US for Use of Cortolano & Barone v. Morano Const.

724 F. Supp. 88
CourtDistrict Court, S.D. New York
DecidedSeptember 21, 1989
Docket87 Civ. 4920 (RWS)
StatusPublished
Cited by6 cases

This text of 724 F. Supp. 88 (US for Use of Cortolano & Barone v. Morano Const.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
US for Use of Cortolano & Barone v. Morano Const., 724 F. Supp. 88 (S.D.N.Y. 1989).

Opinion

724 F.Supp. 88 (1989)

UNITED STATES of America for the Use and Benefit of CORTOLANO & BARONE, INC., Plaintiff,
v.
MORANO CONSTRUCTION CORPORATION, f/k/a Morano Excavating, Inc., Fireman's Fund Insurance Company, and the American Insurance Company, Defendants.
MORANO CONSTRUCTION CORPORATION, f/k/a Morano Excavating, Inc., Defendant and Counterclaimant,
v.
INTERNATIONAL FIDELITY INSURANCE COMPANY, Counterclaim Defendant.

No. 87 Civ. 4920 (RWS).

United States District Court, S.D. New York.

September 21, 1989.

Melvin J. Kalish, New York City, for plaintiff and counterclaim defendant.

Berman, Paley, Goldstein & Berman, New York City, for defendants; Howard Burger, of counsel.

SWEET, District Judge.

Plaintiff Cortolano & Barone, Inc. ("C & B"), a subcontractor on a United States of America project at Stewart International Airport, brought this action under the Miller Act, 40 U.S.C. § 270a et seq., against a prime contractor on the project, Morano Construction Corporation ("Morano") and its sureties who then counterclaimed against C & B and its surety. After a bench trial, judgment will be entered in accordance with the findings and conclusions set forth below granting certain of the relief C & B sought.

Prior Proceedings

C & B commenced this action by filing a complaint on July 10, 1987, which it subsequently amended. Morano filed its answer and counterclaim, an amended answer and counterclaim, and a second amended answer and counterclaims. C & B filed a reply and an amended answer of counterclaim.

Discovery was completed virtually without dispute, and the action was tried before the court on May 2 through May 8, 1989, and resumed on May 25 and 30. Testimony of five witnesses, all in the construction business, was received, as well as several hundred exhibits. Final submissions were filed on June 29, 1989.

*89 The Issues

By the skilled and experienced hands of able counsel for both sides, the court was led through the formation, performance, and termination of a substantial subcontract entered into between C & B and Morano in connection with a government construction project for Stewart International Airport. Notwithstanding the assistance given the court, to account for the issues presented is almost as difficult as to track the progress of this construction job.

The principal issues include the propriety of Morano's termination of the subcontract it had with C & B, whether a subsequent subcontract was entered into or partially performed, and what are the financial consequences of the parties' acts during their relationship from the spring of 1986 to the spring of 1987 against the background of these issues.

As set forth in the findings and conclusions found below, Morano was not justified in terminating the subcontract, there was no subsequent subcontract, and the balance of moneys owed favors C & B.

Findings of Fact

The Parties

C & B is a New York corporation with its principal place of business at 708 Saw Mill River Road, Ardsley, New York. It has been in business in its present form since 1983 and has performed plumbing, heating, ventilating, and mechanical contracts principally in the Westchester area. Its vice president and witness was Armando Barone, Jr. ("Barone") who is the third generation of his family to work at his trade. Barone has fourteen years experience in the type of business C & B conducts.

Morano, formerly known as Morano Excavating, Inc., is a New York corporation with its principal place of business at 18 North Astor Street, Irvington, New York. Prior to the events recounted here, Morano was involved principally in excavating and road building and had not undertaken any building construction. Its president was Michael Morano, its vice president was John Harrington ("Harrington"), and its project manager with respect to the subcontract at issue here after January 1, 1987 was Anthony J. Spinella ("Spinella").

Defendant Fireman's Fund Insurance Company ("Fireman's") is a California corporation with an office at 420 Crossways Park Drive, Woodbury, New York and is Morano's surety. Defendant The American Insurance Company ("American") is a New Jersey corporation with an office at 420 Crossways Park Drive, Woodbury, New York and is Morano's surety. Counterclaim defendant International Fidelity Insurance Company ("International") is a New Jersey corporation with its principal place of business in Newark, New Jersey and is C & B's surety. Fireman's, American, and International as sureties have each tendered their defense to their respective principals. Each surety reserves the right to assert herein any and all defenses it may have against the claims asserted against said surety.

The Contract, Its Extensions, and the Subcontract and Phase III

On October 22, 1985, Morano was awarded an over $4 million contract by the United States of America, acting through the New York Air National Guard ("NYANG") and United States Marine Corps ("USMC") for site improvement at Stewart International Airport, described as Contract # DAHA 30-85-C-0028 Site preparation Phase III (the "Contract").

The Contract between Morano and the government called for Morano to construct a water storage basin, a water booster pump house (to pump uphill, under pressure, water supplied by the local utility), two water storage tanks, a utility center containing, among other things, pumps to furnish water for domestic and emergency use throughout the military airfield, and associated process piping, fuel tank, electricity, etc. (the "Project"). Subcontracts were let for structural, electrical, and mechanical work (plumbing, pumps, process piping, fire protection, heating, ventilating, and air conditioning). The first mechanical subcontractor, Star Mechanical Corp. ("Star Mechanical"), was terminated on May 2, 1986 for non-performance.

*90 On May 27, 1986, Morano and C & B entered into a written subcontract for plumbing work, process piping work, sprinkler system work, and heating, ventilating, and air-conditioning work ("HVAC") at the Project (the "Subcontract"). The base Subcontract price was $607,000.00 which Addendum # 4 increased by $11,681.81.

The Subcontract provided, among other things, as follows:

Sub-Contractor must follow submittal schedule.
(Subcontract, at p. 4)
Extra work must be approved by the owner both in context and value as valid extra work prior to any compensation from Morano Construction Corporation.
(Subcontract, at p. 5)
THIRD: PROVISIONS OF GENERAL CONTRACT. The Subcontractor has read and is familiar with the General Contract....
(Subcontract, at p. 6)
FOURTH; PROGRESS. Time is of the essence of the Subcontractor's performance under this agreement and the Subcontractor ... shall progress the same as not to delay or interfere with the Contractor in any of its operations and shall proceed in such order and sequence as the Contractor may direct and so as to enable the Contractor to complete its work within the limits specified in the General Contract or as the same may be extended ..., it being the Subcontractor's obligation to coordinate its work with the work of the Contractor.
(Subcontract, at p. 6)
SIXTH; CANCELLATION OF CONTRACT.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melanie Culp v. John Trimberger
Michigan Court of Appeals, 2024
United States v. Quicken Loans Inc.
District of Columbia, 2016
US EX REL. VIRG. BEACH MECH. v. SAMCO Const. Co.
39 F. Supp. 2d 661 (E.D. Virginia, 1999)
Carter v. Krueger
916 S.W.2d 932 (Court of Appeals of Tennessee, 1995)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
724 F. Supp. 88, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-for-use-of-cortolano-barone-v-morano-const-nysd-1989.