Beebe v. Redward

77 P. 1052, 35 Wash. 615, 1904 Wash. LEXIS 487
CourtWashington Supreme Court
DecidedSeptember 21, 1904
DocketNo. 4927
StatusPublished
Cited by16 cases

This text of 77 P. 1052 (Beebe v. Redward) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Beebe v. Redward, 77 P. 1052, 35 Wash. 615, 1904 Wash. LEXIS 487 (Wash. 1904).

Opinion

Fullerton, C. J.

On May 24, 1901, the respondent Clifford D. Beebe entered into a contract with tie appellant Join C. Redward, by tie terms of which. Redward undertook to furnish all tie necessary labor and materials and erect for tie respondent a building, according to plans and specifications referred to in tie contract, for tie agreed price of $25,022. Shortly after the execution of tie contract, tie appellant Redward, as principal, and his co-appellant Tie United States Fidelity and Guaranty Company, as surety, executed and delivered to the respondent a bond in tie sum of six thousand dollars, conditioned, among other things, that tie contractor would well, truly, and faithfully comply with all tie terms, covenants, and conditions of tie contract on his part to be kept and performed according to its tenor and effect. After tie execution of tie contract and bond, Redward entered upon tie work of constructing tie building, substantially complet[617]*617ing it about December 1, 1901, some three months later than the time fixed in the contract for its completion. On the date last named, R. Clark & Sons filed a lien on the building, to secure themselves for materials sold the contractor, and used in the construction of the building. Later on, two certain other liens were filed, one by the Robinson Manufacturing Company, and the other by the Seattle Lumber Oopmany, each claiming balances due from Red-ward for materials furnished him for use in the construction of the building.

Foreclosure actions were thereafter begun on the several liens, against which the respondents and the appellants Redward unsuccessfully defended, the several claimants recovering judgment of foreclosure against the property, for the amount claimed by them, with costs of suit and attorney’s fees added, which judgments the respondents paid in full. The judgment in favor of R. Clark & Sons was for the sum of $1,840.89, was entered June 30, 1902, and was paid on J uly 2, 1902. The judgment in favor of the Rohinson Manufacturing Company was for the sum of $1,150, was entered on the 6th of Rovember, 1902, and was paid on December 5,1902. The judgment in favor of the Seattle Lumber Company was for the sum of $1,038.38, was entered on the 8th of October, 1902, and was paid December 10, 1902. In addition to these sums, the respondents paid in each case the statutory appearance fee of $2.00, and $50 to' the attorneys employed by them to defend the actions. At the time of the filing of the first lien, the respondents had paid to the contractor all of the original contract price, except the sum of $280. There was, however, an amount owing for extra work and material. This amount was in dispute between the respondents and the contractor, but it was conceded by the respondents that the amount aggregated at least $663.50.

[618]*618This action was begun on December 16, 1902. In their complaint the respondents alleged that there was due them, by reason of the matters above set forth, the sum of $3,270.19, being the difference between the amount paid on account of the construction of the building and the contract price plus the value of the conceded extras. To the complaint the appellants answered separately. They put in issue the rendition and payment of the lien judgments set out in the complaint, and set up several affirmative defenses. One of those set up by the appellants Redward, was the claim that the contractor Redward had performed extra labor upon, and furnished extra material used in, the construction of the building, to an amount aggregating $1,676.50, which had not been paid or allowed to him by the respondents. The other appellant set up the same defense, contending however, that the reasonable value of the extra work and material put on the building by the contractor more than exceeded the difference between the contract price and the amount actually paid to his account, and the further defense that the action had not been begun within the time prescribed by the terms of the bond. Replies were filed, putting in issue the new matter of the answers, and a trial had before the court and a jury, resulting in a verdict and judgment in favor of the respondents for the sum of $2,812.75 and the costs of the action.

