Carney v. United States Guarantee Co.

177 A. 157, 168 Md. 134, 1935 Md. LEXIS 138
CourtCourt of Appeals of Maryland
DecidedJanuary 16, 1935
Docket[No. 85, October Term, 1934.]
StatusPublished
Cited by1 cases

This text of 177 A. 157 (Carney v. United States Guarantee Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carney v. United States Guarantee Co., 177 A. 157, 168 Md. 134, 1935 Md. LEXIS 138 (Md. 1935).

Opinion

Urner, J.,

delivered the opinion of the Court.

In a bill of interpleader the State Roads Commission alleged that it had a total of $8,231.96 as retained percentages payable under two completed contracts of Henry L. Maas & Sons, Inc., for the construction of highway *136 bridges over relocated tracks of the Pennsylvania Railroad at Elkton, Maryland; that before those balances became due, on final estimates, the affairs of the contracting company were placed in the hands' of receivers, who claimed the funds accruing under the contracts, and that a claim to the funds has also been preferred by the United States Guarantee Company, as surety on the contractor’s bonds, because of its liability thereon, to an amount in excess of the retained balances, for unpaid labor and material costs incurred in the constructions to which the contracts and bonds referred. Phrsuant to a decree of inter-pleader, the State Roads Commission paid into court the sum of- money involved in the conflicting claims of the receivers and the surety, and they were directed to litigate, in that proceeding, the question as to the proper disposition of the funds. Subsequently the labor and material creditors were made parties to the suit and filed answers asserting an equitable right to have their claims paid out of the fund in litigation. The final decree provided for the distribution of the funds among the labor and material claimants. From that decree the receivers of the contractor have appealed.

Included in the condition expressed in the bond, given in connection with each of the contracts, was the requirement that the contractor should “well and truly pay all and every person furnishing material or performing labor, in and about the construction of said bridge, all and every sum or sums of money due him, them or any of them for such labor and materials for which the contractor is liable.”

The bonds were given in compliance with the following provisions of section 6 of article 89R of the Code (as enacted by chapter 539 of the Acts of 1931), relating to bonds under contracts with the State Roads Commission, and of section 14 of article 90 of the Code, relating generally to bonds for public works:

“In no case shall any such bond be approved or accepted unless the obligators bind themselves therein to the payment of all just debts for labor and materials incurred by *137 the bidder in the construction and improvement of the road contracted for.” Code, art. 89B, sec 6.
“In all cases where any bond or undertaking, conditioned for the faithful performance of any contract for construction, installation or repair work,' is given to the State of Maryland, or any of its agencies, such bond or undertaking shall not be approved or accepted unless the obligors bind themselves therein to the payment of all just debts for labor and materials incurred, through subcontract or in any other manner, by or in behalf of the person, firm or corporation to whom such contract has been given, and who is named as principal in such recognizance, stipulation, bond or undertaking. Provided, that in the event that there is a liability to the State, or any agency thereof, under any such bond or undertaking, and also a liability thereunder for labor and materials, then the liability of the State shall be preferred, and shall be paid and discharged in full before any payment is made for or on account of the liability for labor or materials; and provided, further, that any suit or proceedings to enforce the liability under any such bond or undertaking for the payment of debts for labor or materials shall be brought in the name of the obligee named in such bond or undertaking, for the use and benefit pro rata of all creditors for labor or materials who may be entitled to claim thereunder, and shall be instituted not later than one year from the completion of the whole work covered by the contract and the acceptance thereof by the State, or its agency as aforesaid.” Code, art. 90, sec. 14.

The question for decision is whether, in view of the statutory provisions just quoted, and of the obligations thereby exacted, the unpaid balances of the contract cost of the work, to which the labor and material creditors contributed, should be appropriated to their claims in preference to those of the contractor’s general creditors represented by the receivers.

There have been numerous cases in the federal and state courts in which questions analogous to the one now *138 under consideration have been determined. In the great majority of such cases the conclusions support in principle the decree under review on this appeal. Relevant decisions under provisions substantially similar to the Maryland statutes are summarized in 76 A. L. R. 917, and in 40-42 U. S. Code Ann. pp. 111, 112, and include Henningsen v. U. S. Fidelity & Guaranty Co., 208 U. S. 404, 28 S. Ct. 389, 52 L. Ed. 547; Hardaway v. National Surety Co., 211 U. S. 552, 29 S. Ct. 202, 53 L. Ed. 321; Alfred Richards Brick Co. v. Rothwell, 18 App. D. C. 516; In re P. McGarry & Son (C. C. A.) 240 Fed. 400; Massachusetts Bonding & Ins. Co. v. Chouteau Trust Co. (C. C. A.) 264 Fed. 793; Belknap Hardware & Mfg. Co. v. Ohio River Contract Co. (C. C. A.) 271 Fed. 144; Central State Bank v. U. S. Fidelity & Guaranty Co. (C. C. A.) 9 Fed. (2nd) 326; Maryland Casualty Co. v. Dulaney Lumber Co. (C. C. A.) 23 Fed. (2nd) 378; Riverview State Bank v. Wentz (C. C. A.) 34 Fed. (2nd) 419; American Bank & T. Co. v. Langston, 180 Ark. 643, 22 S.W. (2nd) 381; Southern Surety Co. v. Merchants’ & Farmers’ Bank, 203 Ind. 173, 176 N. E. 846, 179 N. E. 327; Canton Exch. Bank v. Yazoo County, 144 Miss. 579, 109 So. 1; Massachusetts Bonding & Ins. Co. v. Ripley County Bank, 208 Mo. A.pp. 560, 237 S. W. 182; First Nat. Bank v. Pesha, 99 Neb. 785, 157 N. W. 924; Wasco County v. New England Equitable Ins. Co., 88 Or. 465, 172 P. 126; Haverstick v. Paul H. Sheirich, Inc., 304 Pa. 437, 155 A. 859; Maryland Casualty Co. v. Washington Nat. Bank, 92 Wash. 497, 159 P. 689; Barrett Bros. Co. v. St. Louis County, 165 Minn. 158, 206 N. W. 49.

Under the federal statute, commonly known as the Heard Act (U. S. Code, tit. 40, sec. 270, 40 U. S. Code Ann. sec. 270), which closely resembles the second of the Maryland statutory provisions above quoted, it was held, in the leading case of Henningsen v. U. S. Fidelity & Guaranty Co., supra, that the surety on the contractor’s bond, upon paying labor and material claims, as to which the contractor had defaulted, was entitled, by way of subrogation, and as against an assignee of the contractor, *139 to the unpaid balance due under the contract, so far as needed for the surety’s reimbursement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. A. D. Ingalls, Inc.
197 A.2d 214 (Supreme Court of New Hampshire, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
177 A. 157, 168 Md. 134, 1935 Md. LEXIS 138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carney-v-united-states-guarantee-co-md-1935.