City of Des Plaines v. B — W Construction Co.

42 N.E.2d 343, 314 Ill. App. 610, 1942 Ill. App. LEXIS 1064
CourtAppellate Court of Illinois
DecidedMay 27, 1942
DocketGen. No. 42,067
StatusPublished
Cited by1 cases

This text of 42 N.E.2d 343 (City of Des Plaines v. B — W Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Des Plaines v. B — W Construction Co., 42 N.E.2d 343, 314 Ill. App. 610, 1942 Ill. App. LEXIS 1064 (Ill. Ct. App. 1942).

Opinion

Mr. Presiding Justice Burke

delivered the opinion of the court.

In a complaint filed in the circuit court of Cook county on October 18, 1935, the City of Des Plaines, a municipal corporation, sought a judgment in the sum of $17,326.79 for damages sustained because of the alleged failure of the B — W Construction Company, a corporation (hereinafter called the “A” contractor) to carry out its agreement for the construction of a portion of a softening plant, reservoir and pumping station, the performance of which was guaranteed by the American Surety Company of New York (hereinafter called the “Surety”). Issue was joined. At the close of plaintiff’s case, the court directed a verdict for the defendants and entered judgment accordingly, to reverse which this appeal is prosecuted.

The parties are in agreement that the question of law presented upon a motion to direct a verdict is whether when all of the evidence is considered, together with all reasonable inferences drawn from it in its most favorable aspects to the party against whom the motion is directed, there is a total failure to prove one or more necessary elements of the case. (Foreman-State Trust & Savings Bank v. Demeter, 347 Ill. 72.) Plaintiff insists that it proved all of the elements to make out a prima facie case, and that the court was not warranted in directing a verdict. Defendants, on the other hand, maintain that plaintiff failed to prove an essential element of its cause of action. To determine this point, we have carefully read' the transcript of the testimony and the exhibits. In 1935, the municipality, a suburb located northwest of Chicago, undertook with the aid of federal funds, the construction of a water softening plant, reservoirs and other structures necessary for the operation and maintenance of a public water works system. The construction work and installation of the necessary machinery was to be done by six different contractors and agreements were entered into between the city and each of the contractors. In this case only two contractors need be considered. The “A” contractor was the successful bidder for section “A” of the project, which, included the principal construction of the plant' and reservoirs, including necessary excavation.The “B” contract was awarded.to the Economy Heating and Plumbing Company, which agreed to install the plumbing and to construct a toilet sewer. Each contract was executed separately. The contracts included, in addition to the agreement, plans and specifications, construction regulations issued by the Federal Government and general conditions of the contract in a form prepared and approved by the American Institute of Architects. Each set of specifications included details of the work to be done by all of the contractors. The agreement with the “A” contractor was entered into on October 18, 1935. At that time the “B” contract had not been executed. On November 6,1935, the “A” contractor commenced excavating on the site of the project. At that time the “B” contract had not been approved and it was not officially approved until the latter part of November 1935. The specifications for the work alloted to the “A” contractor provided that “the toilet sewer shall be installed by contractor “B” as the first construction and used to drain the excavation.” Defendants maintain that this language required the installation of a sewer which would actually drain the excavation as a condition precedent to the obligation of “A” contractor under its agreement with plaintiff. We are of the opinion that the contract contemplated that before the “A” contractor could be required to perform its part of the work, plaintiff would cause the “B” contractor to install a toilet sewer which could be used by the “A” contractor to drain the excavation. The specifications required the “A” contractor to excavate an area approximately 18,000 square feet to a depth varying between 4 and 4% feet. During the month of November the “A” contractor continued to work and excavate on the site. It completed the excavation about December 5, 1935, and removed its excavating equipment. It then caused reinforcing steel and lumber to be delivered to the site. Thereafter, it had a superintendent on the job, who supervised the building of an office and staked out the job. On February 26, 1936, the “A” contractor notified plaintiff that it was electing to terminate the contract. Plaintiff thereafter called upon this contractor to resume work and notified the Surety that it would hold it to its bond in case any loss resulted from the failure of the contractor to proceed with the work.. On May 14, 1936, neither the Surety nor the contractor having recommenced work, another contractor, R. 0. Wieboldt Company, started the completion of the project originally undertaken by contractor “A.” The work to be done by Wieboldt was identical with that contracted by contractor “A.”

Lancelot F. Wysockey, called as a witness by plaintiff, testified that he was a construction engineer; that he represented the Public Works Administration in connection with the construction of the waterworks project for the City of Des Plaines; that he was assigned to the project about November 1, 1935, and was there until February 18, 1936; that it was his duty to report to the State Engineer Inspector the progress and activities of construction and to see that the project was constructed according to the plans and specifications; that he had an office on the project; that the “B” contractor came to the site about December 21, 1935, and started excavating a drain line from the main excavation, that is where the site of the plant was, to a connected sewer along the east side of the property, and worked on that until January 18, 1936, when it had completed that portion of the contract. On cross-examination, this witness testified that the “B” contractor came to the site the latter part of November 1935, and actually commenced work about December 21; that this contractor started excavating the north side of the plant and continued until the holidays and then put in several days between Christmas and New Year’s, started again the first part of January 1936, and continued until about the middle of January 1936, “When he completed that portion of it.” When asked what he meant by “portion,” the witness stated that the “B” contractor had a contract to install pipe inside as well as outside of the building, that he started the outside work first and came on to the site where the building was going to be erected, and that the balance of the work on the inside could not be completed until the other contractor had completed part of his work. Counsel called the witness’s attention to the provision that “the toilet sewers shall be installed by contractor ‘B’ as the first construction and used to drain the excavation” and asked, “Now when you say they completed their work on January 18, 1936, had they completed the toilet sewers to drain the excavation that this specification called for ? ’ ’ Witness answered, “Yes, that is a waste line; I made the statement that they had installed a waste line and drain line, and that is a toilet sewer.” In answer to the question as to where it was, he answered, “It was on the east side, on the north side of the plant, and it came in from the north, in along the east side and made a connection across into the plant and also another connection over to the old present pumping station. In other words, it came over in sort of an H-shape.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cady v. Hartford Fire Insurance
206 N.E.2d 535 (Appellate Court of Illinois, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
42 N.E.2d 343, 314 Ill. App. 610, 1942 Ill. App. LEXIS 1064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-des-plaines-v-b-w-construction-co-illappct-1942.