The appellants Redward first assign that the court erred in refusing to grant their motion for nonsuit, made at the close of the plaintiffs’ case. The motion was based on the ground that the respondents had failed to prove payment by them of the judgments obtained by the lien claimants. The proofs on this point consisted of a transcript of the judgment roll, showing the commencement and prosecution of the several actions, the judgments entered therein, and [619]*619a signed receipt from each of the judgment creditors acknowledging payment to them of the amounts of their respective judgments. It is objected that these receipts were incompetent to prove payment, because no proof was made of their authenticity or execution, and that they were not, before the trial, submitted to the apppellants for inspection, nor were the appellants, before the trial, served with a copy of the instruments or with notice that the respondents intended to read them in evidence, as required by the statute. But the receipts were objected to in the court below because they did not show payment, and not on the grounds here suggested, and we think the appellants cannot now urge these objections. By failing to object on the ground that the instruments were not duly authenticated, or shown to have been executed by the judgment creditors, the appellants admitted their genuineness, and they were properly admitted in evidence if competent for any purpose.

So, likewise, the failure to object on the ground that the writings were not submitted to inspection before the trial is a waiver of that objection. This objection is also unsound for the reason that the statute cited (§ 6048 Bal. Code) does not make it necessary that a writing, material as evidence, be offered to the other party for inspection and be served on him by copy prior to the trial, before it can be admitted in evidence. ' This section of the statute was intended to enable a party to ascertain, in advance of the trial, whether or not it will be necessary for him to prove the genuineness of his written evidence at the trial. If he offers the writings for the inspection of the other party, and delivers him a copy thereof, with notice that he intends to read the same in evidence at the trial, they may be so read without proof of their genuineness or execution, un[620]*620less the other party, before the commencement of the trial, denies their genuineness by affidavit; but the statute was intended to afford an additional remedy; it was not intended as a denial of the right to put in evidence a writing in the manner prescribed by the general rules of evidence. It was proper, therefore, for the plaintiffs to offer these writings in evidence at the trial in the manner they did offer them, and the court did not err in admitting them over the objections urged. It may be well to say here, however, that we do not intend to assert that a receipt, acknowledging payment of money, is generally admissible as evidence of such payment as against strangers thereto; as to them, of bourse, it is but the hearsay declaration of the party who signed it. But where a receipt is admitted in evidence against such a stranger, without objection on that ground, it is, like other hearsay evidence so admitted, sufficient to support a finding based thereon. The motion for nonsuit was properly Denied.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mobile Components, Inc. v. Layon
1980 OK 173 (Supreme Court of Oklahoma, 1980)
Hartford Accident and Indemnity Company v. Orr
1957 OK 165 (Supreme Court of Oklahoma, 1957)
Haddock Construction Co. v. Wilber
169 P.2d 599 (Oregon Supreme Court, 1946)
Atkins v. Clein
100 P.2d 1 (Washington Supreme Court, 1940)
State v. Pappas
80 P.2d 770 (Washington Supreme Court, 1938)
Columbia Security Co. v. Aetna Accident & Liability Co.
183 P. 137 (Washington Supreme Court, 1919)
Fitger Brewing Co. v. American Bonding Co.
131 N.W. 1067 (Supreme Court of Minnesota, 1911)
Ætna Indemnity Co. v. Town of Comer
70 S.E. 676 (Supreme Court of Georgia, 1911)
James Black Masonry & Contracting Co. v. National Surety Co.
112 P. 517 (Washington Supreme Court, 1911)
Sheard v. United States Fidelity & Guaranty Co.
107 P. 1024 (Washington Supreme Court, 1910)
Martin v. Empire State Surety Co.
101 P. 876 (Washington Supreme Court, 1909)
Denny v. Spurr
80 P. 541 (Washington Supreme Court, 1905)
Seattle v. Aetna Indemnity Co.
79 P. 1097 (Washington Supreme Court, 1905)
Ovington v. Aetna Indemnity Co.
78 P. 1021 (Washington Supreme Court, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
77 P. 1052, 35 Wash. 615, 1904 Wash. LEXIS 487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/beebe-v-redward-wash-1904.