Savannah Lighting Co. v. Fidelity & Deposit Co.

95 S.E. 113, 21 Ga. App. 758, 1918 Ga. App. LEXIS 516
CourtCourt of Appeals of Georgia
DecidedFebruary 19, 1918
Docket8364
StatusPublished
Cited by4 cases

This text of 95 S.E. 113 (Savannah Lighting Co. v. Fidelity & Deposit Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Savannah Lighting Co. v. Fidelity & Deposit Co., 95 S.E. 113, 21 Ga. App. 758, 1918 Ga. App. LEXIS 516 (Ga. Ct. App. 1918).

Opinions

Bloodworth, J.'

The Savannah Lighting Company entered into a written contract with Lightman, McDonald & Company, under which the latter were to build “additions to power station and substation” of the former. A bond for the faithful performance of the contract was'given to the owner by the contractors, with the Fidelity and Deposit Company of Maryland as surety. The owner contended that the contractors violated certain conditions of the contract, and it brought suit against the surety company, on the bond. A demurrer to the petition was sustained, and the plaintiff excepted.

1. The contract between the owner and the contractor is, by the express terms of the bond, made a part thereof, and both instruments must be construed together. Thus construing them; the surety company is liable to suit under each of at least two conditions : the one upon cancellation of the contract under the stipulations thereof hereinafter set out, — the cancellation to be upon the initiative of the owner; the other, the abandonment of the contract, — which! would be the voluntary act of the contractors. The demurrer which was sustained was as follows: “1st. The petition as amended is not sufficient in law. 2d. The petition as amended fails to show that the notices of October 1 and October 8 were given, upon the judgment of the engineers, as required by the contract. 3d. The petition as amended fails to show that any [760]*760notice was given to the surety of plaintiff’s contention that the contractor had abandoned the contract, as required by the condition in the bond that ‘The said surety shall be notified in writing of any act on the part of the said principals, or their agents or employees, which may involve a loss for which the said surety is responsible hereunder, immediately after the occurrence of such act shall have come to the knowledge of said owner, or to any representative duly authorized to oversee the performance of said contract; and a registered letter, mailed to the president of said surety at its principal office in Baltimore City, Maryland, shall be the notice required within the meaning of this bond/ ” It will be- seen that the defendants insist, that the cancellation was of no effect, because the notices given (the substance of each of which is hereinafter copied) were not based upon the certificate of the engineers, as provided by the contract, and that no notice whatever was given that the contract had been abandoned; and that one or the other of these two conditions' must be complied with before there can be a recovery; the character of the notice required as a condition of recovery being dependent upon whether the suit is brought because the contract is cancelled, or because it is abandoned. In this case another issue is presented, — whether -one can give notice of cancellation, construct his petition on this theory, and then amend and recover on the ground that the contract had been abandoned. Just here we call attention to the entirely different results that follow from a cancellation of the contract and from the abandonment thereof.

In the event of cancellation the provision applicable is as follows: ‘‘The contractor further agrees that in the event of the annulment of this contract, as above provided, the owner shall have the right to enter upon the premises and take possession, for the purpose of completing the work under this contract, of all materials, tools, and appliances thereon belonging to the contractor, and to employ any other person or persons to finish the work herein provided for, and to provide all the materials necessary therefor. TJpon such notice of cancellation being given, all payments to the contractor under this contract shall cease, and all moneys due or to become due the contractor shall be retained by the owner until final completion and acceptance of the work. The cost of all labor, machinery, and materials provided by the [761]*761owner for any of the purposes of this section; including the extra cost of inspection and superintendence, concerning which the certificate- of the engineers shall be final, shall be deducted from any moneys due or which may become due the contractor under this contract, and the owner shall have the right to recover any excess of-such costs, over the unpaid balance remaining on account of said contract . . .” In ease of abandonment the bond provides that “If the said principals shall -voluntarily abandon said contract, . . then the surety shall have the right, in its option, to assume the said contract and to sublet or complete the same, and if said contract shall be assumed by the surety, then as such contract is duly performed, any reserve, deferred payments, and all other moneys provided by said contract to be paid to the principals, shall be paid to the surety, at the times and under the same conditions as by the terms thereof such moneys would have been paid to' the principals had the contract been duly performed by them. And if said owner shall complete or relet the said contract, then any forfeitures provided in said contract against the principals shall not he operative as against the surety, but all reserves, deferred payments, and all other moneys provided in said contract, which would have been paid to the principals had they completed the contract in accordance with its terms, shall be credited upon claim the said owner may make upon said surety.” ■

Having before us the above, let us consider, first the conditions upon which the contract may be cancelled.as stated in the contract, in connection with the notices given, the petition, and ground 2 of the demurrer. This portion of the contract is as follows: “The contractor further agrees: that should he fail to at any time provide a sufficiency of competent workmen, machinery, or materials; or that should the progress of this work at any time-be such as would result in his failure to complete the work upon the. daté herein agreed upon, of which conditions, the engineers are to be the judge, the owner shall have the right to require, by written notice, the contractor to, • at his own expense, employ such additional labor, machinery, or material as the engineers may direct to be put upon the work. The contractor .further agrees that should he fail to providé a sufficiency of labor; machinery, or proper materials within five days of such notice, or should he fail to remove rejected materials or objectionable employees, as here[762]*762inafter provided, or should he fail to comply with auy other requirements of this agreement, the owner shall have the right after five days written notice, to cancel this contract.” The further provisions in reference to cancellation of the contract are herein-before set out in that portion of this opinion which refers to the “results that follow from cancellation of the contract,” and attention is directed thereto.

The owner, evidently acting upon these provisions, sought to cancel .the contract; for on October 1, 1914, he wrote to the contractors and sent a copy of his letter to the surety company, and in this letter said: “We enclose therewith a copy of letter of even date received from the Scofield Engineering Company, our consulting engineers . . . This letter also certifies as to the extension in time allowed account of delays for which you were not responsible and because of these additions. This will confirm the instructions given you by them, . . and the extension in time stated in their letter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. Towns
126 S.E.2d 718 (Court of Appeals of Georgia, 1962)
Jenkins v. Gordy
124 S.E.2d 303 (Court of Appeals of Georgia, 1962)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
Morris v. Peachtree Heights Park Co.
143 S.E. 909 (Court of Appeals of Georgia, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
95 S.E. 113, 21 Ga. App. 758, 1918 Ga. App. LEXIS 516, Counsel Stack Legal Research, https://law.counselstack.com/opinion/savannah-lighting-co-v-fidelity-deposit-co-gactapp-1918.