Camelot Excavating Co., Inc. v. St. Paul Fire & Marine Ins. Co.

301 N.W.2d 275, 410 Mich. 118, 1981 Mich. LEXIS 232
CourtMichigan Supreme Court
DecidedFebruary 3, 1981
Docket62978, (Calendar No. 14)
StatusPublished
Cited by46 cases

This text of 301 N.W.2d 275 (Camelot Excavating Co., Inc. v. St. Paul Fire & Marine Ins. Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camelot Excavating Co., Inc. v. St. Paul Fire & Marine Ins. Co., 301 N.W.2d 275, 410 Mich. 118, 1981 Mich. LEXIS 232 (Mich. 1981).

Opinions

Blair Moody, Jr., J.

Plaintiff Camelot Excavating Company (hereafter Camelot) brought action against defendant St. Paul Fire and Marine Insurance Company (hereafter St. Paul) to recover payment on a labor and materials bond. Camelot was a subcontractor of third-party defendant Priestly Contracting, Inc. (hereafter Priestly). Priestly was named as principal on the bond. Defendant St. Paul moved for accelerated judgment on the basis of a one-year period of limitations contained in the [124]*124bond contract.1 Plaintiff Camelot brought a motion for summary judgment under GCR 1963, 117.2(3).2 Camelot’s motion was granted; St. Paul’s motion was denied.

St. Paul appealed to the Court of Appeals. The Court reversed on grounds that the one-year limitations period did apply so as to preclude Camelot’s third-party claim under the bond. 89 Mich App 219; 280 NW2d 491 (1979). We granted leave to appeal. 406 Mich 1009 (1979).

We must resolve two questions presented by the parties: (1) whether the bond contract negotiated by the principal, Priestly, and surety, St. Paul, to insure claims against labor and material for the benefit of a third party can subject plaintiff Camelot to a limitation period which is shorter than that created by the Legislature; and (2) whether the form of bond used in this state in this case and in other states throughout the United States which makes reference to statutes of limitations within the particular state where it is used is ambiguous.

We hold that neither public policy nor existing [125]*125authority prohibit private contracting parties from including in a labor and materials payment bond a provision which reasonably limits claimants to a period within which to bring suit that is shorter than the applicable state statute of limitations. We further find that the form of contract used in this case is clear on its face. The contractual exception clause to the one-year limitation provision is relevant only where state statutes prohibit shorter than statutory limits. Thus, this clause does not apply to preclude the one-year provision in this case. The Court of Appeals is therefore affirmed.

I

On April 8, 1973, defendant Priestly, general plumbing contractor for a private apartment construction project, contracted with defendant St. Paul to obtain a required labor and materials payment bond. The bond provided that St. Paul, as surety, would pay claims made by subcontractors of Priestly, as principal, where the subcontractor had not been paid in full within 90 days of the completion of the subcontractor’s work. The bond was primarily intended to protect the owner of the project, Village Homes, Inc., against mechanics’ lien claims which might accrue over the course of building construction. Priestly entered into a subcontract with Camelot for certain excavation work. The claims intended to be secured were those of subcontractors such as plaintiff Camelot.

As subcontractor, Camelot completed the excavation work pursuant to its contract with Priestly. The construction proceeded until April, . 1974, when defendant Priestly abandoned the project. Priestly gave no notice to Camelot that it was leaving the project. At that time, the balance due for the work Camelot had provided was $18,848.

[126]*126Camelot brought suit against Priestly and recovered a default judgment for the amount owing. Then, on August 26, 1976, plaintiff separately sued defendant St. Paul on the bond. St. Paul interposed the defense that the contract barred Camelot’s suit on the basis of the one-year limitation clause contained in the bond contract.

The learned trial judge held that the qualifying language in regard to prohibition of private limitation periods by the state limitations statute rendered the contract provision ambiguous and therefore rejected the asserted defense against plaintiff’s claim. On appeal, the Court of Appeals reversed. It found no ambiguity in that the qualifying provision proscribed a shorter limitation than the statutory period only where prohibited by law. The Court of Appeals determined that Michigan’s general statutory limitation provision does not prohibit shorter contractual limitations on suits pertaining to private construction bonds. Consequently, the limitation provision was a valid defense to plaintiff’s suit.

