Hartford Accident and Indemnity Company v. Orr

1957 OK 165, 321 P.2d 373, 1957 Okla. LEXIS 645
Supreme Court of Oklahoma·Decided June 25, 1957·No. No. 37483·Published·Cited by 2 cases

Opinion

BLACKBIRD, Justice.

This appeal involves liability under a bond which a contractor named Karl K. Adams of Shawnee, Oklahoma, d/b/a Adams Plumbing, or Plumbing & Heating,, Company, furnished to assure his faithful performance of a contract to construct an automobile service station in Norman, Oklahoma, for said City’s Glenn L. Orr, who appears herein as defendant in error. The bond was issued to Adams by one Jerry Casey, plaintiff in error’s Shawnee, Oklahoma, agent, after his wife, as one of said company’s attorneys-in-fact had executed it for said company, as surety. Adams was the Principal and Orr, the ob-ligee, named in the bond. It appears that Orr had originally promised the construction contract to one Russel F. Henry, who was living in Norman at the time; but, when it was discovered that Henry could not obtain a performance bond, the contract was entered into with Adams, who, previous to September 20, 19S4, the date of both the contract and bond, had agreed to become associated with Henry. This agreement between the two was evidenced by a writing entitled “Joint Venture Agreement”, dated September 16, 1954, drawn by the bonding company’s Shawnee agent, Casey, and signed by both men. The agreement recited that Adam’s and Orr’s purpose in entering into it was to bid on and perform “contracts as joint venturers under the name of General Construction Company”, and it provided that each would have a 50% interest in said “joint venture * * or any work in connection therewith * ⅜ ‡ »

As the work on the Norman service station progressed, Orr paid the price specified' for its construction in the above-mentioned' contract, in three separate installments. All' of these payments were made by checks payable to “General Contracting Company (Karl K. Adams and Russel F. Henry).”’ Orr issued and delivered the last of these checks on February 4, 1955, after construction of the station had been completed and he had received a letter from Adams, dated February 3, 1955, stating: “This is to certi[375]*375fy that all material and labor incurred in the construction of * * * (the) building, have been paid in full, as of this date,” and an instrument entitled “Waiver Of Lien” executed by both Adams and Henry, in which, among other things, it was stated: “We * * * certify that all claims for labor, materials and machinery rentals and any other claims and demands that may be the basis of liens against the * * * property have been paid in full.”

Notwithstanding the foregoing assurances, the G & M Woodworking Shop, who claimed to have furnished some of the labor and materials that went into construction of the station, filed a labor and material-man’s lien therefor against the property, on February 23, 19SS, alleging a balance due it of more than $1,000. During the ensuing month, other such liens were filed against the property; and, on March 9, 1955, one of these lien claimants, Jess Waters, d/b/a Waters Electric Company, commenced the present action to foreclose his lien. By March 17th of that year, two other such lien claimants had filed answers and cross petitions seeking foreclosure of their liens in the same action. Almost ten days thereafter, or on March 25th, the attorney who appears herein for Mr. Orr, addressed a registered letter to the bonding company, calling its attention to the fact that it had executed Adams’ performance bond as surety; stating, among other things, that Adams had defaulted in payment of the bills incurred in the station’s construction; and calling upon said surety to fulfill its duty, under the provisions of the bond, by taking “immediate steps to discharge or see that your Principal discharges all of his unpaid obligations covered by” the bond. When no reply was received to said letter, Orr obtained an order of court in the aforesaid lien foreclosure action, making additional parties defendant thereto, both Adams, d/b/a Adams Plumbing & Heating-Company, and said surety on Adams’ bond. Subsequently, after other lien claimants had filed pleadings, setting up their lien claims therein, and said action had been consolidated with another such action, the court, in the consolidated case, rendered its judgment on December 5, 1955, granting said lien claimants money recoveries on their claims, totalling more than $3,000, plus a further sum totalling more than $900 as said lien claimants’ attorneys fees, against both “Karl K. Adams and R. F. Henry, partners doing business as General Construction Company otherwise known as General Contracting Company and Karl K. Adams, a sole trader doing business as Adams Plumbing Company”, and establishing said claims as valid liens against Orr’s service station property.

The cause thereafter went to trial upon the issues (with which we are concerned herein) between Orr and the bonding company. At the close of said trial, the court rendered judgment in Orr’s favor against the bonding company for the principal sum of $3,627 with interest, which principal sum, according to the journal entry of said judgment, represented “the unpaid balances w;.'i interest to date on the judgments rendered herein against Karl K. Adams, d/b/a Adams Plumbing & Heating Company, on December 5, 1955 * * * ”. The judgment also granted Orr recovery of the additional sum of $942.50, as the total of the attorneys fees for which the lien claimants had been granted recovery against Adams by the December 5th judgment. The judgment here involved also granted Orr recovery of the additional sum of $750 as his attorneys fees for defending himself in the lien-foreclosure phase of the action, and for prosecuting his own claim against the bonding company. The judgment was based upon certain findings of fact and conclusions of law pertinent to the issues argued in the bonding company’s present appeal therefrom. These will hereinafter be mentioned in connection with said company’s argument. As it and Orr appear herein as appellant and appellee, respectively, we will hereinafter refer to them as such.

The first, of the three propositions appellant urges to show error in the trial court’s determination of its liability as surety on the performance bond furnished Adams, pursuant to his construction contract with [376]*376appellee, involves a provision of said bond therein made a condition of said company’s liability thereon to appellee Orr, as the ob-ligee named therein. Said provision reads, in part, as follows:

“ * * * it shall be a condition precedent to any right of recovery hereunder that, in the event of any default on the part of the Principal, a written statement of the particular facts showing the date and nature of such default shall be immediately given by the Obligee to the Surety and shall be forwarded by registered mail to the Surety. * * * ” (Emphasis ours.)

Appellant concedes that, under court decisions governing the matter, provisions for the obligee’s giving the surety immediate notice, such as the foregoing, are to be construed to mean “within a reasonable time”; but it points to Orr’s testimony to the effect that he knew “within the week” after his last payment to General Contracting Company “that a lien had been filed * * * or claims were being made for unpaid accounts” on the job; and, on the basis of such knowledge coming to Orr, as indicated, on or about February 11th, it argues that the 41 days which elapsed between that date and Orr’s aforedescribed letter of March 25th, to the bonding company, was not a reasonable time under the circumstances.

Free access — add to your briefcase to read the full text and ask questions with AI

Hartford Accident and Indemnity Company v. Orr, 1957 OK 165, 321 P.2d 373, 1957 Okla. LEXIS 645 (Okla. 1957).

1957 OK 165 (Hartford Accident and Indemnity Company v. Orr) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mobile Components, Inc. v. Layon
1980 OK 173 (Supreme Court of Oklahoma, 1980)