Fitger Brewing Co. v. American Bonding Co.

131 N.W. 1067, 115 Minn. 78, 1911 Minn. LEXIS 808
CourtSupreme Court of Minnesota
DecidedJune 30, 1911
DocketNos. 17,041 — (145).
StatusPublished
Cited by14 cases

This text of 131 N.W. 1067 (Fitger Brewing Co. v. American Bonding Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fitger Brewing Co. v. American Bonding Co., 131 N.W. 1067, 115 Minn. 78, 1911 Minn. LEXIS 808 (Mich. 1911).

Opinion

Simpson, J.

This action was brought to recover for payment made by plaintiff *79 upon lien claims after the same had been adjudged valid charges against his property. ' The claimed liability of defendant Hilliard, the general contractor, arose out of a breach of his contract in failing to refund to plaintiff the amount paid on lien claims. The claimed liability of the defendant the American Bonding Company of Baltimore arose upon a bond given by it, as surety, and Hilliard, as principal, conditioned upon the performance by Hilliard of his contract, through the required payment by plaintiff of the lien claims. The defendant company interposed a general demurrer to the complaint. The district court, by its order, sustained the demurrer on the ground that it conclusively appeared from the complaint that the action on .the defendant’s bond was not brought within the period limited by the terms of the bond for bringing actions thereon. The case is brought to this court by the appeal of the plaintiff from such order.

The plaintiff questions the correctness of the order sustaining the demurrer, and claims (1) that, the limitation being by contract, the bar is not invoked by deiirarrer, but must be set up by answer as a defense; and (2) that it does not appear from the complaint that the action is not brought within the period limited by the bond.

1. The established rule in this state is that the bar of a limitation, when fixed by statute, may be invoked by a general demurrer. No reason is suggested or is apparent why a different rule should be adopted as to a valid limitation established by contract. The same principle applies in each case. A demurrer should be given a uniform effect as a pleading. If it conclusively appears by the complaint that the action on the bond was not brought within the time limited by the terms of the bond for bringing actions thereon, the general demurrer was properly sustained.

2. A more difficult question arises when we undertake to determine by an examination of the complaint whether the time limited by the bond for bringing an action thereon had expired before this action was brought.

The contract and bond involved are set out in full in the complaint. The contract between the plaintiff and the defendant Hilliard is a usual building contract, by which Hilliard agreed to furnish all la *80 bor and material and erect a building in tbe city of; Duluth for the ^plaintiff, according to plans and specifications, for an agreed price. The contract provided that the building should be completed January 1, 1909, that the owner might withhold from any payment due the contractor an amount sufficient to indemnify it against any lien claim, and, “should there prove to be any such claim after all payments are made, the contractor shall refund to the owner all moneys that the latter may be compelled to pay in discharging any lien on said premises made obligatory in consequence of the contractor’s default,” and contained the further agreement: “The contractor to furnish to the owner a satisfactory bond executed by some good surety company in the sum of ten thousand dollars for the faithful performance of this contract on his part.”

The bond, in the sum of $10,000, executed by the defendant company in the usual form, recited the making of the above contract, conditioned its obligation on the failure of the contractor to fully perform his contract, and continued: “Notwithstanding that, said contract is hereby referred to, this bond is nevertheless 'issued subject to the following express conditions, which shall be conditions precedent to the right of the ‘owner’ to recover hereunder: * * *

“Provided, that said ‘surety’ shall be notified in writing of any breach of said contract by said ‘principal,’ or of any act on the part of the said ‘principal’ or his agent or employees, which may involve a loss for which the said ‘surety’ may be liable hereunder, immediately after the occurrence of such act shall have come to the knowledge of said 'owner.' * * *
“The ‘surety’ shall not be liable under this bond to any one except the ‘owner;’ but it is agreed that the ‘owner,’ in estimating his damage, may include the claim of mechanics and materialmen, arising out of the performance of the contract, and paid by him only when the same, by the statutes of the state where the contract is to be performed, are valid liens against said property. * * *"
“And provided, further, that any suits at law or proceedings in equity brought or to be brought against said ‘surety’' to recover any claim hereunder must be instituted within six (6) months after the first breach of said contract; and in no event shall any action or pro *81 ceedings be brought against the surety hereunder after the expiration of six months after the date of the completion of the work under said contract.”

