Cook v. Heinbaugh

210 N.W. 129, 202 Iowa 1002
CourtSupreme Court of Iowa
DecidedSeptember 21, 1926
StatusPublished
Cited by6 cases

This text of 210 N.W. 129 (Cook v. Heinbaugh) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cook v. Heinbaugh, 210 N.W. 129, 202 Iowa 1002 (iowa 1926).

Opinion

Albert, J.

Heinbaugh made a contract with Cook and thé. G-rande Avenue Land Company, by which he was to ’furnish material for the construction of a residence for the sum of $5,050. To guarantee the performance of- his contract, he furnished to them the -bond o.f the United States • Fidelity & Guaranty Company. Among the provisions of said bond is the following:

“In no event shall.the surety be * * * subject to any suit, action or proceeding thereon, that is instituted later than the first day of September, A. D. 1923.”’

Heinbaugh defaulted on his contract, and the building was not .completed by July 1st,- as therein provided: it was not, in fact, completed until after the middle of August, 1923. This action- was commenced on the 30th of July, 1924, which gives rise to the first question argued, to wit, that the action; not having been commenced before the first day of September, is not now maintainable.

*1004 *1003 ' We have recognized the rule in this state that, notwithstanding 'the general statute of limitation, parties to a contract may stipulate to a shorter limitation than that provided by the *1004 statute, and such, an agreement, generally speaking, supersedes the statute and binds the parties. Harrison v. Hartford Fire Ins. Co., 102 Iowa 112, and cases there cited. We do not care to disturb this general rule, but, like all general rules, it has its limitations. While the legislature has the right to enact statutes of limitation, and its pronouncement therein is usually conclusive, yet even the power of the legislature in this respect is limited, or subject to the fundamental condition that a reasonable time shall be allowed for the exercise of the right of action. See 12 Corpus Juris 978, Section 574, where a wealth of authority is cited on this proposition. An elaborate discussion of this question may be found in a decision from the United States circuit court of appeals, Lamb v. Powder River Live Stock Co., 65 C. C. A. 570 (132 Fed. 434), where it is said:

“But the power to enact such statutes is subject to the fundamental condition that a reasonable time must be given for the exercise of the right of action, whether existing or prospective, after it comes within the prospective or present operation of the statute, and before the bar becomes effective. ’ ’

We are of the opinion that the right and power of the parties to a private contract is limited in the same way, to wit: that the time provided must be a reasonable time, in the light of the surrounding circumstances, facts, and nature of the contract, and its purpose. In 1 Wood on Limitations (4th Ed.), Section 42, it is said:

Parties to a contract may, by an express provision therein, provide another and different period of limitation from that provided by statute, and that such limitation, if reasonable, will be binding and obligatory upon the parties.”

Throwing light on this subject are Longhurst v. Star Ins. Co., 19 Iowa 364; Gintjee v. Knieling, 35 Cal. App. 563 (170 Pac. 641) ; Sheard v. United States Fid. & Guar. Co., 58 Wash. 29 (107 Pac. 1024); Columbia Sec. Co. v. Aetna Acc. & L. Co., 108 Wash. 116 (183 Pac. 137) ; Pacific Mut. Life Ins. Co. v. Adams, 27 Okla. 496 (112 Pac. 1026).

Turning now to the building contract existing between the appellees and Heinbaugh, we note that the contract provides that the building shall be completed by July 1, 3923: but time is not made the essence of the contract by any provision therein. *1005 Under Section 10278, Code of 1924, all of Heinbaugh’s subcontractors had sixty days after the completion of the contract m which to file mechanic’s liens. During that time it would ordinarily be uncertain as to just what outstanding claims there might be which would be the subject of mechanic’s liens, and it would not be safe for the owner to make payment until the time had expired for filing mechanic’s liens. After the time had expired for filing mechanic’s liens, the owner would he bound to pay such lien holders before he could maintain the action on this bond. New England Equitable Ins. Co. v. Boldrick, 192 Iowa 763; Cousins v. Paxton & Gallagher Co., 122 Iowa 465; Wilson v. Smith, 23 Iowa 252. It is quite apparent from this situation that, until the expiration of sixty days for filing mechanic’s liens, it would be uncertain what the owner would have to pay out on account of Heinbaugh’s breach of contract; therefore, it would have been impossible for him to have commenced his action on this bond "not later than September 1st.”

We have also held that, as against a limitation of this kind in an insurance policy, such limitation does not operate against outstanding mechanic’s liens until the amount due on said mechanic’s liens is determined. Stout v. City Fire Ins. Co., 12 Iowa 371; Longhurst v. Star Ins. Co., supra; Ellis v. Council Bluffs Ins. Co., 64 Iowa 507. We hold, therefore, that, under the facts in this case, the limitation provided in the bond was unreasonable, and therefore void. This being so, the general statute of limitations would apply; and as the action was brought within the time provided by the general statute of limitations, it is validly maintained.

However, appellant company insists that the foregoing rule should not apply because of the fact that, on the 30th day of August, Cook phoned the company and asked for an extension of time, and the company sent him a written extension of time providing that action might be brought up to the 15th day of October.

The owner was not in any better position on the 15th day of October, to determine the exact amount of loss' he would suffer under this contract, than he was on the first day of September. We find nothing available to the appellant on this contention.

*1006 To a fair understanding of the questions raised herein, a general review of the fact situation is necessary. Malcolm V. Bolton conducted a general insurance business, under the trade name of Malcolm V. Bolton & Company, in the city of Cedar Rapids at the time involved herein. C. C. Cook, the appellee, was in the employ of that company, as manager of the insurance department. At this time, Bolton & Company were local representatives or agents of appellant Fidelity & Guaranty Company. Cook had bought a lot from the Grande Avenue Land Company, of which Bolton was secretary and sales agent, on which he proposed to build a dwelling house. He let a contract to Heinbaugh to furnish the material and construct the building under certain plans and specifications, which- are not now material. To secure the performance of this contract by Hein-baugh, an application was made to the appellant guaranty company for a bond. Cook filled out the application, and Hein-baugh signed the same. The bond issued thereon is the bond in suit herein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Douglass v. American Family Mutual Insurance Co.
508 N.W.2d 665 (Supreme Court of Iowa, 1993)
Camelot Excavating Co., Inc. v. St. Paul Fire & Marine Ins. Co.
301 N.W.2d 275 (Michigan Supreme Court, 1981)
Page County v. Fidelity & Deposit Co.
216 N.W. 957 (Supreme Court of Iowa, 1927)
Ryan v. Phoenix Insurance
215 N.W. 249 (Supreme Court of Iowa, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
210 N.W. 129, 202 Iowa 1002, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cook-v-heinbaugh-iowa-1926.