II

Absent any statute to the contrary, the general rule followed by most courts has been to uphold provisions in private contracts limiting the time to bring suit where the limitation is reasonable, even though the period specified is less than the applicable statute of limitations. The Tom Thomas Organization, Inc v Reliance Ins Co, 396 Mich 588, 592; 242 NW2d 396 (1976). See also Barza v Metropolitan Life Ins Co, 281 Mich 532, 538; 275 NW 238 (1937); Turner v Fidelity & Casualty Co of New York, 112 Mich 425, 427; 70 NW 898 (1897).

This rule has been held to apply in contracts bonding the performance of building or construe[127]*127tion projects. See Burlew v Fidelity & Casualty Co of New York, 64 F2d 976, 977 (CA 6, 1933), cert den 290 US 686; 54 S Ct 122; 78 L Ed 591 (1933); Adams v Standard Accident Ins Co, 124 Cal App 393; 12 P2d 464 (1932); Cook v Heinbaugh, 202 Iowa 1002, 1003-1004; 210 NW 129 (1926); Lesher v United States Fidelity & Guaranty Co, 239 Ill 502, 511; 88 NE 208 (1909); McGarry v Seiz, 129 Ga 296, 299; 58 SE 856 (1907); Ausplund v Aetna Indemnity Co, 47 Or 10, 22; 81 P 577 (1905), reh den 47 Or 23; 82 P 12 (1905). See also Anno: Validity of contractual time period, shorter than statute of limitations, for bringing action, 6 ALR3d 1197; Anno: Validity of contractual limitation of time for bringing action, 121 ALR 758.

The boundaries of what is reasonable under the general rule require that the claimant have sufficient opportunity to investigate and file an action, that the time not be so short as to work a practical abrogation of the right of action, and that the action not be barred before the loss or damage can be ascertained. See Page County v Fidelity & Deposit Co of Maryland, 205 Iowa 798; 216 NW 957 (1927); Cook v Northern Pacific R Co, 32 ND 340; 155 NW 867 (1915); Sheard v United States Fidelity & Guaranty Co, 58 Wash 29; 107 P 1024 (1910), reh den 58 Wash 37; 109 P 276 (1910).

In the instant case, the bond secured claims for labor and materials brought by subcontractors in plaintiff Camelot’s position. However, the primary object of the bond contract was to protect the owner, Village Homes, Inc., against such claims:

"The purpose and only purpose of a labor and materials payment bond is to protect the owner against the claims of those who furnish' labor and materials to the contractor because, if he fails to pay these bills, mechanics liens can be filed against the owner and pay[128]*128ment enforced even though the owner had no direct dealing with the labor and materialmen.” Standard Accident Ins Co of Detroit v Rose, 314 Ky 233, 238; 234 SW2d 728 (1950).

Camelot was not a party to the payment bond. Rather, this contract was negotiated between the principal, general contractor Priestly, and the surety, St. Paul.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yaser Saidizand v. Gojet Airlines LLC
Michigan Court of Appeals, 2026
Toth v. Rocket Mtge., L.L.C.
2026 Ohio 926 (Ohio Court of Appeals, 2026)
Untitled Case
E.D. Michigan, 2026
Martaz Coleman v. Magni Industries Inc
Michigan Court of Appeals, 2026
Chrystal Robinson v. Quicken Loans Inc
Michigan Court of Appeals, 2026
Shaunte Johnson v. Best Buy Company Inc
Michigan Court of Appeals, 2025
Morgan v. Federal Express Corp.
114 F. Supp. 3d 434 (S.D. Texas, 2015)
Martinez-Santiago v. Public Storage
38 F. Supp. 3d 500 (D. New Jersey, 2014)
McFarland v. Century Truss Co.
518 F. Supp. 2d 977 (E.D. Michigan, 2007)
Clark v. DaimlerChrysler Corp.
706 N.W.2d 471 (Michigan Court of Appeals, 2005)
Rory v. Continental Insurance
703 N.W.2d 23 (Michigan Supreme Court, 2005)
Wineman v. Durkee Lakes Hunting & Fishing Club, Inc.
352 F. Supp. 2d 815 (E.D. Michigan, 2005)
Rory v. Continental Insurance
687 N.W.2d 304 (Michigan Court of Appeals, 2004)
Lewis v. Harper Hospital
241 F. Supp. 2d 769 (E.D. Michigan, 2002)
Wright v. DaimlerChrysler Corp.
220 F. Supp. 2d 832 (E.D. Michigan, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
301 N.W.2d 275, 410 Mich. 118, 1981 Mich. LEXIS 232, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camelot-excavating-co-inc-v-st-paul-fire-marine-ins-co-mich-1981.