Van Buskirk v. Board of Education

75 A. 909, 78 N.J.L. 650, 1910 N.J. LEXIS 149
CourtSupreme Court of New Jersey
DecidedFebruary 28, 1910
StatusPublished
Cited by7 cases

This text of 75 A. 909 (Van Buskirk v. Board of Education) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Van Buskirk v. Board of Education, 75 A. 909, 78 N.J.L. 650, 1910 N.J. LEXIS 149 (N.J. 1910).

Opinion

The opinion of the court was delivered by

Reed, J.

This action was brought to recover the unpaid portion of the contract price of $8,309 to be paid by the board of edneation of the township of Passaic, in the county of Morris, for the erection by the plaintiff of a four-room school building, and to recover for extra work amounting to $574.40. After the allowance of certain payments plaintiff claimed a balance due of $2,650.40. At the close of the plaintiff’s case t lie trial court directed a verdict for the sum of $647, and this writ of error brings up the judgment entered upon this verdict.

The reduction by the trial judge from the amount claimed insulted from the court’s allowance to the defendant of liquidated damages for the failure of the plaintiff to complete its contract by the date stipulated in the contract, and it resulted further from the disallowance of the plaintiff’s claim for extra work upon the building.

A general exception to the direction of the court raises the correctness of the judicial view upon both of these points. We will first consider the question of the allowance of liquidated damages. The contract provides as follows:

“The contractor shall complete the several portions and the whole of the work comprehended in this agreement by and at the time or times hereinafter stated, to wit, foundation walls to he ready to receive joists by the 15th of June, 1908. Brick walls to be ready for rafters by the 10th of July, 1908. Plastering to be completed by the 15th of August, 1908. The entire building to be completed and ready for occupancy by the loth day of September, 1908, providing, however, that the aforesaid owner removes the present building from the proposed site before the 15th of May, 1908.”

The contract also contains a provision as follows:

“Should the contractor be delayed in the prosecution or [652]*652completion, of the work by the act, neglect or default of the owner, of the architect, or of any other contractors employed by the OAvner upon the work, * * * then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all of the causes aforesaid, Avhicli extended period shall be determined and fixed by the architect, but no such allowance shall be made unless a claim therefor is presented in writing to the architect within forty-eight hours of the occurrence of such delay.”

There AAras no claim for extension of time under this clause presented to the architect, and no allowance made by the architect. The building ^was not completed until November 14th, 1908.

The contract also provides as follows:

“The Avork herein called for is to be hastened to completion as rapidly as possible consistent with first-class workmanship, and must be completed on or before the date agreed upon in the contract, and should the contractor fail to complete the entire work by said date, allowing such extensions of time, if any, in the ease of such extra work as may have been agreed upon and certified to by the architect, then the contractor shall pay to the OAvner the sum of $25 per day as liquidated and ascertained damages for each and every day’s delay that the work shall remain unfinished after the date agreed upon for the completion of the same. It is understood and agreed that by the signing of these specifications and the accompanying contract the contractor waives any legal defence he might have because of the omission of a bonus in event of the building being completed before the date agreed upon, the term liquidated and ascertained damages governing absolutely.”

There Avas no allowance of an extension of time certified by the architect on account of extra work.

Under the clause the architect deducted from the contract price $25 each day from the 17th day of September, 1908, to the 14th day of November, 1908.

The plaintiff in error first insists that the language of the [653]*653contract is such as to lead to the conclusion that this clause was not intended to provide for liquidated damages, but was ini ended for a penalty only, and so the defendant was entitled only to such damages as it could prove had resulted from the delay in the completion.

This contention, however, is unsound. The delay for which these damages were to be paid was for the completion of the entire work. The facts bring the case under the control of the rule laid down in Monmouth Park Association v. Wallis Iron Works, 20 Vroom 132.

It is next insisted that the right of the defendant to be allowed liquidated damages failed because the old building was not removed from the proposed site before the loth day of May, 1908.

It appears that the old building was not entirely removed from the proposed site on that date. The building was removed, but some stringers extended over the proposed site from May 15th to May 17th, when the building was entirely removed and placed in position, about twelve feet from the proposed site.

The view propounded by the plaintiff in error is that the removal of the old building before the date mentioned was a condition precedent to the right to recover any liquidated damages for any delay in the completion of the work. The plaintiff in error would read the clause providing for liquidated damages as if it read thus: “The contractor shall pay twenty-live dollars a day for each day’s delay after September 15th, 1908, to complete the same, only in case the old building is removed before May 15th, 1908.” This, however, is not the language of the contract. By the contract the damages are to be paid for every day’s delay that the work shall remain unfinished after the date agreed upon for the completion of same.

Now, the building was to be completed either on September 15th, 1908, or on a later dale in ease the contractor, in the completion of the work, by any act or default of the owner, or of any other contractor employed by the owner upon the work, should be delayed. In such case the contract pro[654]*654vided tliat the time feed for the completion of the work shall be extended for the period equivalent to the time lost by reason of any or all the causes aforesaid, which extended period shall be determined and feed by the architect.

It thus appears that if the contractor was delayed in the completion of the work by the neglect of the owner in failing to remove the old building before May 15th, the contract itself provided for an extension of the time for the completion of the work. In case of such extension, if there was a failure to complete the work at the end of the extended period, the work remained unfinished after the date agreed upon for the completion of same, fo.r the provision for the extended period was as much agreed upon as was the feed period, namely, September 15th, 1908, the liquidated damages were to be paid for each day’s delay that the work remained unfinished — not after September 15th — but after the date agreed upon for the completion of the same.

By the failure of the plaintiff to give written notice to the architect of any claim for an extension of the time for completing the work, the time for the completion remained September 15th, although two days were allowed, namely, from September 15th to September 17th, and the direction for a deduction of liquidated damages from the 17th to the date of completion was correct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buckley & Co., Inc. v. State
356 A.2d 56 (New Jersey Superior Court App Division, 1975)
Terminal Const. Corp. v. Bergen, Etc., Authority
112 A.2d 762 (New Jersey Superior Court App Division, 1954)
Leigland v. Rundle Land & Abstract Co.
208 P. 1075 (Montana Supreme Court, 1922)
Wm. P. Jungclaus Co. v. Ratti
118 N.E. 966 (Indiana Court of Appeals, 1918)
Humphreys v. Walsh
248 F. 414 (Third Circuit, 1918)
Wiley v. Hart
132 P. 1015 (Washington Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
75 A. 909, 78 N.J.L. 650, 1910 N.J. LEXIS 149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/van-buskirk-v-board-of-education-nj-1910.