Lindblom v. Mayar

142 P. 695, 81 Wash. 350, 1914 Wash. LEXIS 1415
CourtWashington Supreme Court
DecidedAugust 17, 1914
DocketNo. 11990
StatusPublished
Cited by12 cases

This text of 142 P. 695 (Lindblom v. Mayar) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lindblom v. Mayar, 142 P. 695, 81 Wash. 350, 1914 Wash. LEXIS 1415 (Wash. 1914).

Opinion

Parker, J.

The plaintiff commenced this action in the superior court for Chelan county to foreclose a lien claimed by him upon a lot and building thereon belonging to the defendants, as security for a balance due him upon a contract for the construction of the building, entered into by him with the defendants. At the conclusion of the evidence introduced in plaintiff’s behalf, the defendants not having introduced any evidence, the trial court, upon motion by counsel for defendants, dismissed the case, reciting in the final judgment as the reason therefor the following:

. . for the reason that the plaintiff did not prior to the commencement of this suit, obtain a final certificate from the architect who had supervision of the work performed by the plaintiff for the defendant according, to the contract entered into by and between the plaintiff and the defendant Deed H. Mayar; and for the reason that it was not plead or proven by the plaintiff that such certificate had' been demanded and unreasonably, wrongfully or capriciously withheld by the architect . . .”

From this disposition of the cause, the plaintiff has appealed, his principal contention being that the defendants [352]*352have waived the benefits of the provisions of the contract relating to certificate by the architect as to the proper completion of the building, so as to entitle him to a decision of the superior court upon the merits of his claim without such certificate by the architect and without any showing by him of wrongful or capricious withholding of such certificate by the architect.

Appellant alleges in his complaint, in very general terms, that he entered into the contract for the construction of the building, for $5,324, without setting out a copy of the contract or any of its terms relative to the supervision of the construction of the building by the architect or his certificates to be issued during the progress of the construction and upon completion. This is followed by allegations that the building has been completed; that certain extra work was performed by him in the construction of the building, amounting in value to $218.25; that $4,638.15 has been paid to him by respondents upon the contract and extra work, leaving a balance of $904.10 due thereon, for which he prays judgment of foreclosure of his claimed lien. Appellant’s complaint is wholly silent as to any facts tending to show the necessity for the architect’s certificate as a condition precedent to his recovery, and also, of course, is silent as to any excuse for his failure to procure such certificate.

In their answer, respondents deny the allegations of appellant’s complaint except as to the entering into the contract, the payment to appellant of the $4,638.15; and allege, as an affirmative defense, or, it might better be said, defenses, that the contract is in writing, setting out a copy thereof, which, so far as we need notice its terms here, is as follows:

“The contractor shall and will provide all the materials and perform all the work for the erection and completion (except the heating, electric wiring and plumbing) of the Leavenworth Echo Building, to be erected on east 25 feet of lots 22, 23, and 24, Bl’k 4, town of Leavenworth, Wash., as [353]*353shown on original plat and as shown on the drawings and described in the specifications prepared by C. Ferris White of Spokane, Wash., Architects, which drawings and specifications are identified by the signatures of the parties hereto, and become hereby a part of this contract.
“It is understood and agreed by and between the parties hereto that the work included in this contract is to be done under the direction of the said architects, and that their decision as to the true construction and meaning of the drawings and specifications shall be final.
“It is hereby mutually agreed between the parties hereto that the sum to be paid by the owner to the contractor for said work and materials, shall be five thousand, three hundred and twenty-four dollars ($5,324.00) subject to additions and deductions as hereinbefore provided, and that such sum shall be paid by the owner to the contractor, in current funds, and only upon certificates of the architects, as follows:
“85% of the work done and materials delivered will be paid for from time to time as the work progresses.
“The final payment shall be made within twenty days after the completion of the work included in this contract, and all payments shall be due when certificates for the same are issued.”

Respondents also allege, “that the said building has never been completed and has never been accepted according to the contract.” Respondents also allege and claim damages as against appellant for $853, resulting to them from defective construction of the building. While they ask affirmative judgment in this sum, it is apparent from their answer as a whole that they are entitled to it only as a set-off against the claim of appellant, and they so treated it by their motion to dismiss.

Replying to the affirmative allegations of respondents’ answer, appellant admits the making of the contract as therein alleged, denies, by special reference thereto, respondents’ allegation that the building “has never been accepted according to such contract,” and denies all of respondents’ allegations of damage resulting from defective construction of the building.

[354]*354It has become the settled law of this state, as it generally prevails elsewhere, that certificates of supervising architects and engineers required by the terms of construction contracts as evidence of progress and completion of the- work as conditions precedent, entitling the contractor to payment for the work, will be given full force and effect; and that the contractor will be denied relief by the courts until he procures the required certificate or shows excuse for failure so to do, such as arbitrary or fraudulent withholding thereof by the supervising architect or engineer, or by waiver of such certificate by the owner. In other words, in the absence of such a showing, the courts will not hear the contractor upon the merits of his claim for compensation. Craig v. Geddis, 4 Wash. 390, 30 Pac. 396; Schmidt v. North Yakima, 12 Wash. 121, 40 Pac. 790; Wiley v. Hart, 74 Wash. 142, 132 Pac. 1015; Dickerman v. Reeder, 59 Wash. 405, 109 Pac. 1060; 6 Cyc. 88.

In harmony with this view of the law, it is held that a complaint seeking recovery upon such a contract, the terms of the contract requiring an architect’s or engineer’s certificate being disclosed by a complaint, fails to state a cause of action, in the absence of a pleading of facts showing an excuse for failure to produce the architect’s certificate. Dealing with a complaint of this character, the court of appeals of New York, in Weeks v. O’Brien, 141 N. Y. 199, 36 N. E. 185, said:

“By the true construction of the building contract, the procuring by the plaintiff of the certificate of the architect that the building had been completed, was a condition precedent to his right to recover under the contract the last installment of $6,185, for which this action is brought.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haugen v. Raupach
260 P.2d 340 (Washington Supreme Court, 1953)
In Re Estate of Crane
99 N.E.2d 204 (Appellate Court of Illinois, 1951)
Bank of America v. Jorjorian
24 N.E.2d 896 (Appellate Court of Illinois, 1940)
Goddard v. Security Title Insurance & Guarantee Co.
92 P.2d 804 (California Supreme Court, 1939)
Everts v. Blaschko
61 P.2d 776 (California Court of Appeal, 1936)
Linton v. State
52 P.2d 1239 (Washington Supreme Court, 1936)
Sloane v. State
297 P. 194 (Washington Supreme Court, 1931)
Matteson v. Klump
279 P. 669 (California Court of Appeal, 1929)
Peterson v. Parker
275 P. 729 (Washington Supreme Court, 1929)
Olmstead v. Downie
248 P. 385 (Washington Supreme Court, 1926)
Ragsdale v. Dyer
150 Tenn. 496 (Tennessee Supreme Court, 1924)
Henry v. Chicago, Milwaukee & Puget Sound Railway Co.
147 P. 425 (Washington Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
142 P. 695, 81 Wash. 350, 1914 Wash. LEXIS 1415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lindblom-v-mayar-wash-1914.