defective and were not such as were called for by the contract. Consequently the motion for a non-suit was properly overruled.

[569]*569In connection with this same matter it is contended that the court erred in overruling the motion of appellant to exclude from the consideration of the jury all evidence as to loss of rent accruing between July 1, 1890, and September 9, 1890, the first daté being the time fixed in the original contract for the completion of the building, and the last date being the time when the last payment was made by the plaintiffs to Stetson. We think this point is well taken, for if no contract had been entered into with Stetson for the completion of the building after the falling of a portion of it, and conceding that Stetson was continuing the work under the original contract, the making of these payments with full knowledge of the facts was a waiver of all claims for damages, except as against the balance remaining unpaid, for a failure to complete the building by the time specified, up certainly to the date of the last payment, and the plaintiffs could not maintain an action therefor. Henricus v. Englert, 17 N. Y. Supp. 235-237. Evidence in support of appellant’s counterclaim was excluded by the court. We are of the opinion also that the waiver of time may have gone further than this, which we shall hereafter consider.

It is further contended that the court erred in overruling appellant’s motion to withdraw from the consideration of the jury the evidence of damage in consequence of the building being above the grade. The grounds for said motion being that it appeared from the evidence of the plaintiffs that with full knowledge of the facts they had voluntarily paid more money to the contractors than they now claim to be damaged by reason of the building being above the grade; and it further appeared by the testimony of the plaintiffs that it was their duty to provide the foundation for the building, and they undertook to do so. The building [570]*570was being erected upon tide lands and the foundation was in part composed of piles driven into the ground. The plaintiffs procured this to be done and had the piles sawed off and capped and left in condition for the building to be erected upon; and if the foundation they had thus prepared was too high, it was their fault and not the fault of the defendants. The evidence of damage in this particular was therefore inadmissible.

It is next contended that the court erred in excluding from the jury all evidence offered by appellant Stetson under his counterclaim. The respondents urge that this evidence was-incompetent, and that the written contract entered into by the defendants must govern. But this does not seem to us as well founded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Frizzell v. Murray
Washington Supreme Court, 2013
Collier v. Merced Irrigation District
2 P.2d 790 (California Supreme Court, 1931)
North Pacific Mortgage Co. v. Krewson
224 P. 566 (Washington Supreme Court, 1924)
Johnson v. Washington Phi Keia, Inc.
218 P. 263 (Washington Supreme Court, 1923)
Beck v. Boucher
195 P. 996 (Washington Supreme Court, 1921)
Wiley v. Hart
132 P. 1015 (Washington Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
40 P. 189, 11 Wash. 565, 1895 Wash. LEXIS 344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brodek-v-farnum-wash-1895.