It further appears by the complaint that on April 23, 1909, the plaintiff duly notified the defendant company “of the broach of said contract by said contractor, and of his failure to pay claims for labor and material used in the performance of said building contract;” that certain lien claims were duly filed, and in a suit brought were duly adjudged valid claims against plaintiff’s property in the aggregate sum of $3,191.89; that plaintiff paid this amount and caused the judgment to be satisfied and discharged; that the amount so paid was $2,613 in excess of the unpaid balance of the contract price of said building; that the defendant company was duly given notice of such suit and leave to defend therein; that the defendant Hilliard failed and refused to refund the amount so paid. From the facts so alleged, the defendant company claims it is made to appear by the complaint that a lien claim was filed against said property April 23, 1909, and thereby there was a breach of the contract; that this breach was known to and treated as such by the plaintiff on that date; that the plaintiff’s right to sue on the bond was limited to a period within six months after April 23, 1909, the date of the “first breach -of said contract;” and that this action, having been brought long after the expiration of such period, is barred by the limitation contained in the bond.

We are of the opinion that this position is not warranted by a fair construction of the terms of the bond. It is clear that by the terms •of the bond — reference being had to the first proviso set out above— a right of action on the bond did not arise from the failure of the contractor to perform his contract and the resulting existence of valid liens on the property for unpaid material or labor, but arose from payment of such claims by the owner. The company, through this proviso, assumed, not the full obligation of suretyship, but, as to lien claims, only that of indemnifying the plaintiff for sums paid by him to discharge valid liens. The limitation clause in the bond relates to actions brought to enforce liability under the bond. It would seem, therefore, that the breach of the contract referred to therein, *82 was a continuing breach, resulting in a loss to the plaintiff, for .which the defendant company -was liable — that is, as to lien claims, a payment by the plaintiff of a valid lien against the property.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prior Lake State Bank v. National Surety Corp.
80 N.W.2d 612 (Supreme Court of Minnesota, 1957)
State Bank of New Prague v. American Surety Co.
288 N.W. 7 (Supreme Court of Minnesota, 1939)
State v. Tupa
260 N.W. 875 (Supreme Court of Minnesota, 1935)
Odegard v. General Casualty & Surety Co.
44 F.2d 31 (Eighth Circuit, 1930)
National Tea Co. v. McDonough
227 N.W. 205 (Supreme Court of Minnesota, 1929)
Watters v. Fisher
139 A. 842 (Supreme Court of Pennsylvania, 1927)
Johnson v. Laurence
214 N.W. 24 (Supreme Court of Minnesota, 1927)
Community Bldg. Co. v. Maryland Casualty Co.
8 F.2d 678 (Ninth Circuit, 1925)
Chicago, Rock Island & Pacific Railway Co. v. Theobald Flour Mills Co.
191 N.W. 920 (Supreme Court of Minnesota, 1923)
Kildall Fish Co. v. Giguere
162 N.W. 671 (Supreme Court of Minnesota, 1917)
Church of Immaculate Conception v. Curtis
153 N.W. 259 (Supreme Court of Minnesota, 1915)
Ferrier v. McCabe
152 N.W. 734 (Supreme Court of Minnesota, 1915)
Fitger Brewing Co. v. American Bonding Co. of Baltimore
149 N.W. 539 (Supreme Court of Minnesota, 1914)
Pulaski Hall Ass'n v. American Surety Co.
143 N.W. 715 (Supreme Court of Minnesota, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
131 N.W. 1067, 115 Minn. 78, 1911 Minn. LEXIS 808, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fitger-brewing-co-v-american-bonding-co-minn-1911.