George A. Fuller Co. v. Doyle

87 F. 687, 1898 U.S. App. LEXIS 2732
CourtU.S. Circuit Court for the District of Eastern Missouri
DecidedJune 4, 1898
DocketNo. 4,097
StatusPublished
Cited by20 cases

This text of 87 F. 687 (George A. Fuller Co. v. Doyle) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Eastern Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George A. Fuller Co. v. Doyle, 87 F. 687, 1898 U.S. App. LEXIS 2732 (circtedmo 1898).

Opinion

ADAMS, District Judge.

This is an action at law wherein the plaintiff, as obligee in a penal bond for $5,000, seeks to recover from defendant Doyle, as principal obligor, and the other defendant as surety, certain damages resulting from a failure of the principal to do certain brickwork in the construction of what is known as the “Fullerton Building,” located on the corner of Seventh and Pine streets, in the city of St. Louis, as required by a contract existing between the plaintiff and defendant Doyle in relation thereto. The condition of the bond, among other things, requires the defendant Doyle to well and truly perform the contract referred to.

In order to properly dispose of this case, it seems to me necessary to refer quite at length to the pleadings, with a view of ascertaining the issues on trial.

The plaintiff counts on the bond, and, by way of assigning breaches, alleges that Doyle, soon after commencing the work required by his contract, totally abandoned the same, and that plaintiff afterwards undertook, and did perform, the work and labor required of Doyle under his bond, and in so doing did necessarily and reasonably expend $4,765.93 over and. above the amount for which Doyle had agreed to do it. Plaintiff’s allegations in relation to the abandonment of the work, by Doyle consist of statements of admissions made by Doyle to that effect, and hardly reach that degree of certainty, in státing ultimate facts, required by rules of pleading; but the answers of both defendants so clearly treat the petition as alleging a total abandonment of the work, and so supplement the same, as to present the issue of abandonment clearly and distinctly.

The defendant trust company, for its amended answer, first denies every allegation of the petition, except such as it afterwards expressly admits. I will confine myself to a consideration of this aménded answer, as it includes all that is claimed in the answer of Doyle. An analysis of the trust company’s answer shows that it admits — First, that the defendants executed the bond sued on; second, that Doyle had a contract with the plaintiff to furnish all the materials and do the work referred to in the petition; third, that Doyle, soon after making the contract, abandoned the same, and refused to proceed further in its performance, and surrendered the premises to the plaintiff, and that thereafter the plaintiff took possession of the premises described in said contract, and proceeded in its own way, and on its own account, to do the work mentioned in Doyle’s contract. And for its affirmative defenses the defendant trust company pleads, in substance, that it was provided in the contract between Doyle and the plaintiff that if Doyle at any time should fail, refuse, or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any agreements contained in said contract, such refusal, neglect, or failure being certified by the architect, the plaintiff, after three days’ written notice to said Doyle, should be at liberty to provide such labor and materials, and to deduct the cost thereof from any money due', or thereafter to become due,' to said Doyle under said contract, and that the plaintiff should be a.t liberty to terminate the employment [689]*689of said Doyle for said work, and to enter upon the premises and take possession, for the purpose of completing the work comprehended under said contract, of all materials, tools, and appliances thereon, and to employ any other person or persons to finish the work, and to provide the materials therefor; and, in case of such discontinuance of the employment of said Dovle, that he (Doyle) should not be entitled to receive any further payment under said contract until the said work should be wholly finished, at which time1, if the unpaid balance of the amount to be paid under said contract should exceed the expense incurred by plaintiff in finishing the work, such excess should he paid by plaintiff' to■ said Doyle, but if such expense should exceed such unpaid balance then said Doyle should pay the difference to the plaintiff. Defendant trust company, after pleading the foregoing provisions of the contract known and referred to a.s article 5 thereof, alleges, in substance, that after the making thereof, to wit, on the 12th day of May, 1897, Doyle, by his certain writing described in plaintiff’s petition, ma.de and delivered to the plaintiff, waived the three-days notice provided for in that part of the contrae!, to which attention has just been called, and also waived the certificate therein provided for to be made by the architect, and notified the plaintiff that he could not perform said contract, and thereupon fully abandoned the performance of the same, and surrendered the premises to the plaintiff, and that the plaintiff proceeded, in its own way and on its own account, to construct the building mentioned in said contract, including the brick masonry therein, without giving notice to this defendant, namely, the trust company, of the fact that said Doyle had waived said three days’ written notice and certificate of the architect, or of the fact that the said Doyle had aban doned said work, and that plaintiff had undertaken to perform the same. The defendant trust company further alleges that it was not advised of such action on the part of Doyle until after plaintiff undertook to do the work; meaning, by necessary inference, that it was so advised at that time. The defendant trust company further alleges that it was the duty of the plaintiff to notify it of Doyle’s abandonment of the contract, and further alleges, in its answer, that, under the terms and conditions of said contract so pleaded by it. it became and was the duty of the plaintiff to employ some other person or persons to finish the work which Doyle had contracted to do and had abandoned as aforesaid. And defendant trust company concludes that, by reason of the plaintiff’s failure to give the nolice to defendant, prior to its entering upon and performing the work which Doyle had undertaken to do, of the fact that Doyle had abandoned the same, and by reason of the fact that the plaintiff had not employed some other person or persons to finish the work which Doyle had failed to do, hut, on the contrary, proceeded to perforin the work itself, the trust company was discharged from any liability. And for a second affirmative defense the trust compauv alleges, in substance, that, under the contract between Doyle and the plaintiff, Doyle was required to perform the work in question in strict accordance with the terms and conditions of the contract, including the [690]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oden Const. Co. v. HELTON
65 So. 2d 442 (Mississippi Supreme Court, 1953)
Future Fashions v. American Surety Co. of New York
58 F. Supp. 36 (S.D. New York, 1944)
Ware v. Davidson
42 S.W.2d 463 (Court of Appeals of Texas, 1931)
School Dist. Eddystone v. Lewis
101 Pa. Super. 583 (Superior Court of Pennsylvania, 1930)
Massachusetts Bonding & Ins. Co. v. Davis
274 S.W. 230 (Court of Appeals of Texas, 1925)
Savannah Lighting Co. v. Fidelity & Deposit Co.
95 S.E. 113 (Court of Appeals of Georgia, 1918)
Boise City v. National Surety Co.
165 P. 1131 (Idaho Supreme Court, 1917)
Board of Education of Salt Lake City v. Wright-Osborn Co.
164 P. 1033 (Utah Supreme Court, 1917)
Church of Immaculate Conception v. Curtis
153 N.W. 259 (Supreme Court of Minnesota, 1915)
Minor v. Woodward
166 S.W. 855 (Missouri Court of Appeals, 1914)
American Fidelity Co. v. Velie
196 F. 190 (Eighth Circuit, 1912)
Heidbrink v. Schaffner
127 S.W. 418 (Missouri Court of Appeals, 1910)
American Bonding Co. v. United States
167 F. 910 (Ninth Circuit, 1909)
Elmore & Womble v. Thaggard
61 S.E. 726 (Supreme Court of Georgia, 1908)
American Bonding & Trust Co. v. Gibson County
127 F. 671 (Sixth Circuit, 1904)
White v. Mitchell
65 N.E. 1061 (Indiana Court of Appeals, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
87 F. 687, 1898 U.S. App. LEXIS 2732, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-a-fuller-co-v-doyle-circtedmo-1898.